C Wing · Infinity Avana
Punawale · RERA P52100047662
IDBLD_03176032 floorsExtended 4 mo
32Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 31 Dec 2026
40 of 114Units bookedMahaRERA project page
Floors
32 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100047662 · registered 17 Nov 2022
- Promised completion
- 31 Dec 2026
- Revised completion
- 30 Apr 2027
- Sanctioned habitable floors
- 32
- ProjectId
- 38,260
- ProjectName
- INFINITY AVANA
- TotalUnitCount
- 129
- ProjectBuildingId
- 1,48,247
- BuildingNameNumber
- C WING
- FsiWithSanctionSqmts
- 35
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 119
- ProjectRegistartionNo
- P52100047662
- ProjectBuildingWingsId
- 1,51,664
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 10
- AdvertisedBuildingNameNumber
- C WING
- NoOfBuildingWingFloorProposed
- 35
- NoOfBuildingWingFloorHabitable
- 32
- NoOfBuildingWingFloorSanctioned
- 35
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 62.4 m² (671 sq.ft) | 26 | 5 |
| 2BHK | 64.4 m² (693 sq.ft) | 26 | 0 |
| 2BHK | 65.7 m² (707 sq.ft) | 4 | 3 |
| 3BHK | 84.1 m² (905 sq.ft) | 22 | 14 |
| 3BHK | 90 m² (969 sq.ft) | 25 | 18 |
| Guest Room | 103 m² (1,108 sq.ft) | 1 | 0 |
| Shop | 34.7 m² (374 sq.ft) | 1 | 0 |
| Shop | 39.6 m² (427 sq.ft) | 1 | 0 |
| Shop | 40.9 m² (440 sq.ft) | 2 | 0 |
| Shop | 41.3 m² (445 sq.ft) | 1 | 0 |
Show all 14 unit typesShow fewer unit types
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 48.6 m² (523 sq.ft) | 1 | 0 |
| Shop | 53.5 m² (576 sq.ft) | 2 | 0 |
| Shop | 55.2 m² (595 sq.ft) | 1 | 0 |
| Shop | 62.9 m² (677 sq.ft) | 1 | 0 |
| Total | 114 | 40 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology