Anugraha
Deedo IDDP-PUN-EBYRCompletion was pushed back 2 years and 1 month to Nov 2025, and that date has passed too; no MahaRERA orders on record; 80% of its units are booked.
Sadashiv Peth, Pune 411030 · by Avadhoot Constructions · 0% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 2 years and 1 month to Nov 2025, and that date has passed too
- This projectRegistered 25 Oct 2021, completion promised 31 Oct 2023, revised to 21 Nov 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100031495
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100031495 | 25 Oct 2021 | 31 Oct 2023 | 21 Nov 2025 | Avadhoot Constructions | Project page |
Documents53
3 documents held by Deedo, 50 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN Card00_Pan Card_Avadhoot Construction.pdf · uploaded 1 Oct 2021Source
Show all 53 documentsShow fewer documents
Legal
- Other02_POA Limaye_12_22.pdf · uploaded 1 Oct 2021Source
- OtherShirish Limaye_01_10.pdf · uploaded 1 Oct 2021Source
- OtherShirish Limaye_11_21.pdf · uploaded 1 Oct 2021Source
- OtherShirish Limaye_22_36.pdf · uploaded 1 Oct 2021Source
- Declaration Form B13_Anughraha_Declaration B.pdf · uploaded 1 Oct 2021Source
- Legal Title report1257_Legal Tital Report Form A_1.pdf · uploaded 23 Oct 2021Source
- Declaration Form B03 1257 Sadashiv peth Declaration B new.pdf · uploaded 19 Dec 2023Source
Migrated
- 1 PAN Card00_Pan Card_Avadhoot Construction.pdf · uploaded 1 Oct 2021Source
- 1 Details of encumbrances10_Anughraha_Encombrances Self Declaration format.pdf · uploaded 1 Oct 2021Source
- 1 Copy of Layout Approval (in case of layout)06_Anughraha_IOD Certificate.PDF · uploaded 1 Oct 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan 1.PDF · uploaded 1 Oct 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentPlan 2.PDF · uploaded 1 Oct 2021Source
- 3 Building Plan Approval / NA Order for plotted developmentplan 3.PDF · uploaded 1 Oct 2021Source
- 1 Commencement Certificates / NA Order for plotted development11_Anughraha_Commencement Certificate.pdf · uploaded 1 Oct 2021Source
- 1 Declaration about Commencement CertificateAnugraha_Format D.pdf · uploaded 1 Oct 2021Source
- 1 Declaration in FORM B13_Anughraha_Declaration B.pdf · uploaded 1 Oct 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)15_Anughraha_Architects Certificate_Form_01.pdf · uploaded 1 Oct 2021Source
- 1 Proforma of Allotment letter07_Anughraha_ ALLOTMENT LETTER.pdf · uploaded 1 Oct 2021Source
- 2 Proforma of Allotment letter_Anugraha_Flat_ Agreement.pdf · uploaded 1 Oct 2021Source
- 1 Other01_1257_Abhijit Limiaye_Sale Deed_01_12.pdf · uploaded 1 Oct 2021Source
- 2 Other02_1257_Abhijit Limiaye_Sale Deed_13_21.pdf · uploaded 1 Oct 2021Source
- 3 Other03_1257_Abhijit Limiaye_Sale Deed_22_29.PDf · uploaded 1 Oct 2021Source
- 4 Other01_POA Limaye_01_11.pdf · uploaded 1 Oct 2021Source
- 5 Other02_POA Limaye_12_22.pdf · uploaded 1 Oct 2021Source
- 6 OtherShirish Limaye_01_10.pdf · uploaded 1 Oct 2021Source
- 7 OtherShirish Limaye_11_21.pdf · uploaded 1 Oct 2021Source
- 8 OtherShirish Limaye_22_36.pdf · uploaded 1 Oct 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 AC Anugraha 30092021.pdf · uploaded 4 Oct 2021Source
- 1 Copy of the legal title report1257_Legal Tital Report Form A_1.pdf · uploaded 23 Oct 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Anugraha Form 02 Engineers Certificate Dec 21.pdf · uploaded 12 Mar 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A Engineers' Certificate_Anugraha_2A_Oct to Dec_2021.pdf · uploaded 12 Mar 2022Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold or booked inventory.pdf · uploaded 12 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 ANUGRAH FY 21-22.pdf · uploaded 21 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)02_Anugraha_Engineers Certificate_Form 2A_July to Sept_.pdf · uploaded 7 Nov 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Anugraha_Engineers Certificate_Form 2A_ March 22.pdf · uploaded 7 Nov 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)06_Anugraha_Eng Cert_2A March_2023.pdf · uploaded 7 Nov 2023Source
- 2 Declaration in FORM B03 1257 Sadashiv peth Declaration B new.pdf · uploaded 19 Dec 2023Source
- 2 Disclosure of sold/ booked inventory05_Avadhoot_Sold_Unsold_information.pdf · uploaded 19 Dec 2023View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Anugraha_Form_05_2022_2023__compressed.pdf · uploaded 19 Dec 2023Source
Technical
Technical (Architect)
- Document15_Anughraha_Architects Certificate_Form_01.pdf · uploaded 1 Oct 2021Source
Technical (Engineer)
- DocumentForm 2 Anugraha Form 02 Engineers Certificate Dec 21.pdf · uploaded 12 Mar 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 1257
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK, Shop15 units in all
- Address
- 1257, Sadashiv Peth, BHOPATKAR ROAD, SADASHIV PETHPIN 411030
- Village
- Pune (M Corp.), Pune City taluka
- Location
- 18.51188, 73.85213
- Land area for this project
- 401 sq m (4,320 sq ft)
- Permissible built-up area
- 902 sq m (9,708 sq ft)
- Sanctioned built-up area
- 902 sq m (9,708 sq ft)
- Designated bank account
- 203
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
1257, Sadashiv Peth
Boundaries
- North
- Road And Nimbalkar Talim
- South
- Mr Kaushik Society
- East
- Castle Of Mr Godbole
- West
- Castle Of Mr Padhye
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking15 units
12 of 15 units booked (80%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 30.19 sq m · 325 sq ft | 1 | 1 |
| 1BHK | 41.9 sq m · 451 sq ft | 1 | 0 |
| 1BHK | 42.55 sq m · 458 sq ft | 1 | 1 |
| 1RK | 29.17 sq m · 314 sq ft | 1 | 1 |
| 2BHK | 60.2 sq m · 648 sq ft | 2 | 2 |
| 2BHK | 67.92 sq m · 731 sq ft | 1 | 1 |
| 2BHK | 69.96 sq m · 753 sq ft | 3 | 3 |
| 2BHK | 70.23 sq m · 756 sq ft | 1 | 0 |
Show all 12 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 77.67 sq m · 836 sq ft | 1 | 1 |
| 2BHK | 91.51 sq m · 985 sq ft | 1 | 1 |
| Shop | 62.06 sq m · 668 sq ft | 1 | 1 |
| Shop | 64.57 sq m · 695 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shailesh Salehittal | — |
| Chartered accountant | Mahesh Ankush Ghare | — |
| Engineer | Parag S. Sura | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Sadashiv Peth
- Anika EleganceRERA PM1260002503060
- GulmoharRERA PR1260002501351
- The CapitalRERA PM1260002501067
- LaxminiwasRERA P52100080012
- ImperiaRERA P52100078314
- Nirman AnamikaRERA P52100076906
- PremanandRERA P52100055780
- YashwantRERA P52100052140
All 38 projects in Sadashiv Peth · Compare Anugraha with another project