Peth, Pune
Deedo IDDL-PUN-PETH9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects52
Registrations52
Completion still due2329 past their date
Median extension4 months54% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
52 MahaRERA registrations in Peth
7 not yet due16 extended, not yet due29 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Peth
52 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| NidishKalashree Properties | 2 yrs 2 mo late | — | 94% |
| Dhanlaxmi MarketDhanlaxmi Infra | Due Dec 2026, extended 2 yrs | — | 16% |
| Gulab SadanButtepatil Properties | Completed | — | 74% |
| Arsh ComplaxMilan Developers | Due Dec 2027, extended 4 yrs 7 mo | — | 4% |
| NikunjDMBhosale | Completed | — | — |
| Vintage City Ph 2Eiffel Landmarks Private Limited | Completed | — | — |
| Gulab CourtButtepatil Properties | Completed | — | 97% |
| Gulab Bhakti NiwasButtepatil Properties | Completed | — | 100% |
| Vishal ApartmentVijay Shankar Inamdar | 11 mo late | — | — |
| Sonai Dada HeightsK M Developers | Completed, extended 1 yr 1 mo | — | 42% |
| Jaishankar HeightsSarthak Developers | Completed | — | 100% |
| Prasanna TulshibaugPrasanna Developers | 3 yrs 11 mo late | — | 18% |
| Va.Na.Oak Trust SankulSanjay Vasantlal Gundecha | 2 yrs 8 mo late | — | 24% |
| Saianand Trade CentreJalan Sable Associates | Due Jun 2027, extended 3 yrs | — | 38% |
| Urban SolitaireUrban Realty | Completed, extended 11 mo | — | 31% |
| Dhanlaxmi IconHari Om Developers | Completed | — | 55% |
| Blue Bird Co Operative Society LtdAsha Arun Sane | Completed, extended 9 mo | — | 100% |
| Vintage CityEiffel Landmarks Private Limited | Completed | — | — |
| Kalp ResidencyKalp Buildcon And Infra | 4 yrs 8 mo late | — | 60% |
| Shobha ChambersRajesh Nandlal Peswani | Completed | — | — |
| Kapil SankalpAvadhoot Constructions | Completed, extended 1 yr 6 mo | — | 9% |
| Lakshmi Gopal NivasGund And Pethe Associates | Completed | — | 92% |
| Gulab VishwaButtepatil Properties | Completed, extended 1 yr | — | 91% |
| Gulab KunjButtepatil-Sabale Properties | Completed | — | 52% |
| KrushnaiB K Pate Enterprises | 7 yrs 5 mo late | — | 86% |
Nearby: other villages in Haveli
Most active promoters
- Buttepatil Properties4 projects
- Eiffel Landmarks Private Limited2 projects
- Agr Realtors Llp1 project
- Ajay Jayawant Bhosle1 project
- Ascent Landmarks1 project
- Asha Arun Sane1 project
- Ashok Dhanraj Chordia1 project
- A Square Developer1 project
- Avadhoot Constructions1 project
- Belvalkar Realtors LLP1 project
Peth, in questions
How many projects in Peth run late?
9 in 10 MahaRERA registrations (45 of 52): their completion date was extended or has passed, data through 5 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Peth by Deedo. Medians on fewer than 3 deeds are not shown.
Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology