Nanded City Development & Construction Co. Ltd
Company or firm · 17 projects · 21 MahaRERA registrations
Also appears as Nanded City Development & Construction Co. Ltd.
17Projects21 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date16 of 16 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 5 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| PanchamP52100000288 | Nanded | 2017 | Certificate Signed | 30 Apr 2022 | 30 Apr 2022 | On date |
| Sargam at Nanded CityP52100000292 | Nanded | 2017 | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| PanchamP52100000385 | Nanded | 2017 | Certificate Signed | 31 Oct 2019 | 31 Oct 2019 | On date |
| Dhanashree at Nanded CityP52100002425 | Nanded | 2017 | Certificate Signed | 1 Jul 2023 | 1 Jul 2023 | On date |
| JanaranjaniP52100015719 | Nanded | 2018 | Certificate Signed | 31 Aug 2019 | 31 Aug 2019 | On date |
| JanaranjaniP52100015725 | Nanded | 2018 | Certificate Signed | 30 Nov 2020 | 30 Nov 2020 | On date |
| Bageshree at Nanded CityP52100021465 | Nanded | 2019 | Certificate Signed | 30 May 2023 | 30 May 2023 | On date |
| Kalashree at Nanded CityP52100021483 | Haveli | 2019 | Certificate Signed | 30 May 2023 | 30 May 2023 | On date |
| Yogashree at Nanded CityP52100022562 | Nanded | 2019 | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| RhythmP52100028606 | Nanded | 2021 | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| RhythmP52100028623 | Nanded | 2021 | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| RhythmP52100028650 | Nanded | 2021 | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Sur at Nanded CityP52100032686 | Nanded | 2022 | Certificate Signed | 31 Aug 2025 | 31 Aug 2025 | On date |
| Janaranjani - D Phase II at Nanded CityP52100047078 | Nanded | 2022 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Bahaar at Nanded CityP52100049984 | Nanded | 2023 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Melody II at Nanded CityP52100051867 | Nanded | 2023 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Melody I at Nanded CityP52100051948 | Nanded | 2023 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Aalaap - I at Nanded CityP52100055134 | Nanded | 2024 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| Destination Center - IIP52100079788 | Nanded | 2025 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| SaajgiriPR1260002501621 | Nanded | 2025 | Certificate Signed | 31 Aug 2029 | 31 Dec 2029 | +4 months |
| Harmony ApartmentsPR1260002502527 | Nanded | 2026 | Certificate Signed | 30 Sep 2029 | 30 Jan 2030 | +4 months |
Show all 21 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 21 registrations
Track record notes
- 16 of 16 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Bahaar at Nanded City (P52100049984).
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- DeregisteredDeregistered: Yogashree At Nanded City · Yogashree at Nanded City · P52100022562
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology