Avadhoot Constructions

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 3 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kapil SankalpP52100006505Peth2017Not reported31 Mar 201930 Sep 2020+18 months
Anitakunj Hsg Soc LtdP52100028701Kothrud2021Not reported30 Dec 20236 Mar 2025+15 months
AnugrahaP52100031495Pune (M Corp.)2021Not reported31 Oct 202321 Nov 2025+25 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kapil Sankalp+18 mo
  • Anitakunj Hsg Soc Ltd+15 mo
  • Anugraha+25 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 25 months, for Anugraha (P52100031495).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology