Residential / Group Housing · 2 buildings · 178 unitsRERA P52100015918

SkyHigh Towers - D1D2

Deedo IDDP-PUN-76ND

Completion was pushed back 4 months, to Jul 2028; 1 listing or order with MahaRERA on record; 94% of its units are booked.

Man, Pune 411057 · Property rates in Man · by New World Landmark Llp

DeliveryExtended 4 moPromised Mar 2028 · now due Jul 2028Regulatory1 listing or orderLatest: Regulatory order, 2026Sales94% booked168 of 178 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2028

  • This projectRegistered 9 Apr 2018, completion promised 31 Mar 2028, revised to 31 Jul 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory record1

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

  • Regulatory order31 Aug 2026Matched by RERA number

    Regulatory order: PROJECT NAME: SKY HIGH TOWERS - D1D2 (Regulatory Case No. 595 OF 2026) dated 31 Aug, 2026.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100015918
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000159189 Apr 201831 Mar 202831 Jul 2028New World Landmark LLPProject page
Documents171

1 document held by Deedo, 170 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN card.pdf · uploaded 5 Apr 2018Source

Legal

  • Legal Title reportSearch And Tital Report Maan.pdf · uploaded 4 Apr 2018Source
  • Declaration Form BForm B declaration.pdf · uploaded 5 Apr 2018Source
  • Declaration Form BForm B PH 2 D1 D2.pdf · uploaded 14 Aug 2019Source
  • OtherBank Details PH 2.pdf · uploaded 8 Jul 2021Source
  • OtherRENEWAL OF CONSENT TO OPERATE.pdf · uploaded 14 Nov 2022Source
  • OthersEnvironmental Clearance EC.pdf · uploaded 12 Nov 2025Source
Show all 171 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportSearch And Tital Report Maan.pdf · uploaded 4 Apr 2018Source
  • 1 Copy of Layout Approval (in case of layout)1289-069 Phase II Wise Layout.pdf · uploaded 4 Apr 2018Source
  • 1 PAN CardPAN card.pdf · uploaded 5 Apr 2018Source
  • 1 Details of encumbrancesEmcumbrance.pdf · uploaded 5 Apr 2018Source
  • 1 Building Plan Approval (IOD)Sanction Plan.pdf · uploaded 5 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 5 Apr 2018Source
  • 1 Declaration in FORM BForm B declaration.pdf · uploaded 5 Apr 2018Source
  • 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 5 Apr 2018Source
  • 1 Proforma of Allotment letterAllotment Letter Draft Agreement.pdf · uploaded 5 Apr 2018Source
  • 2 Copy of Layout Approval (in case of layout)Layout PH2 D1 D2.pdf · uploaded 14 Aug 2019Source
  • 2 Building Plan Approval (IOD)Layout Plan-(1MB).pdf · uploaded 14 Aug 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencment PH2 D1 D2.pdf · uploaded 14 Aug 2019Source
  • 2 Declaration in FORM BForm B PH 2 D1 D2.pdf · uploaded 14 Aug 2019Source
  • 2 Proforma of Allotment letterAgmt Allotmt Concern Letter NWLLLP PH2.pdf · uploaded 14 Aug 2019Source
  • 2 Certificates of CA (Form 3)FORM 3 HIGHMONTD1D2.pdf · uploaded 9 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)Form 5 New World Landmark llp Sky high towers D1,D2.pdf · uploaded 29 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)New World Ph 2.pdf · uploaded 31 Mar 2021Source
  • 2 Details of encumbrances.pdf · uploaded 5 Jul 2021Source
  • 3 Details of encumbrancesNO DUES LETTER OF PNB.pdf · uploaded 7 Jul 2021Source
  • 3 Proforma of Allotment letterSky High.pdf · uploaded 7 Jul 2021Source
  • 1 OtherBank Details PH 2.pdf · uploaded 8 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A March 2021 SkyHigh.pdf · uploaded 25 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Annual Audit Report of Statutory CA (Form 5).pdf · uploaded 25 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch cert Sky High.pdf · uploaded 20 Sep 2021Source
  • 3 Certificates of CA (Form 3)New World Land mark LLP Form 3 March 21.pdf · uploaded 16 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)NEW WORLD LANDMARK LLP Sky high D1D2 Form 5.pdf · uploaded 16 Mar 2022Source
  • 4 Proforma of Allotment letterSky High Booking Form.pdf · uploaded 27 Jun 2022Source
  • 2 OtherRENEWAL OF CONSENT TO OPERATE.pdf · uploaded 14 Nov 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1- MAAN-VK ARCHITECT.pdf · uploaded 14 Dec 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2-MAAN.pdf · uploaded 14 Dec 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 SkyHigh tower D1, D2 31-3 Sign_compressed.pdf · uploaded 17 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)SkyHigh D1D2 form 2A March 22 signed.pdf · uploaded 13 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)NEW WORLD LANDMARK LLP-D1-D2 June 2022.pdf · uploaded 20 Feb 2023Source
  • 4 Certificates of CA (Form 3)Form 3 Skyhigh D1-D2 30062022 Both Sign_compressed.pdf · uploaded 20 Feb 2023Source
  • 4 Details of encumbrancesEncumbrance update D1-D2.pdf · uploaded 21 Feb 2023Source
  • 5 Certificates of CA (Form 3)Form-3 Both Sign As on 30092022 Skyhigh D1 D2_compressed.pdf · uploaded 28 Mar 2023Source
  • 1 Proforma of Agreement for saleProforma of Agreement to sale.pdf · uploaded 21 Jun 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MAAN D1 D2.pdf · uploaded 31 Jul 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 SKY HIGH D1-D2 ARCHITECT CERTIFICATE.pdf · uploaded 31 Jul 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 U D DEVELOPERS ARCHITECT CERTIFICATE.pdf · uploaded 31 Jul 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)NEW WORLD LAND MARK LLP-D1D2 Form 2.pdf · uploaded 31 Jul 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SKY HIGH D1-D2 ENGINEERING CERTIFICATE.pdf · uploaded 31 Jul 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 U D DEVELOPERS ENGINEERING CERTIFICATE.pdf · uploaded 31 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)From 2A SKY HIGH D1-D2 QUALITY ASSURANCE CERTIFICATE.pdf · uploaded 31 Jul 2023Source
  • 6 Certificates of CA (Form 3)Form 3 Skyhigh D1-D2 31122022 both sign.pdf · uploaded 31 Jul 2023Source
  • 7 Certificates of CA (Form 3)Form 3 Skyhigh D1-D2 30032023 both sign_compressed.pdf · uploaded 31 Jul 2023Source
  • 8 Certificates of CA (Form 3)Form 3 AS Skyhigh D1-D2 30062023-both sign_compressed.pdf · uploaded 7 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 PC FY 22-23 SkyHigh Towers D1-D2_both sign_compressed.pdf · uploaded 7 Sep 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 SKY HIGH TOWERS D1D2.pdf · uploaded 7 Dec 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SkyHigh Towers D1D2.pdf · uploaded 7 Dec 2023Source
  • 9 Certificates of CA (Form 3)form 3 Sky High Towers D1D2 30092023_compressed.pdf · uploaded 7 Dec 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 SKY HIGH TOWER D1D2.pdf · uploaded 20 Mar 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_Sky High Towners D1D2.pdf · uploaded 20 Mar 2024Source
  • 10 Certificates of CA (Form 3)Form 3 Skyhigh D1D2 31122023 both sign_compressed.pdf · uploaded 20 Mar 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 SkyHigh D1D2_compressed.pdf · uploaded 29 Apr 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 D1D2.pdf · uploaded 29 Apr 2024Source
  • 11 Certificates of CA (Form 3)form 3 SkyHigh Towers D1D2 31032024_compressed.pdf · uploaded 29 Apr 2024Source
  • 1 Disclosure of sold/ booked inventoryd1d2 q1.pdf · uploaded 4 May 2024Source
  • 2 Disclosure of sold/ booked inventoryd1d2 q2.pdf · uploaded 4 May 2024Source
  • 3 Disclosure of sold/ booked inventoryd1d2 q3.pdf · uploaded 4 May 2024Source
  • 4 Disclosure of sold/ booked inventoryd1d2 q4.pdf · uploaded 4 May 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_SkyHigh Towers D1D2_compressed.pdf · uploaded 20 Jul 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2_SkyHigh Towers D1D2.pdf · uploaded 20 Jul 2024Source
  • 12 Certificates of CA (Form 3)form 3 SkyHigh D1D2 30-06-2024_compressed.pdf · uploaded 20 Jul 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2_SkyHigh Towers D1D2.pdf · uploaded 31 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)SkyHigh Towers D1D2.pdf · uploaded 13 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 SkyHigh Towers D1D2 31-03-2024.pdf · uploaded 8 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 D1-D2.pdf · uploaded 11 Nov 2024Source
  • 2 Certificates of CA (Form 3)form 3 Sky High Towers D1-D2 30-09-2024_compressed.pdf · uploaded 11 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_SkyHigh Towers D1D2.pdf · uploaded 11 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 SkyHigh Towers D1D2-.pdf · uploaded 29 Jan 2025Source
  • 1 Certificates of CA (Form 3)form 3 SkyHigh Towers D1D2 31-12-2024_compressed.pdf · uploaded 29 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SkyHigh Towers D1D2.pdf · uploaded 29 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySky High D1 D2_compressed.pdf · uploaded 29 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A FY 2019-20.pdf · uploaded 8 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 FY 2018-19.pdf · uploaded 8 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 FY 2019-20.pdf · uploaded 8 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 2020-21.pdf · uploaded 8 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A FY 2020-21.pdf · uploaded 8 Apr 2025Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 8 Apr 2025Source
  • 1 Certificates of CA (Form 3)form 3 sky High tower D1 D2 31-12-2024 sign_11zon.pdf · uploaded 12 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 SkyHigh D1D2 Mar 2025.pdf · uploaded 2 May 2025Source
  • 1 Certificates of CA (Form 3)Form 3 Skyhigh D1-D2 30032025_compressed.pdf · uploaded 2 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2 SkyHigh D1D2 Mar 2025.pdf · uploaded 2 May 2025Source
  • 1 Declaration about Commencement CertificateREVISED Format D_organized.pdf · uploaded 13 May 2025Source
  • 1 Disclosure of sold/ booked inventoryCIrcular 29 - Mar 2023.pdf · uploaded 6 Jun 2025Source
  • 2 Disclosure of sold/ booked inventoryCircular 29 - Jun 2024.pdf · uploaded 6 Jun 2025Source
  • 3 Disclosure of sold/ booked inventoryCircular 29 - Sep 2024.pdf · uploaded 6 Jun 2025Source
  • 4 Disclosure of sold/ booked inventoryCircular 29 - Dec 2024.pdf · uploaded 6 Jun 2025Source
  • 1 Certificates of CA (Form 3)15 Certificates of CA (Form 3).pdf · uploaded 2 Jul 2025Source
  • Withdrawal Update Form 1FORM 1 SKY HIGH TOWERS D1 u0026 D2.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 1FORM 1 SKY HIGH TOWER D1 u0026 D2.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Skyhigh D1 D2 June 2025Updated.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Sky High Tower D1D2Upated.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 3Form 3 Skyhigh D1-D2 30062025 Fsign_compressed.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 3Form 3 Skyhigh D1-D2 30092025 F sign_compressed.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 1Form 1 SkyHigh Towers D1D2 31122025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 2Form 2 NWLLLP D1D2 31122025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 3Form 3 Skyhigh D1 D2 31122025 F sign.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 1Form 1 D1D2.pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 2Form 2 D1D2.pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 3Form 3 Skyhigh D1 D2 30032026 F sign_compressed.pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 1Form 1 Highsky Tower D1 D2.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 2Form 2- Skyhigh tower D1D2.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Skyhigh D1 D2 30062026 sign.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 1Form 1 Highsky Tower D1 D2.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 2Form 2- Skyhigh tower D1D2.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Skyhigh D1 D2 30062026 sign.pdf · uploaded 24 Jul 2026Source
  • Form 1Form1 SkyHigh D1D2 Mar 2025.pdf · uploaded 28 Jul 2026Source
  • Form 1Form1 SkyHigh D1D2 Mar 2025.pdf · uploaded 28 Jul 2026Source
  • Form 2Form2 SkyHigh D1D2 Mar 2025.pdf · uploaded 28 Jul 2026Source
  • Form 2Form 2 SkyHigh Towers D1D2.pdf · uploaded 28 Jul 2026Source
  • Form 3Form 3 SkyHigh Towers D1D2 mar 2025.pdf · uploaded 28 Jul 2026Source
  • Form 3Form 3 SkyHigh Towers D1D1 Dec 2024.pdf · uploaded 28 Jul 2026Source
  • Disclosure of Sold and Booked InventoryInventory D1D2.pdf · uploaded 28 Jul 2026Source
  • Disclosure of Sold and Booked InventoryInventory SkyHigh Towers D1D2 Dec 2024.pdf · uploaded 28 Jul 2026Source
  • OthersD1D2 layout and CC.pdf · uploaded 28 Jul 2026Source
  • OthersIOD Plans for SkyHigh Towers.pdf · uploaded 28 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2A SkyHigh Towers D1 D2.pdf · uploaded 3 Aug 2026Source
  • Form 5 (FY 2022-2023)Form 5 PC FY 22-23 SkyHigh Towers D1-D2_both sign.pdf · uploaded 3 Aug 2026Source
  • Form 5 (FY 2023-2024)form 5 SkyHigh Towers D1D2 31-03-2024.pdf · uploaded 3 Aug 2026Source
  • Form 5 (FY 2024-2025)Form 5_SkyHigh Towers D1-D2_FY 2024-2025 sign_compressed.pdf · uploaded 3 Aug 2026Source
  • Form 5 (FY 2018-2019)Form 5 2018-2019.pdf · uploaded 4 Aug 2026Source
  • Form 5 (FY 2020-2021)Form 5 2020-2021.pdf · uploaded 4 Aug 2026Source
  • Form 5 (FY 2021-2022)Form 5 2021-2022.pdf · uploaded 4 Aug 2026Source
  • Form 2A (FY 2024-2025)Form2A SkyHigh D1D2 Mar 2025_compressed_compressed.pdf · uploaded 11 Aug 2026Source
  • Form 5 (FY 2025-2026)Form 5_SkyHigh Towers D1-D2_FY 2025-26 Sign_compressed.pdf · uploaded 1 Oct 2026Source

Technical

  • Document1289-069 Phase II Wise Layout.pdf · uploaded 4 Apr 2018Source
  • DocumentSanction Plan.pdf · uploaded 5 Apr 2018Source
  • DocumentLayout PH2 D1 D2.pdf · uploaded 14 Aug 2019Source
  • DocumentLayout Plan-(1MB).pdf · uploaded 14 Aug 2019Source
  • Others01-21 Layout.pdf · uploaded 12 Nov 2025Source
  • Others240716 - CC.pdf · uploaded 12 Nov 2025Source
  • Document240716 - CC.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 01-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 02-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 03-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 04-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 05-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 06-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 07-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 08-21 - 2024 - D1.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 09-21 - 2024 - D1.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 10-21 - 2024 - D1.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 11-21 - 2024 - D2.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 12-21 - 2024 - D2.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 13-21 - 2024 - D2.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 14-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 15-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 16-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 17-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 18-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 19-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 20-21 - 2024.pdf · uploaded 22 Jul 2026Source
  • DocumentLayout Plans - 21-21 - 2024.pdf · uploaded 22 Jul 2026Source

Technical (Architect)

  • DocumentForm 1 D1-D2.pdf · uploaded 11 Nov 2024Source
  • DocumentForm 1 SkyHigh Towers D1D2-.pdf · uploaded 29 Jan 2025Source
  • DocumentForm1 SkyHigh D1D2 Mar 2025.pdf · uploaded 2 May 2025Source
  • DocumentForm 1 Highsky Tower D1 D2.pdf · uploaded 22 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2_SkyHigh Towers D1D2.pdf · uploaded 11 Nov 2024Source
  • DocumentForm 2 SkyHigh Towers D1D2.pdf · uploaded 29 Jan 2025Source
  • DocumentForm2 SkyHigh D1D2 Mar 2025.pdf · uploaded 2 May 2025Source
  • DocumentForm 2- Skyhigh tower D1D2.pdf · uploaded 22 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 3 Part, New S No. 277 Plot 2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK178 units in all
Address
New S No. 277 Plot 2 and 3 Part, Near Hinjewadi Phase 2, HinjewadiPIN 411057
Village
Man, Mulshi taluka
Land area for this project
784 sq m (8,437 sq ft)
Permissible built-up area
15,411 sq m (1,65,880 sq ft)
Sanctioned built-up area
15,411 sq m (1,65,880 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

3 PartNew S No. 277 Plot 2

Land as published on MahaRERA's project page

New S No. 277 Plot 2 and 3 Part

Boundaries

North
Future and completed phase
South
Amenity Space
East
Adjoining S No 341
West
15 M wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking178 units

168 of 178 units booked (94%), as the promoter reported to MahaRERA

2BHK · 132 units3BHK · 46 units
BuildingTypeCarpet areaUnitsBooked
D12BHK44.14 sq m · 475 sq ft2019
D12BHK44.38 sq m · 478 sq ft2018
D12BHK45.1 sq m · 485 sq ft11
D12BHK45.33 sq m · 488 sq ft22
D13BHK66.97 sq m · 721 sq ft2222
D13BHK67.3 sq m · 724 sq ft2422
D22BHK44.63 sq m · 480 sq ft11
D22BHK44.86 sq m · 483 sq ft2019
Show all 15 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
D22BHK44.87 sq m · 483 sq ft22
D22BHK45.1 sq m · 485 sq ft2018
D22BHK46.31 sq m · 498 sq ft11
D22BHK46.55 sq m · 501 sq ft22
D22BHK47.97 sq m · 516 sq ft11
D22BHK47.99 sq m · 517 sq ft2020
D22BHK48.23 sq m · 519 sq ft2220

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantKailash Agarwal—
Chartered accountantM A Agarwal And asso—
Chartered accountantPriyanka Chordiya and Associates—
Chartered accountantSAC & Co LLp—
EngineerManjiri Desai—

Source: MahaRERA project page. Contact details are not shown.