Skip to content
Residential / Group Housing · 1 building · 14 unitsRERA P52100053103

Sarika

Deedo IDDP-PUN-8XQM

MahaRERA shows it completed; no MahaRERA orders on record; 7% of its units are booked.

Chinchwad, Pune 411033 · Property rates in Chinchwad · by Anand Constructions

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales7% booked1 of 14 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 16 Oct 2023, completion promised 30 Jun 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100053103
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005310316 Oct 202330 Jun 202630 Jun 2026M/s ANAND CONSTRUCTIONSProject page
Documents72

1 document held by Deedo, 71 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFirm Pan.pdf · uploaded 4 Sep 2023Source

Legal

  • Declaration Form BForm B.pdf · uploaded 4 Sep 2023Source
  • Legal Title reportLegal Title_compressed.pdf · uploaded 16 Sep 2023Source

Migrated

  • 1 PAN CardFirm Pan.pdf · uploaded 4 Sep 2023Source
  • 1 a Details of encumbrances concerned to FinanceLegal Encumbrances.pdf · uploaded 4 Sep 2023Source
  • 2 a Details of encumbrances concerned to FinanceFinance Encumbrances.pdf · uploaded 4 Sep 2023Source
  • 1 b Details of encumbrances concerned to LegalLegal Encumbrances.pdf · uploaded 4 Sep 2023Source
Show all 72 documentsShow fewer documents

Migrated

  • 2 b Details of encumbrances concerned to LegalFinance Encumbrances.pdf · uploaded 4 Sep 2023Source
  • 1 Copy of Layout Approval (in case of layout)Main Layout highlighted.pdf · uploaded 4 Sep 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding layout.pdf · uploaded 4 Sep 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 4 Sep 2023Source
  • 1 Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 4 Sep 2023Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 4 Sep 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnand.pdf · uploaded 4 Sep 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsChaitali.pdf · uploaded 4 Sep 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsJaiwant.pdf · uploaded 4 Sep 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsSandhya.pdf · uploaded 4 Sep 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report_200279480137_For_Asset_Based_Search_05_09_2023_11_49_24_232.pdf · uploaded 5 Sep 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate_compressed.pdf · uploaded 5 Sep 2023Source
  • 1 Proforma of Allotment letterAllotment Letter_compressed.pdf · uploaded 5 Sep 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank.pdf · uploaded 5 Sep 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation wrt Allotment.pdf · uploaded 5 Sep 2023Source
  • 1 Deviation Report with respect to model copy of AgreementAC Sarika Rera Deviation.pdf · uploaded 5 Sep 2023Source
  • 1 Copy of the legal title reportLegal Title_compressed.pdf · uploaded 16 Sep 2023Source
  • 1 Proforma of Agreement for saleRERA Draft Agreement.pdf · uploaded 18 Sep 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed.pdf · uploaded 28 Feb 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3 with sign_compressed.pdf · uploaded 28 Feb 2024Source
  • 2 Copy of Layout Approval (in case of layout)New Layout.pdf · uploaded 7 Jun 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentIOD.pdf · uploaded 7 Jun 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentNew CC (2).pdf · uploaded 7 Jun 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q4_compressed.pdf · uploaded 7 Jun 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q4.pdf · uploaded 7 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FOrm 2A_compressed.pdf · uploaded 7 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q4_compressed.pdf · uploaded 7 Jun 2024Source
  • 2 Declaration about Commencement CertificateDeclaration of Commencement.pdf · uploaded 8 Jun 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1.pdf · uploaded 17 Aug 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q1.pdf · uploaded 17 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Anand Construction.pdf · uploaded 11 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3_compressed.pdf · uploaded 29 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 29 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 31122024_compressed.pdf · uploaded 16 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_11zon.pdf · uploaded 18 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_11zon.pdf · uploaded 18 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q3.pdf · uploaded 18 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q4.pdf · uploaded 18 Apr 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q4.pdf · uploaded 18 Apr 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 3form 3 or_11zon.pdf · uploaded 19 Jul 2025Source
  • Form 5 (FY 2024-2025)form 5.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 (2).pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 2form 2 with sign.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 3FORM 3 SaRIKA Q 2_11zon.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 1Form 1 (2).pdf · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 2form 2 engineers certificate.pdf · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 3form 3_1_11zon.pdf · uploaded 19 Jan 2026Source
  • Occupational CertificateCompletion Certificate.pdf · uploaded 5 Feb 2026Source
  • Occupational CertificateCompletion mail SS.pdf · uploaded 5 Feb 2026Source

Technical

  • DocumentMain Layout highlighted.pdf · uploaded 4 Sep 2023Source
  • DocumentBuilding layout.pdf · uploaded 4 Sep 2023Source
  • DocumentNew Layout.pdf · uploaded 7 Jun 2024Source
  • DocumentIOD.pdf · uploaded 7 Jun 2024Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 29 Nov 2024Source
  • DocumentForm 31122024_compressed.pdf · uploaded 16 Apr 2025Source
  • DocumentForm 1_11zon.pdf · uploaded 18 Apr 2025Source
  • DocumentForm 1 (2).pdf · uploaded 19 Jan 2026Source

Technical (Engineer)

  • DocumentForm 2 Engineer Certificate Q3.pdf · uploaded 18 Apr 2025Source
  • DocumentForm 2 Engineer Certificate Q4.pdf · uploaded 18 Apr 2025Source
  • DocumentForm 2 Engineer Certificate Q4.pdf · uploaded 18 Apr 2025Source
  • Documentform 2 engineers certificate.pdf · uploaded 17 Jan 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 4317/1 to 4317/5, C.T.S No. 4317

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—14 units in all
Address
Survey No. 271/1 to 8, C.T.S No. 4317, 4317/1 to 4317/5, Chinchwad, Pune, Chinchwad, ChinchwadPIN 411033
Village
Pimpri Chinchawad (M Corp.), Haveli taluka
Land area for this project
559 sq m (6,012 sq ft)
Permissible built-up area
1,956 sq m (21,058 sq ft)
Sanctioned built-up area
1,879 sq m (20,225 sq ft)
Designated bank account
212
Developed in phases
No

Survey, CTS, gat or plot numbers

4317/1 to 4317/5C.T.S No. 4317Survey No. 271/1 to 8

Land as published on MahaRERA's project page

Survey No. 271/1 to 8,C.T.S No. 4317, 4317/1 to 4317/5, Chinchwad, Pune

Boundaries

North
Odha
South
Colony road
East
Plot No 19
West
Plot No 21

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

14 units registered

— · 14 units
TypeCarpet areaUnits
——14

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSanjeev Bhosale—
Chartered accountantGanesh Sunil Mandlecha—
Chartered accountantNPSR & Associates - CA. Nandkishor Lahoti—
EngineerHanmant Patil—
EngineerJadhav Sanket Sanjay—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Chinchwad

All 2,866 projects in Chinchwad · Compare Sarika with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology