RERA projects in Lonikand
4 projects under 4 MahaRERA registrations, registered 2017–2025. 75% have a completion date extended beyond the one promised.
Locality
4RERA projects
4Registrations
1Completion still due3 past their completion date
9 monthsMedian extension beyond promised date75% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 0 |
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Lonikand
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Oxy Flora Phase 4Yogesh Developers | P52100080690 | 25 Jun 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| A P Pinnacle Phase 1A P Construction | P52100019457 | 1 Feb 2019 | 30 Mar 2024 | 30 Mar 2024 | Promised date passed | 0 |
| Aapla Ghar LonikandMIA Properties | P52100008033 | 18 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
| Rajesh East EnigmaRajesh Developers | P52100007846 | 18 Aug 2017 | 31 Mar 2018 | 31 Dec 2018 | Extended 9 mo | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- A P Construction1 project
- MIA Properties1 project
- Rajesh Developers1 project
- Yogesh Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology