RERA projects in Pisoli
42 projects under 46 MahaRERA registrations, registered 2017–2026. 20% have a completion date extended beyond the one promised.
Locality
42RERA projects
46Registrationssome projects hold several
15Completion still due31 past their completion date
12 monthsMedian extension beyond promised date20% of registrations extended
1Regulatory caseson 1 project
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 18 |
| 2018 | 11 |
| 2019 | 5 |
| 2020 | 1 |
| 2021 | 1 |
| 2022 | 3 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 2 |
| 2026 | 4 |
Projects in Pisoli
42 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Advika Phase IV-CAdvika Constructions Private Limited | PR1260002600100 | 15 Apr 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Prime Vista Row HousesBarmecha Darda Associates LLP | PR1260002503031 | 24 Mar 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Prime VistaBarmecha Darda Associates LLP | PC1260002502685 | 10 Mar 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Kumar Palmcrest A6Kumar Properties And Promoters Private Limited | P52100081089 | 30 Jan 2026 | 31 Mar 2029 | — | Not yet due | 0 |
| Emerald GreenM/S Shri Chintamani Associates | PM1260002500169 | 30 Jun 2025 | 9 Aug 2028 | — | Not yet due | 0 |
| Savvitri AarcadeShree Sai Developers | P52100079994 | 11 Apr 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Atur Valley Vista Wing AM/S Atur Sangtani And Associates | P52100045737 | 6 Jun 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Kumar PalmnestKumar Properties And Promoters Private Limited | P52100045312 | 12 May 2022 | 31 Dec 2030 | — | Not yet due | 0 |
| Kumar Palmcrest A5Kumar Properties And Promoters Private Limited | P52100033817 | 8 Mar 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Brookefield Willows- A2Nirman Trimurti Developers | P52100028570 | 22 Mar 2021 | 30 Jun 2025 | — | Promised date passed | 0 |
| ARV Newtown Phase IIIVedant Infracon | P52100027214 | 24 Nov 2020 | 30 Jun 2026 | — | Promised date passed | 0 |
| Arv RegaliaUnitree India Realty LLP | P52100023200 | 6 Dec 2019 | 30 Dec 2026 | — | Not yet due | 0 |
| Avaunce Building B And C Phase 2Golden Palm Infrastructure | P52100022846 | 30 Oct 2019 | 10 Dec 2022 | — | Promised date passed | 0 |
| Kumar Palmcrest A4 BuildingKumar Properties And Promoters Private Limited | P52100022295 | 9 Sep 2019 | 28 Aug 2023 | — | Promised date passed | 0 |
| Kingston Greens Phase 1Vedant Developments | P52100019471 | 1 Feb 2019 | 30 Jun 2027 | — | Not yet due | 0 |
| Anika ArcadeArun Pitamber Sheth | P52100018361 | 26 Oct 2018 | 31 May 2019 | — | Promised date passed | 0 |
| Banka Sapphire A WingBanka Constructions | P52100017790 | 17 Sep 2018 | 30 Dec 2024 | — | Promised date passed | 0 |
| Dynamic Imperia Plus A Phase 4AVedant Dynamic Associates | P52100017545 | 24 Aug 2018 | 30 Jun 2028 | — | Not yet due | 0 |
| Dynamic Imperia Plus B Phase 5BVedant Dynamic Associates | P52100017200 | 23 Jul 2018 | 30 Jun 2026 | — | Promised date passed | 0 |
| Sunshine Hills Phase-II A-5Tricon Builderss | P52100017202 | 23 Jul 2018 | 30 Dec 2023 | — | Promised date passed | 0 |
| Dynamic Imperia Plus D Phase 2BVedant Dynamic Associates | P52100017126 | 16 Jul 2018 | 30 Jun 2026 | — | Promised date passed | 0 |
| Dynamic Imperia PlusVedant Dynamic Associates | P52100017070, P52100017142 | 11 Jul 2018 | 30 Jun 2023 | — | Promised date passed | 0 |
| Dynamic Imperia Plus B Phase 5AVedant Dynamic Associates | P52100017094 | 11 Jul 2018 | 30 Jun 2026 | — | Promised date passed | 0 |
| Dynamic Imperia Plus D Phase 2AVedant Dynamic Associates | P52100017073 | 11 Jul 2018 | 30 Jun 2026 | — | Promised date passed | 0 |
| ARV Newtown Phase IIVedant Infracon | P52100015904 | 9 Apr 2018 | 24 Dec 2025 | — | Promised date passed | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- Vedant Dynamic Associates6 projects
- Kumar Properties And Promoters Private Limited4 projects
- Vedant Infracon3 projects
- Barmecha Darda Associates LLP2 projects
- Sanjay Dnyanoba Jagtap2 projects
- Tricon Builderss2 projects
- Advika Constructions Private Limited1 project
- Advika Constructions Pvt.ltd1 project
- Arun Pitamber Sheth1 project
- Asian Ventures1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology