Avadhoot Constructions
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 3 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kapil SankalpP52100006505 | Peth | 2017 | Not reported | 31 Mar 2019 | 30 Sep 2020 | +18 months |
| Anitakunj Hsg Soc LtdP52100028701 | Kothrud | 2021 | Not reported | 30 Dec 2023 | 6 Mar 2025 | +15 months |
| AnugrahaP52100031495 | Pune (M Corp.) | 2021 | Not reported | 31 Oct 2023 | 21 Nov 2025 | +25 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 25 months, for Anugraha (P52100031495).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology