Deedo IDDD-4FPAOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 35 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kapil SankalpP52100006505 | Peth | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Anitakunj Hsg Soc LtdP52100028701 | Kothrud | Certificate Signed | 30 Dec 2023 | 6 Mar 2025 | +35 mo* |
| AnugrahaP52100031495 | Sadashiv Peth | Certificate Signed | 31 Oct 2023 | 21 Nov 2025 | +37 mo* |
Avadhoot Constructions, in questions
Does Avadhoot Constructions finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 35 mo late. Across Maharashtra, 73% kept their date.
How many projects has Avadhoot Constructions registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Avadhoot Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.