Shubham
Deedo IDDP-PUN-0115Completion was pushed back 1 year to Dec 2019, and that date has passed too; no MahaRERA orders on record; 8% of its units are booked.
Nanded, Pune 411068 · Property rates in Nanded · by Sankalpconstruction
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year to Dec 2019, and that date has passed too
- This projectRegistered 7 Sep 2017, completion promised 31 Dec 2018, revised to 31 Dec 2019, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100012774
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100012774 | 7 Sep 2017 | 31 Dec 2018 | 31 Dec 2019 | Sankalpconstruction | Project page |
Documents25
2 documents held by Deedo, 23 filings listed on MahaRERA's project page
Finance
- PAN Cardpan crad firm.pdf · uploaded 31 Aug 2017Source
Legal
Show all 25 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)copy of layout approval.pdf · uploaded 31 Aug 2017Source
- 1 Building Plan Approval (IOD)BUILDING PLAN.pdf · uploaded 31 Aug 2017Source
- 1 Declaration in FORM Bform b.pdf · uploaded 31 Aug 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM NO 1.pdf · uploaded 31 Aug 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM NO 2.pdf · uploaded 31 Aug 2017Source
- 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 31 Aug 2017Source
- 1 Proforma of Allotment letteragreement sale.pdf · uploaded 31 Aug 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate.pdf · uploaded 1 Sep 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architech Certificate.pdf · uploaded 8 Jan 2019Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 8 Jan 2019Source
- 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 8 Jan 2019Source
- 1 Certificates of CA (Form 5)Form 5.pdf · uploaded 8 Jan 2019Source
- 2 Proforma of Allotment letterDraft Agreement shubham 964 KB.pdf · uploaded 29 Jul 2020Source
Technical
Technical (Architect)
- DocumentArchitech Certificate.pdf · uploaded 8 Jan 2019Source
Technical (Engineer)
- DocumentEngineers Certificate.pdf · uploaded 8 Jan 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 244
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 2BHK, Offices, Shop39 units in all
- Address
- 244PIN 411068
- Village
- Nanded, Haveli taluka
- Location
- 19.18341, 72.97810
- Land area for this project
- 888 sq m (9,555 sq ft)
- Permissible built-up area
- 1,785 sq m (19,212 sq ft)
- Sanctioned built-up area
- 1,785 sq m (19,212 sq ft)
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
244
Boundaries
- North
- Cts No 244 Remaining Property
- South
- Cts No 242
- East
- Cts No 244 Own Road
- West
- Cts No 272
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking39 units
3 of 39 units booked (8%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 715.46 sq m · 7,701 sq ft | 18 | 3 |
| 2BHK | 486.08 sq m · 5,232 sq ft | 8 | 0 |
| Offices | 407.62 sq m · 4,388 sq ft | 9 | 0 |
| Shop | 76.59 sq m · 824 sq ft | 4 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Walhekar Associates | — |
| Other | Mohan D Deshmukh | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Nanded
- VrundavanRERA PR1260002601635
- Harmony ApartmentsRERA PR1260002502527
- SaajgiriRERA PR1260002501621
- Destination Center - IIRERA P52100079788
- Aalaap - I at Nanded CityRERA P52100055134
- Melody I at Nanded CityRERA P52100051948
- Melody II at Nanded CityRERA P52100051867
- Bahaar at Nanded CityRERA P52100049984
All 20 projects in Nanded · Compare Shubham with another project