Others · 5 buildings · 546 unitsRERA P52100047662

Infinity Avana

Deedo IDDP-PUN-0W9W

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 60% of its units are booked.

Punawale, Pune 411033 · Property rates in Punawale · by Tulip Infra

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales60% booked329 of 546 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 17 Nov 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100047662
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004766217 Nov 202231 Dec 202630 Apr 2027Tulip InfraProject page
Documents353

1 document held by Deedo, 352 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardTulip Infra - Pan Card.pdf · uploaded 11 Oct 2022Source
  • OthersFormat B Opening of RERA Designated Bank Account.pdf · uploaded 9 Jul 2025Source

Legal

  • Declaration Form BForm B Affidavit Cum Declaration-Infra.pdf · uploaded 17 Oct 2022Source
  • Legal Title reportSEARCH 1.pdf · uploaded 18 Oct 2022Source
  • Legal Title reportSEARCH 2 (1).pdf · uploaded 18 Oct 2022Source

Migrated

  • 1 PAN CardTulip Infra - Pan Card.pdf · uploaded 11 Oct 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Certificate no loan.pdf · uploaded 17 Oct 2022Source
Show all 353 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalEncumbrance Certificate No letigation.pdf · uploaded 17 Oct 2022Source
  • 1 Copy of Layout Approval (in case of layout)scan Plan 0001.pdf · uploaded 17 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentscan plan 002.pdf · uploaded 17 Oct 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate-Infra.pdf · uploaded 17 Oct 2022Source
  • 1 Declaration in FORM BForm B Affidavit Cum Declaration-Infra.pdf · uploaded 17 Oct 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate-Tulip Infra.pdf · uploaded 17 Oct 2022Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 17 Oct 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report - Allotment Letter.pdf · uploaded 17 Oct 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report - Agreement.pdf · uploaded 17 Oct 2022Source
  • 1 Copy of the legal title reportSEARCH 1.pdf · uploaded 18 Oct 2022Source
  • 2 Copy of the legal title reportSEARCH 2 (1).pdf · uploaded 18 Oct 2022Source
  • 1 Proforma of Agreement for saleDRAFT AGREEMENT - AS PER RERA - FOR RERA REGISTRATION.pdf · uploaded 21 Oct 2022Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 21 Oct 2022Source
  • 1 Declaration about Commencement CertificateDeclaration -Commencement Certificate.pdf · uploaded 1 Nov 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration- Separate Bank Account- Infra.pdf · uploaded 1 Nov 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Rera Engineers Certificate-Infra_compressed.pdf · uploaded 3 Nov 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1.pdf · uploaded 3 Nov 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentscan 001.pdf · uploaded 21 Dec 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentscan 002.pdf · uploaded 21 Dec 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentscan 003.pdf · uploaded 21 Dec 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentscan 004.pdf · uploaded 21 Dec 2022Source
  • 6 Building Plan Approval / NA Order for plotted developmentscan 005.pdf · uploaded 21 Dec 2022Source
  • 7 Building Plan Approval / NA Order for plotted developmentscan 006.pdf · uploaded 21 Dec 2022Source
  • 8 Building Plan Approval / NA Order for plotted developmentscan 007.pdf · uploaded 21 Dec 2022Source
  • 9 Building Plan Approval / NA Order for plotted developmentscan 009.pdf · uploaded 21 Dec 2022Source
  • 10 Building Plan Approval / NA Order for plotted developmentscan 008.pdf · uploaded 21 Dec 2022Source
  • 11 Building Plan Approval / NA Order for plotted developmentscan 010.pdf · uploaded 21 Dec 2022Source
  • 12 Building Plan Approval / NA Order for plotted developmentscan 011.pdf · uploaded 21 Dec 2022Source
  • 13 Building Plan Approval / NA Order for plotted developmentscan 012.pdf · uploaded 21 Dec 2022Source
  • 14 Building Plan Approval / NA Order for plotted developmentscan 013.pdf · uploaded 21 Dec 2022Source
  • 15 Building Plan Approval / NA Order for plotted developmentscan 014.pdf · uploaded 21 Dec 2022Source
  • 16 Building Plan Approval / NA Order for plotted developmentscan 015.pdf · uploaded 21 Dec 2022Source
  • 17 Building Plan Approval / NA Order for plotted developmentscan 016.pdf · uploaded 21 Dec 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 21 Dec 2022Source
  • 2 Declaration about Commencement CertificateCommencement Certificate - Declaration.pdf · uploaded 21 Dec 2022Source
  • 2 Proforma of Agreement for saleAgreement for sale-Infinity Avana.pdf · uploaded 28 Dec 2022Source
  • 2 Deviation Report with respect to model copy of AgreementDEVIATION REPORT-TULIP INFRA.pdf · uploaded 2 Jan 2023Source
  • 18 Building Plan Approval / NA Order for plotted developmentscan 001.pdf · uploaded 23 Feb 2023Source
  • 19 Building Plan Approval / NA Order for plotted developmentscan 002.pdf · uploaded 23 Feb 2023Source
  • 20 Building Plan Approval / NA Order for plotted developmentscan 003.pdf · uploaded 23 Feb 2023Source
  • 21 Building Plan Approval / NA Order for plotted developmentscan 004.pdf · uploaded 23 Feb 2023Source
  • 22 Building Plan Approval / NA Order for plotted developmentscan 005.pdf · uploaded 23 Feb 2023Source
  • 23 Building Plan Approval / NA Order for plotted developmentscan 006.pdf · uploaded 23 Feb 2023Source
  • 24 Building Plan Approval / NA Order for plotted developmentscan 007.pdf · uploaded 23 Feb 2023Source
  • 25 Building Plan Approval / NA Order for plotted developmentscan 008.pdf · uploaded 23 Feb 2023Source
  • 26 Building Plan Approval / NA Order for plotted developmentscan 009.pdf · uploaded 23 Feb 2023Source
  • 27 Building Plan Approval / NA Order for plotted developmentscan 010.pdf · uploaded 23 Feb 2023Source
  • 28 Building Plan Approval / NA Order for plotted developmentscan 011.pdf · uploaded 23 Feb 2023Source
  • 29 Building Plan Approval / NA Order for plotted developmentscan 012.pdf · uploaded 23 Feb 2023Source
  • 30 Building Plan Approval / NA Order for plotted developmentscan 013.pdf · uploaded 23 Feb 2023Source
  • 31 Building Plan Approval / NA Order for plotted developmentscan 014.pdf · uploaded 23 Feb 2023Source
  • 32 Building Plan Approval / NA Order for plotted developmentscan 015.pdf · uploaded 23 Feb 2023Source
  • 33 Building Plan Approval / NA Order for plotted developmentscan 016.pdf · uploaded 23 Feb 2023Source
  • 34 Building Plan Approval / NA Order for plotted developmentscan 017.pdf · uploaded 23 Feb 2023Source
  • 35 Building Plan Approval / NA Order for plotted developmentscan 018.pdf · uploaded 23 Feb 2023Source
  • 36 Building Plan Approval / NA Order for plotted developmentscan 019.pdf · uploaded 23 Feb 2023Source
  • 37 Building Plan Approval / NA Order for plotted developmentscan 019.pdf · uploaded 23 Feb 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 23 Feb 2023Source
  • 3 Declaration about Commencement CertificateDeclaration About Commencement Certificate-infra.pdf · uploaded 3 Mar 2023Source
  • 38 Building Plan Approval / NA Order for plotted developmentScan 10.pdf · uploaded 14 Mar 2023Source
  • 39 Building Plan Approval / NA Order for plotted developmentScan 11.pdf · uploaded 14 Mar 2023Source
  • 40 Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 18 Sep 2023Source
  • 41 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 18 Sep 2023Source
  • 42 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 18 Sep 2023Source
  • 43 Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 18 Sep 2023Source
  • 44 Building Plan Approval / NA Order for plotted developmentPlan 5.pdf · uploaded 18 Sep 2023Source
  • 45 Building Plan Approval / NA Order for plotted developmentPlan 6.pdf · uploaded 18 Sep 2023Source
  • 46 Building Plan Approval / NA Order for plotted developmentPlan 7.pdf · uploaded 18 Sep 2023Source
  • 47 Building Plan Approval / NA Order for plotted developmentPlan 8.pdf · uploaded 18 Sep 2023Source
  • 48 Building Plan Approval / NA Order for plotted developmentPlan 9.pdf · uploaded 18 Sep 2023Source
  • 49 Building Plan Approval / NA Order for plotted developmentPlan 10.pdf · uploaded 18 Sep 2023Source
  • 50 Building Plan Approval / NA Order for plotted developmentPlan 11.pdf · uploaded 18 Sep 2023Source
  • 51 Building Plan Approval / NA Order for plotted developmentPlan 12.pdf · uploaded 18 Sep 2023Source
  • 52 Building Plan Approval / NA Order for plotted developmentPlan 13.pdf · uploaded 18 Sep 2023Source
  • 53 Building Plan Approval / NA Order for plotted developmentPlan 14.pdf · uploaded 18 Sep 2023Source
  • 54 Building Plan Approval / NA Order for plotted developmentPlan 15.pdf · uploaded 18 Sep 2023Source
  • 55 Building Plan Approval / NA Order for plotted developmentPlan 16.pdf · uploaded 18 Sep 2023Source
  • 56 Building Plan Approval / NA Order for plotted developmentPlan 17.pdf · uploaded 18 Sep 2023Source
  • 57 Building Plan Approval / NA Order for plotted developmentPlan 18.pdf · uploaded 18 Sep 2023Source
  • 58 Building Plan Approval / NA Order for plotted developmentPlan 19.pdf · uploaded 18 Sep 2023Source
  • 59 Building Plan Approval / NA Order for plotted developmentPlan 20.pdf · uploaded 18 Sep 2023Source
  • 60 Building Plan Approval / NA Order for plotted developmentPlan 21.pdf · uploaded 18 Sep 2023Source
  • 61 Building Plan Approval / NA Order for plotted developmentPlan 22.pdf · uploaded 18 Sep 2023Source
  • 62 Building Plan Approval / NA Order for plotted developmentPlan 23.pdf · uploaded 18 Sep 2023Source
  • 63 Building Plan Approval / NA Order for plotted developmentPlan 24.pdf · uploaded 18 Sep 2023Source
  • 64 Building Plan Approval / NA Order for plotted developmentPlan 25.pdf · uploaded 18 Sep 2023Source
  • 65 Building Plan Approval / NA Order for plotted developmentPlan 26.pdf · uploaded 18 Sep 2023Source
  • 66 Building Plan Approval / NA Order for plotted developmentPlan 27.pdf · uploaded 18 Sep 2023Source
  • 4 Declaration about Commencement CertificateCommencemet Certificate.pdf · uploaded 18 Sep 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentCommencemet Certificate.pdf · uploaded 10 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Pi7_Tulip_infra_FY_22-23_Q4.pdf · uploaded 25 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Pi7_Tulip_Infra_FY_23-24_Q1.pdf · uploaded 25 Oct 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form -1 Architect Certificate Q4 FY 2022-23.pdf · uploaded 24 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form -1 Q1.pdf · uploaded 24 Nov 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate -Q2.pdf · uploaded 24 Nov 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q4 FY 2022-23.pdf · uploaded 24 Nov 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q1.pdf · uploaded 24 Nov 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate IA Q2.pdf · uploaded 24 Nov 2023Source
  • 1 Disclosure of sold/ booked inventoryPromoters Disclosure Q4 FY 2022-23.pdf · uploaded 24 Nov 2023Source
  • 2 Disclosure of sold/ booked inventoryPromoters Disclosure IA Q1.pdf · uploaded 24 Nov 2023Source
  • 3 Disclosure of sold/ booked inventoryPromoters Disclosure Q2.pdf · uploaded 24 Nov 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form 3 - Infinity Avana Q2.pdf · uploaded 24 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Annual Report - Tulip Infra FY 22-23.pdf · uploaded 10 Jan 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1 Q3.pdf · uploaded 12 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Infra Registration Qtr 3.pdf · uploaded 12 Feb 2024Source
  • 4 Disclosure of sold/ booked inventoryPromoters Disclosure Unit Wise Qtr 3 F.pdf · uploaded 12 Feb 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Infinity Avana F.pdf · uploaded 12 Feb 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Infinity Avana Architect Certificate 07-03-202.pdf · uploaded 8 Mar 2024Source
  • 67 Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 27 Mar 2024Source
  • 68 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 27 Mar 2024Source
  • 69 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 27 Mar 2024Source
  • 70 Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 27 Mar 2024Source
  • 71 Building Plan Approval / NA Order for plotted developmentPlan 5.pdf · uploaded 27 Mar 2024Source
  • 72 Building Plan Approval / NA Order for plotted developmentPlan 6.pdf · uploaded 27 Mar 2024Source
  • 73 Building Plan Approval / NA Order for plotted developmentPlan 7.pdf · uploaded 27 Mar 2024Source
  • 74 Building Plan Approval / NA Order for plotted developmentPlan 8.pdf · uploaded 27 Mar 2024Source
  • 75 Building Plan Approval / NA Order for plotted developmentPlan 9.pdf · uploaded 27 Mar 2024Source
  • 76 Building Plan Approval / NA Order for plotted developmentPlan 10.pdf · uploaded 27 Mar 2024Source
  • 77 Building Plan Approval / NA Order for plotted developmentPlan 11.pdf · uploaded 27 Mar 2024Source
  • 78 Building Plan Approval / NA Order for plotted developmentPlan 12.pdf · uploaded 27 Mar 2024Source
  • 79 Building Plan Approval / NA Order for plotted developmentPlan 13.pdf · uploaded 27 Mar 2024Source
  • 80 Building Plan Approval / NA Order for plotted developmentPlan 14.pdf · uploaded 27 Mar 2024Source
  • 81 Building Plan Approval / NA Order for plotted developmentPlan 15.pdf · uploaded 27 Mar 2024Source
  • 82 Building Plan Approval / NA Order for plotted developmentPlan 16.pdf · uploaded 27 Mar 2024Source
  • 83 Building Plan Approval / NA Order for plotted developmentPlan 17.pdf · uploaded 27 Mar 2024Source
  • 84 Building Plan Approval / NA Order for plotted developmentPlan 18.pdf · uploaded 27 Mar 2024Source
  • 85 Building Plan Approval / NA Order for plotted developmentPlan 19.pdf · uploaded 27 Mar 2024Source
  • 86 Building Plan Approval / NA Order for plotted developmentPlan 20.pdf · uploaded 27 Mar 2024Source
  • 87 Building Plan Approval / NA Order for plotted developmentPlan 21.pdf · uploaded 27 Mar 2024Source
  • 88 Building Plan Approval / NA Order for plotted developmentPlan 22.pdf · uploaded 27 Mar 2024Source
  • 89 Building Plan Approval / NA Order for plotted developmentPlan 23.pdf · uploaded 27 Mar 2024Source
  • 90 Building Plan Approval / NA Order for plotted developmentPlan 24.pdf · uploaded 27 Mar 2024Source
  • 91 Building Plan Approval / NA Order for plotted developmentPlan 25.pdf · uploaded 27 Mar 2024Source
  • 92 Building Plan Approval / NA Order for plotted developmentPlan 26.pdf · uploaded 27 Mar 2024Source
  • 93 Building Plan Approval / NA Order for plotted developmentPlan 27.pdf · uploaded 27 Mar 2024Source
  • 94 Building Plan Approval / NA Order for plotted developmentplan 28.pdf · uploaded 27 Mar 2024Source
  • 95 Building Plan Approval / NA Order for plotted developmentPlan 29.pdf · uploaded 27 Mar 2024Source
  • 96 Building Plan Approval / NA Order for plotted developmentPlan 30.pdf · uploaded 27 Mar 2024Source
  • 5 Commencement Certificates / NA Order for plotted developmentCommencement Certificate 18-3-24.pdf · uploaded 27 Mar 2024Source
  • 5 Declaration about Commencement CertificateFormat D - Declaration of Commencement Certificate 27-03-2024.pdf · uploaded 27 Mar 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 23-24 Q4 Infinity Avana.pdf · uploaded 28 May 2024Source
  • 5 Disclosure of sold/ booked inventoryPromoters Disclosure Unit Wise Qtr 4.pdf · uploaded 28 May 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 23-24 Q4 Infinity Avana.pdf · uploaded 28 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A FY 23-24 Infinity Avana.pdf · uploaded 7 Jun 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY 2024-25 Q1.pdf · uploaded 11 Jul 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Infra Registration Qtr 1.pdf · uploaded 2 Aug 2024Source
  • 6 Disclosure of sold/ booked inventoryPromoters Disclosure Unit Wise Qtr 1.pdf · uploaded 2 Aug 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 24-25 Q1 Infinity Avana.pdf · uploaded 2 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Avana- Form 1 Qtr 2 Resize.pdf · uploaded 18 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q2 Resize.pdf · uploaded 18 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Avana Form 2 Qtr 2.pdf · uploaded 18 Dec 2024Source
  • 2 Disclosure of sold/ booked inventoryPromoters Disclosure Avana - Qtr 2 Resize.pdf · uploaded 18 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Qtr 3 FY 2024-25.pdf · uploaded 18 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 for Q3 FY 2024-25 RESIZE.pdf · uploaded 18 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Infra Registration Qtr 3.pdf · uploaded 18 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryPromoters Disclosure Unit Wise Qtr 3 Resize.pdf · uploaded 18 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)TI_Form-5_FY2023-24.pdf · uploaded 5 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect's Certificate 21-04-2025- Qtr 4_11zon.pdf · uploaded 2 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Avana Form 3_11zon.pdf · uploaded 2 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Infra Registration Qtr 4.pdf · uploaded 3 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Engineer Certificate for Quality Assurance Infinity-Avana.pdf · uploaded 3 May 2025Source
  • Withdrawal Update Form 1FORM 1 Q1 FY 2025-26.pdf · uploaded 8 Aug 2025Source
  • Withdrawal Update Form 2FORM 2 Q1 FY 2025-26.pdf · uploaded 8 Aug 2025Source
  • Withdrawal Update Form 3FORM 3 Q1 FY 2025-26.pdf · uploaded 8 Aug 2025Source
  • Withdrawal Update Form 1FORM 1 Q1 FY 2025-26.pdf · uploaded 6 Sep 2025Source
  • Withdrawal Update Form 2FORM 2 Q1 FY 2025-26.pdf · uploaded 6 Sep 2025Source
  • Withdrawal Update Form 3FORM 3 Q1 FY 2025-26.pdf · uploaded 6 Sep 2025Source
  • Withdrawal Update Form 1Form 1 - Final.pdf · uploaded 1 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 (1).pdf · uploaded 1 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate FY 2025-26 Q2.pdf · uploaded 1 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - Final.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - Final.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - Final.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 (1).pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 (1).pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 (1).pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate FY 2025-26 Q2.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate FY 2025-26 Q2.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate FY 2025-26 Q2.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - Final.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - Final.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - Final.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - Final.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 (1).pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 (1).pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 (1).pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 (1).pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate FY 2025-26 Q2.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate FY 2025-26 Q2.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate FY 2025-26 Q2.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate FY 2025-26 Q2.pdf · uploaded 4 Nov 2025Source
  • Form 5 (FY 2024-2025)Form 5 Annual Report - Tulip Infra- Avana FY 24-25.pdf · uploaded 2 Feb 2026Source
  • Withdrawal Update Form 1Form 1 for FY 2025 26 Q3.pdf · uploaded 10 Feb 2026Source
  • Withdrawal Update Form 2Form 2 for FY 2025 26 Q3.pdf · uploaded 10 Feb 2026Source
  • Withdrawal Update Form 3Form 3 for FY 2025 26 Q3 resize.pdf · uploaded 10 Feb 2026Source
  • Form 2A (FY 2024-2025)Form 2A for FY 2024-25 Avana final.pdf · uploaded 10 Mar 2026Source
  • Form 2A (FY 2025-2026)Form 2A for FY 2025-26 final.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 1Form 1 for FY 2025 26 Q4 final.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 2Form 2 for FY 2025-26 Q4 Avana Final.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 3Form 3 for FY2025-26 Q4 Infinity Avana final.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 1Form 1 For FY 2026-27 Q1 Final.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 2Form 2 For FY 2026-27 Q1 Final.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 3Form 3 For FY 2026-27 Q1 Final.pdf · uploaded 29 Jul 2026Source

Technical

  • Documentscan Plan 0001.pdf · uploaded 17 Oct 2022Source
  • Documentscan plan 002.pdf · uploaded 17 Oct 2022Source
  • Documentscan 001.pdf · uploaded 21 Dec 2022Source
  • Documentscan 002.pdf · uploaded 21 Dec 2022Source
  • Documentscan 003.pdf · uploaded 21 Dec 2022Source
  • Documentscan 004.pdf · uploaded 21 Dec 2022Source
  • Documentscan 005.pdf · uploaded 21 Dec 2022Source
  • Documentscan 006.pdf · uploaded 21 Dec 2022Source
  • Documentscan 007.pdf · uploaded 21 Dec 2022Source
  • Documentscan 009.pdf · uploaded 21 Dec 2022Source
  • Documentscan 008.pdf · uploaded 21 Dec 2022Source
  • Documentscan 010.pdf · uploaded 21 Dec 2022Source
  • Documentscan 011.pdf · uploaded 21 Dec 2022Source
  • Documentscan 012.pdf · uploaded 21 Dec 2022Source
  • Documentscan 013.pdf · uploaded 21 Dec 2022Source
  • Documentscan 014.pdf · uploaded 21 Dec 2022Source
  • Documentscan 015.pdf · uploaded 21 Dec 2022Source
  • Documentscan 016.pdf · uploaded 21 Dec 2022Source
  • Documentscan 007.pdf · uploaded 23 Feb 2023Source
  • Documentscan 008.pdf · uploaded 23 Feb 2023Source
  • Documentscan 009.pdf · uploaded 23 Feb 2023Source
  • Documentscan 010.pdf · uploaded 23 Feb 2023Source
  • Documentscan 011.pdf · uploaded 23 Feb 2023Source
  • Documentscan 012.pdf · uploaded 23 Feb 2023Source
  • Documentscan 013.pdf · uploaded 23 Feb 2023Source
  • Documentscan 014.pdf · uploaded 23 Feb 2023Source
  • Documentscan 015.pdf · uploaded 23 Feb 2023Source
  • Documentscan 016.pdf · uploaded 23 Feb 2023Source
  • Documentscan 017.pdf · uploaded 23 Feb 2023Source
  • Documentscan 018.pdf · uploaded 23 Feb 2023Source
  • Documentscan 019.pdf · uploaded 23 Feb 2023Source
  • Documentscan 019.pdf · uploaded 23 Feb 2023Source
  • Documentscan 001.pdf · uploaded 23 Feb 2023Source
  • Documentscan 002.pdf · uploaded 23 Feb 2023Source
  • Documentscan 003.pdf · uploaded 23 Feb 2023Source
  • Documentscan 004.pdf · uploaded 23 Feb 2023Source
  • Documentscan 005.pdf · uploaded 23 Feb 2023Source
  • Documentscan 006.pdf · uploaded 23 Feb 2023Source
  • DocumentScan 10.pdf · uploaded 14 Mar 2023Source
  • DocumentScan 11.pdf · uploaded 14 Mar 2023Source
  • DocumentPlan 1.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 2.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 3.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 4.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 5.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 6.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 7.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 8.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 9.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 10.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 11.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 12.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 13.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 14.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 15.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 16.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 17.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 18.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 19.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 20.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 21.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 22.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 25.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 26.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 27.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 23.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 24.pdf · uploaded 18 Sep 2023Source
  • DocumentPlan 1.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 2.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 3.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 4.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 5.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 6.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 7.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 8.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 9.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 10.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 11.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 12.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 13.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 14.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 15.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 16.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 17.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 18.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 19.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 20.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 21.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 22.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 23.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 24.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 25.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 26.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 27.pdf · uploaded 27 Mar 2024Source
  • Documentplan 28.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 29.pdf · uploaded 27 Mar 2024Source
  • DocumentPlan 30.pdf · uploaded 27 Mar 2024Source
  • OthersFormat B - Infinity Avana.pdf · uploaded 11 Aug 2025Source
  • DocumentLayout Plan.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 2.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 3.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 4.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 5.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 6.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 7.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 8.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 9.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 10.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 11.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 12.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 13.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 14.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 15.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 16.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 17.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 18.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 19.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 20.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 21.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 22.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 23.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 24.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 25.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 26.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 27.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 28.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 29.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 30.pdf · uploaded 2 May 2026Source
  • DocumentPage No- 31.pdf · uploaded 2 May 2026Source
  • OthersDECLARATION ABOUT COMMENCEMENT CERTIFICATE-AVANA.pdf · uploaded 2 May 2026Source
  • DocumentPlan 01 ( Layout Plan ) - Highlighted.pdf · uploaded 23 Jun 2026Source
  • DocumentPlan 02 ( Basement-1 and Basement-2 ) - Highlighted.pdf · uploaded 23 Jun 2026Source
  • DocumentPlan 03 ( Ground Floor ) - Highlighted.pdf · uploaded 23 Jun 2026Source
  • DocumentPlan 04 ( Mezzanine ) - Highlighted.pdf · uploaded 23 Jun 2026Source

Technical (Architect)

  • DocumentArchitect Certificate Avana- Form 1 Qtr 2 Resize.pdf · uploaded 18 Dec 2024Source
  • DocumentForm 1 Architect Certificate Qtr 3 FY 2024-25.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 1 Architect's Certificate 21-04-2025- Qtr 4_11zon.pdf · uploaded 2 May 2025Source
  • DocumentForm 1 For FY 2026-27 Q1 Final.pdf · uploaded 29 Jul 2026Source

Technical (Engineer)

  • DocumentEngineer Certificate - Avana Form 2 Qtr 2.pdf · uploaded 18 Dec 2024Source
  • DocumentForm 2 Engineer Certificate Infra Registration Qtr 3.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 2 Engineer Certificate Infra Registration Qtr 4.pdf · uploaded 3 May 2025Source
  • DocumentForm 2 For FY 2026-27 Q1 Final.pdf · uploaded 29 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 6/10, 6/3

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
3BHK, 4BHK, Office space, Shop, Amenity, 2BHK, Guest Room, 1BHK546 units in all
Address
Survey Nos. 6/2, 6/3, 6/4, 6/6, 6/7, 6/8, 6/9 And 6/10, At Punawale, Punawale, PunawalePIN 411033
Village
Punawale, Mulshi taluka
Land area for this project
12,800 sq m (1,37,778 sq ft)
Permissible built-up area
67,130 sq m (7,22,581 sq ft)
Sanctioned built-up area
67,130 sq m (7,22,581 sq ft)
Recreational open space
1,238 sq m (13,325 sq ft)
Designated bank account
220
Developed in phases
Yes

Survey, CTS, gat or plot numbers

6/106/36/46/66/76/86/9SURVEY NOS. 6/2

Land as published on MahaRERA's project page

SURVEY NOS. 6/2, 6/3, 6/4, 6/6, 6/7, 6/8, 6/9 AND 6/10, AT PUNAWALE

Boundaries

North
Survey No 1
South
18 Mtr Dp Road
East
Ravet Aundh Brt Road
West
Survey No 6 Hissa No 5

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking546 units

329 of 546 units booked (60%), as the promoter reported to MahaRERA

3BHK · 271 units4BHK · 52 unitsOffice space · 1 unitShop · 53 unitsAmenity · 0 units2BHK · 128 unitsGuest Room · 1 unit1BHK · 40 units
BuildingTypeCarpet areaUnitsBooked
A Wing3BHK88.92 sq m · 957 sq ft2723
A Wing3BHK94.02 sq m · 1,012 sq ft2724
A Wing3BHK102.89 sq m · 1,107 sq ft54
A Wing3BHK103.01 sq m · 1,109 sq ft2717
A Wing4BHK122.77 sq m · 1,321 sq ft2214
A WingOffice space541.85 sq m · 5,832 sq ft10
A WingShop25.27 sq m · 272 sq ft10
A WingShop27.58 sq m · 297 sq ft10
Show all 72 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A WingShop27.8 sq m · 299 sq ft20
A WingShop29.2 sq m · 314 sq ft10
A WingShop29.89 sq m · 322 sq ft20
A WingShop31.13 sq m · 335 sq ft10
A WingShop31.56 sq m · 340 sq ft10
A WingShop33.26 sq m · 358 sq ft10
A WingShop33.65 sq m · 362 sq ft10
A WingShop34.55 sq m · 372 sq ft10
A WingShop35.53 sq m · 382 sq ft10
A WingShop36.07 sq m · 388 sq ft10
A WingShop36.71 sq m · 395 sq ft10
A WingShop37.15 sq m · 400 sq ft50
A WingShop39.14 sq m · 421 sq ft10
A WingShop41.43 sq m · 446 sq ft10
A WingShop43.69 sq m · 470 sq ft10
A WingShop44.38 sq m · 478 sq ft20
A WingShop45.59 sq m · 491 sq ft10
A WingShop49.02 sq m · 528 sq ft10
A WingShop49.04 sq m · 528 sq ft10
A WingShop50.67 sq m · 545 sq ft10
A WingShop52.3 sq m · 563 sq ft10
A WingShop59.77 sq m · 643 sq ft10
A WingShop62.78 sq m · 676 sq ft10
A WingShop63.27 sq m · 681 sq ft10
A WingShop65.74 sq m · 708 sq ft10
B Wing3BHK88.92 sq m · 957 sq ft3029
B Wing3BHK94.12 sq m · 1,013 sq ft3028
B Wing3BHK103.56 sq m · 1,115 sq ft3027
B Wing4BHK122.76 sq m · 1,321 sq ft10
B Wing4BHK122.96 sq m · 1,324 sq ft2926
CommercialAmenity—00
CommercialAmenity—00
C Wing2BHK62.35 sq m · 671 sq ft265
C Wing2BHK64.42 sq m · 693 sq ft260
C Wing2BHK65.67 sq m · 707 sq ft43
C Wing3BHK84.12 sq m · 905 sq ft2214
C Wing3BHK89.98 sq m · 969 sq ft2518
C WingGuest Room102.96 sq m · 1,108 sq ft10
C WingShop34.71 sq m · 374 sq ft10
C WingShop39.63 sq m · 427 sq ft10
C WingShop40.88 sq m · 440 sq ft20
C WingShop41.32 sq m · 445 sq ft10
C WingShop48.56 sq m · 523 sq ft10
C WingShop53.51 sq m · 576 sq ft20
C WingShop55.24 sq m · 595 sq ft10
C WingShop62.92 sq m · 677 sq ft10
D Wing2BHK62.29 sq m · 670 sq ft2926
D Wing2BHK62.35 sq m · 671 sq ft10
D Wing2BHK62.38 sq m · 671 sq ft2919
D Wing2BHK64.42 sq m · 693 sq ft10
D Wing2BHK65.71 sq m · 707 sq ft55
D Wing2BHK74.16 sq m · 798 sq ft72
D Wing3BHK84.2 sq m · 906 sq ft2522
D Wing3BHK89.96 sq m · 968 sq ft2323
D WingShop35.47 sq m · 382 sq ft10
D WingShop38.67 sq m · 416 sq ft10
D WingShop39.47 sq m · 425 sq ft10
D WingShop40.88 sq m · 440 sq ft10
D WingShop42.76 sq m · 460 sq ft10
D WingShop43.37 sq m · 467 sq ft10
D WingShop47.8 sq m · 515 sq ft10
D WingShop55.25 sq m · 595 sq ft10
D WingShop63.88 sq m · 688 sq ft10
MHADA Wing1BHK42.71 sq m · 460 sq ft400

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectLandmark Design Group—
Chartered accountantS U N S V G & Associates—
Chartered accountantV S A P & Company—
EngineerBhimrao Tengle—
EngineerVidyanand Ashok Kyadar—
OtherGolden Elight Bildcon—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Punawale

All 190 projects in Punawale · Compare Infinity Avana with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology