Residential / Group Housing · 6 buildings · 608 unitsRERA P52100049984

Bahaar at Nanded City

Deedo IDDP-PUN-25XV

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 95% of its units are booked.

Nanded, Pune 411068 · by Nanded City Development & Construction Co. Ltd · 75% of its projects kept the RERA date

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales95% booked579 of 608 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 6 Mar 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100049984
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000499846 Mar 202331 Dec 202630 Apr 2027Nanded City Development & Construction Co. Ltd.Project page
Documents157

1 document held by Deedo, 156 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card- NCDCCL.pdf · uploaded 13 Feb 2023Source
  • Other – FinanceDeclaration for name.pdf · uploaded 21 Feb 2023Source

Legal

  • Other – LegalLetter for non requirement of Land owner promoter details.pdf · uploaded 13 Feb 2023Source
  • Other – LegalList of Shareholders - Nanded City (Project BAHAAR).pdf · uploaded 13 Feb 2023Source
  • Other – LegalJoint Development Agreement.pdf · uploaded 13 Feb 2023Source
  • Other – LegalIndex II - Joint Development Agreement.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportSearch Title Report 19 1.pdf · uploaded 13 Feb 2023Source
Show all 157 documentsShow fewer documents

Legal

  • Legal Title reportSearch Title Report 19 2.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportSearch Title Report 19 3.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportSearch Title Report 19 4A.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportSearch Title Report 19 5.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportSearch Title Report 20 1.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportSearch Title Report 20 2.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportSearch Title Report 21 2A 1.pdf · uploaded 13 Feb 2023Source
  • Declaration Form BAffidavit.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportFormat A - Legal Title Report.pdf · uploaded 15 Feb 2023Source

Migrated

  • 1 PAN CardPAN Card- NCDCCL.pdf · uploaded 13 Feb 2023Source
  • 1 Copy of the legal title reportSearch Title Report 19 1.pdf · uploaded 13 Feb 2023Source
  • 2 Copy of the legal title reportSearch Title Report 19 2.pdf · uploaded 13 Feb 2023Source
  • 3 Copy of the legal title reportSearch Title Report 19 3.pdf · uploaded 13 Feb 2023Source
  • 4 Copy of the legal title reportSearch Title Report 19 4A.pdf · uploaded 13 Feb 2023Source
  • 5 Copy of the legal title reportSearch Title Report 19 5.pdf · uploaded 13 Feb 2023Source
  • 6 Copy of the legal title reportSearch Title Report 20 1.pdf · uploaded 13 Feb 2023Source
  • 7 Copy of the legal title reportSearch Title Report 20 2.pdf · uploaded 13 Feb 2023Source
  • 8 Copy of the legal title reportSearch Title Report 21 2A 1.pdf · uploaded 13 Feb 2023Source
  • 1 a Details of encumbrances concerned to FinanceNo Encumbrances - Financial.pdf · uploaded 13 Feb 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrances Letter - Legal.pdf · uploaded 13 Feb 2023Source
  • 1 b Details of encumbrances concerned to LegalNo Encumbrances - Financial.pdf · uploaded 13 Feb 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrances Letter - Legal.pdf · uploaded 13 Feb 2023Source
  • 1 Copy of Layout Approval (in case of layout)1-10.pdf · uploaded 13 Feb 2023Source
  • 1 Building Plan Approval / NA Order for plotted development2-10.pdf · uploaded 13 Feb 2023Source
  • 2 Building Plan Approval / NA Order for plotted development3-10.pdf · uploaded 13 Feb 2023Source
  • 3 Building Plan Approval / NA Order for plotted development4-10.pdf · uploaded 13 Feb 2023Source
  • 4 Building Plan Approval / NA Order for plotted development5-10.pdf · uploaded 13 Feb 2023Source
  • 5 Building Plan Approval / NA Order for plotted development6-10.pdf · uploaded 13 Feb 2023Source
  • 6 Building Plan Approval / NA Order for plotted development7-10.pdf · uploaded 13 Feb 2023Source
  • 7 Building Plan Approval / NA Order for plotted development8-10.pdf · uploaded 13 Feb 2023Source
  • 8 Building Plan Approval / NA Order for plotted development9-10.pdf · uploaded 13 Feb 2023Source
  • 9 Building Plan Approval / NA Order for plotted development10-10.pdf · uploaded 13 Feb 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 13 Feb 2023Source
  • 1 Declaration about Commencement CertificateFormat D - Commencement Certificate Declaration.pdf · uploaded 13 Feb 2023Source
  • 1 Declaration in FORM BAffidavit.pdf · uploaded 13 Feb 2023Source
  • 1 CERSAI detailsDeclaration for Cersai.pdf · uploaded 13 Feb 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Ashish Dedge.pdf · uploaded 13 Feb 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Balasaheb Mane.pdf · uploaded 13 Feb 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Devidas Lagad.pdf · uploaded 13 Feb 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Ishaan Magar.pdf · uploaded 13 Feb 2023Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Jayprakash Girme.pdf · uploaded 13 Feb 2023Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Nilesh Magar.pdf · uploaded 13 Feb 2023Source
  • 7 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Prashant Dugane.pdf · uploaded 13 Feb 2023Source
  • 8 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Pratik Magar.pdf · uploaded 13 Feb 2023Source
  • 9 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Ratnadeep Jadhav.pdf · uploaded 13 Feb 2023Source
  • 10 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Rohan Jadhav.pdf · uploaded 13 Feb 2023Source
  • 11 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Sangram Jadhavrao.pdf · uploaded 13 Feb 2023Source
  • 12 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Sujit Karle.pdf · uploaded 13 Feb 2023Source
  • 13 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Swastik Sirsikar.pdf · uploaded 13 Feb 2023Source
  • 14 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Umesh Magar.pdf · uploaded 13 Feb 2023Source
  • 15 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mr Vaijukumar Ghule.pdf · uploaded 13 Feb 2023Source
  • 16 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations Mrs Rekha Magar.pdf · uploaded 13 Feb 2023Source
  • 17 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organizations.pdf · uploaded 13 Feb 2023Source
  • 1 Proforma of Agreement for saleAgreement For Sale.pdf · uploaded 13 Feb 2023Source
  • 1 Proforma of Allotment letterAllotment letter Draft.pdf · uploaded 13 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank Account.pdf · uploaded 13 Feb 2023Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank No Encumbrance.pdf · uploaded 13 Feb 2023Source
  • 1 Deviation Report with respect to Allotment letterAllotment Letter Deviation Report.pdf · uploaded 13 Feb 2023Source
  • 1 Deviation Report with respect to model copy of AgreementAgreement For Sale - Deviation Report.pdf · uploaded 13 Feb 2023Source
  • 1 Other – LegalLetter for non requirement of Land owner promoter details.pdf · uploaded 13 Feb 2023Source
  • 2 Other – LegalList of Shareholders - Nanded City (Project BAHAAR).pdf · uploaded 13 Feb 2023Source
  • 3 Other – LegalJoint Development Agreement.pdf · uploaded 13 Feb 2023Source
  • 4 Other – LegalIndex II - Joint Development Agreement.pdf · uploaded 13 Feb 2023Source
  • 9 Copy of the legal title reportFormat A - Legal Title Report.pdf · uploaded 15 Feb 2023Source
  • 2 CERSAI detailsCersai Report HDFC Ltd 300 Crore.pdf · uploaded 21 Feb 2023Source
  • 3 CERSAI detailsCersai Report HDFC Ltd 50 Crore.pdf · uploaded 21 Feb 2023Source
  • 1 Other – FinanceDeclaration for name.pdf · uploaded 21 Feb 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3.pdf · uploaded 27 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - March 2023.pdf · uploaded 10 May 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 10 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form - 2A.pdf · uploaded 10 May 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold-Booked inventory - March 2023.pdf · uploaded 10 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - June 2023.pdf · uploaded 29 Jul 2023Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of sold booked Inventory - June 2023.pdf · uploaded 29 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form - 5.pdf · uploaded 18 Sep 2023Source
  • 3 Disclosure of sold/ booked inventoryDisclosure of sold Booked Inventory - September.pdf · uploaded 7 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - September 2023.pdf · uploaded 16 Nov 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - September 2023.pdf · uploaded 10 Jan 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - December 2023.pdf · uploaded 10 Jan 2024Source
  • 4 Disclosure of sold/ booked inventoryDisclosure of sold booked inventory - December 2023.pdf · uploaded 10 Jan 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society - Name Approval.pdf · uploaded 15 Jan 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - March 2024.pdf · uploaded 9 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - March 2024.pdf · uploaded 9 Apr 2024Source
  • 5 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - March 2024.pdf · uploaded 9 Apr 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - December 2023.pdf · uploaded 9 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - March 2024.pdf · uploaded 7 May 2024Source
  • 3 a Details of encumbrances concerned to FinanceOpinion on litigation.pdf · uploaded 8 May 2024Source
  • 3 b Details of encumbrances concerned to LegalOpinion on litigation.pdf · uploaded 8 May 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - March 2024.pdf · uploaded 8 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Jun 2024.pdf · uploaded 29 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Sep 2024.pdf · uploaded 29 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Jun 2024.pdf · uploaded 29 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Oct 2024.pdf · uploaded 29 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Sep 2024.pdf · uploaded 30 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 2024.pdf · uploaded 13 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold Booked Inventory - Dec 2024.pdf · uploaded 13 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Dec 2024.pdf · uploaded 30 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Jan 2025.pdf · uploaded 1 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - March 2025.pdf · uploaded 28 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold Booked Inventory - March 2025.pdf · uploaded 8 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A - 2024-2025.pdf · uploaded 8 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - March 2025.pdf · uploaded 3 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - March 2025.pdf · uploaded 3 May 2025Source
  • Form 1Form 1 - March 2025.pdf · uploaded 17 Jul 2025Source
  • Form 2Form 2 - March 2025.pdf · uploaded 17 Jul 2025Source
  • Form 3Form 3 - March 2025.pdf · uploaded 17 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold Booked Inventory - March 2025.pdf · uploaded 17 Jul 2025Source
  • Form 1Form 1 - June 2025.pdf · uploaded 18 Jul 2025Source
  • Form 2Form 2 - June 2025.pdf · uploaded 18 Jul 2025Source
  • Form 3Form 3 - June 2025.pdf · uploaded 18 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold-Booked Inventory - June 2025.pdf · uploaded 18 Jul 2025Source
  • Form 2A (FY 2024-2025)Form 2A.pdf · uploaded 30 Sep 2025Source
  • Form 5 (FY 2024-2025)Form 5.pdf · uploaded 30 Sep 2025Source
  • Form 1Form 1 - Sep 2025.pdf · uploaded 18 Oct 2025Source
  • Form 2Form 2 - Sep 2025.pdf · uploaded 18 Oct 2025Source
  • Form 3Form 3 - Sep 2025.pdf · uploaded 18 Oct 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - Sep 2025.pdf · uploaded 18 Oct 2025Source
  • Form 1Form 1 - Dec 2025.pdf · uploaded 16 Jan 2026Source
  • Form 2Form 2 - Dec 2025.pdf · uploaded 16 Jan 2026Source
  • Form 3Form 3 - Dec 2025.pdf · uploaded 16 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - Dec 2025.pdf · uploaded 16 Jan 2026Source
  • Form 2A (FY 2025-2026)Form 2A - March 2026.pdf · uploaded 3 Apr 2026Source
  • Form 1Form 1 - March 2026.pdf · uploaded 6 Apr 2026Source
  • Form 2Form 2 - March 2026.pdf · uploaded 6 Apr 2026Source
  • Form 3Form 3 - March 2026.pdf · uploaded 6 Apr 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold Booked inventory - March 2026.pdf · uploaded 6 Apr 2026Source
  • Form 1Form 1 - June 2026.pdf · uploaded 18 Jul 2026Source
  • Form 2Form 2 - June 2026.pdf · uploaded 18 Jul 2026Source
  • Form 3Form 3 - June 2026.pdf · uploaded 18 Jul 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold Booked Inventory - Jun 2026.pdf · uploaded 18 Jul 2026Source
  • Form 5 (FY 2025-2026)Form 5 - 2025 - 2026.pdf · uploaded 29 Sep 2026Source

Technical

  • Document1-10.pdf · uploaded 13 Feb 2023Source
  • Document2-10.pdf · uploaded 13 Feb 2023Source
  • Document3-10.pdf · uploaded 13 Feb 2023Source
  • Document4-10.pdf · uploaded 13 Feb 2023Source
  • Document5-10.pdf · uploaded 13 Feb 2023Source
  • Document6-10.pdf · uploaded 13 Feb 2023Source
  • Document7-10.pdf · uploaded 13 Feb 2023Source
  • Document8-10.pdf · uploaded 13 Feb 2023Source
  • Document9-10.pdf · uploaded 13 Feb 2023Source
  • Document10-10.pdf · uploaded 13 Feb 2023Source

Technical (Architect)

  • DocumentForm 1 - March 2024.pdf · uploaded 9 Apr 2024Source
  • DocumentForm 1 - Jun 2024.pdf · uploaded 29 Oct 2024Source
  • DocumentForm 1 - Sep 2024.pdf · uploaded 29 Oct 2024Source
  • DocumentForm 1 - Dec 2024.pdf · uploaded 13 Jan 2025Source
  • DocumentForm 1 - March 2025.pdf · uploaded 28 Mar 2025Source

Technical (Engineer)

  • DocumentForm 2 - Oct 2024.pdf · uploaded 29 Oct 2024Source
  • DocumentForm 2 - Jan 2025.pdf · uploaded 1 Feb 2025Source
  • DocumentForm 2 - March 2025.pdf · uploaded 3 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S No 19 P 20 P 21 P

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
3BHK, 2.5 BHK, 2BHK608 units in all
Address
S No 19 P 20 P 21 P, Sinhagad Road, Nanded PhataPIN 411068
Village
Nanded, Haveli taluka
Land area for this project
40,310 sq m (4,33,893 sq ft)
Permissible built-up area
73,133 sq m (7,87,192 sq ft)
Sanctioned built-up area
73,133 sq m (7,87,192 sq ft)
Recreational open space
4,031 sq m (43,389 sq ft)
Designated bank account
204
Developed in phases
Yes

Survey, CTS, gat or plot numbers

S No 19 P 20 P 21 P

Land as published on MahaRERA's project page

S No 19 P 20 P 21 P

Boundaries

North
7 M Service Road
South
30 M Road
East
24 M Road
West
Nrd 24

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking608 units

579 of 608 units booked (95%), as the promoter reported to MahaRERA

3BHK · 304 units2.5 BHK · 152 units2BHK · 152 units
BuildingTypeCarpet areaUnitsBooked
A3BHK112.56 sq m · 1,212 sq ft7671
B3BHK112.56 sq m · 1,212 sq ft7671
C2.5 BHK88.09 sq m · 948 sq ft7673
C2BHK75.75 sq m · 815 sq ft7671
D3BHK112.56 sq m · 1,212 sq ft7676
E3BHK112.56 sq m · 1,212 sq ft7676
F2.5 BHK88.09 sq m · 948 sq ft7672
F2BHK75.75 sq m · 815 sq ft7669

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals9

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArch Malay Deshmukh—
Chartered accountantD R Barve & Associates—
Chartered accountantSDB & Company—
EngineerMs Rucha Watve—
EngineerPrashant Kanikdale—
OtherAmey Gawade—
OtherKetan Dantale—
OtherRavi & Varsha Gavandi—
OtherS S Zopate—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology