Oxy Flora Phase 4
Deedo IDDP-PUN-JWP5Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.
Lonikand, Pune 412216 · by Yogesh Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 25 Jun 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100080690
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100080690 | 25 Jun 2025 | 31 Dec 2028 | 30 Apr 2029 | Yogesh Developers | Project page |
Documents72
2 documents held by Deedo, 70 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
Legal
Migrated
- 1 PAN Card1 PAN Card.pdf · uploaded 22 Feb 2025Source
Show all 72 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportsearch_0001_compressed (1).pdf · uploaded 22 Feb 2025Source
- 2 Copy of the legal title reportrera search_0001.pdf · uploaded 22 Feb 2025Source
- 1 Declaration in FORM BFORM B DEVE_0001.pdf · uploaded 22 Feb 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 22 Feb 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentN A.pdf · uploaded 22 Feb 2025Source
- 1 Building Plan Approval / NA Order for plotted development2 (1).pdf · uploaded 22 Feb 2025Source
- 1 Deviation Report with respect to Allotment letterNO DEVIATION ALLOTMENT_0001.pdf · uploaded 22 Feb 2025Source
- 1 Disclosure of Interest in Other Real Estate Organizationsannexture A_0001.pdf · uploaded 22 Feb 2025Source
- 1 a Details of encumbrances concerned to FinanceNO LITIGATION_0001.pdf · uploaded 15 Mar 2025Source
- 1 Copy of Layout Approval (in case of layout)1 (6).pdf · uploaded 15 Mar 2025Source
- 2 Copy of Layout Approval (in case of layout)2 (2).pdf · uploaded 15 Mar 2025Source
- 3 Copy of Layout Approval (in case of layout)3 (1).pdf · uploaded 15 Mar 2025Source
- 1 Proforma of Allotment letterAllotment 15-3.pdf · uploaded 15 Mar 2025Source
- 1 b Details of encumbrances concerned to LegalNO LITIGATION_0001.pdf · uploaded 15 Mar 2025Source
- 1 Declaration about Commencement CertificateFORMAT -D_0001.pdf · uploaded 19 Mar 2025Source
- 2 Other – Technicalclarification.pdf · uploaded 19 Mar 2025Source
- 1 Other – TechnicalANNEXURE A_0001.pdf · uploaded 19 Mar 2025Source
- 3 Other – TechnicalFor CC verification.pdf · uploaded 22 Mar 2025Source
- 1 Deviation Report with respect to model copy of AgreementNO DEVIATION AGREE_0001.pdf · uploaded 22 Mar 2025Source
- 4 Other – TechnicalCC Verifiecation EMAIL Acknowledgement.pdf · uploaded 28 Mar 2025Source
- 1 Proforma of Agreement for saleAgmt 28-3.pdf · uploaded 28 Mar 2025Source
- 1 CERSAI detailscersai_0001.pdf · uploaded 29 Mar 2025Source
- 2 a Details of encumbrances concerned to Financelegal and finance_0001.pdf · uploaded 22 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1_0001.pdf · uploaded 22 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2_0001.pdf · uploaded 22 Apr 2025Source
- 2 b Details of encumbrances concerned to Legallegal and finance_0001.pdf · uploaded 22 Apr 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)format b_0001.pdf · uploaded 22 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 UPDATES .pdf · uploaded 4 Jun 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A.pdf · uploaded 4 Jun 2025Source
- 1 Other – FinanceSELF DECLARATION.pdf · uploaded 4 Jun 2025Source
- 5 Other – TechnicalCersai declration.pdf · uploaded 4 Jun 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosur finance.pdf · uploaded 4 Jun 2025Source
- 2 Disclosure for secured/unsecured finance availed for the projectRelease Deed.pdf · uploaded 19 Jun 2025Source
- 3 Disclosure for secured/unsecured finance availed for the project140 Release Deed of Yogesh Developers_compressed.pdf · uploaded 19 Jun 2025Source
- 4 Disclosure for secured/unsecured finance availed for the projectDECLAARTION.pdf · uploaded 19 Jun 2025Source
- Form 1Form 1 Architect Certificate_0001.pdf · uploaded 4 Dec 2025Source
- Form 2Form 2 Engineers Certificate_0001.pdf · uploaded 4 Dec 2025Source
- Form 3Form 3 C A Certificate flora P-4 September qtr_0001.pdf · uploaded 4 Dec 2025Source
- Disclosure of Sold and Booked InventorySold -Booked p-4_0001.pdf · uploaded 4 Dec 2025View
- Form 1form 1.pdf · uploaded 22 Jan 2026Source
- Form 2form 2.pdf · uploaded 22 Jan 2026Source
- Form 3form 3.pdf · uploaded 22 Jan 2026Source
- Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 22 Jan 2026View
- Form 1Form 1 Flora Phase 4_0001.pdf · uploaded 26 May 2026Source
- Form 2Form 2 Flora phase 4_0001.pdf · uploaded 26 May 2026Source
- Form 3Form 3 Oxy Flora phase 4_0001.pdf · uploaded 26 May 2026Source
- Disclosure of Sold and Booked InventoryOxy Flora phase 4 sold inventory_0001.pdf · uploaded 26 May 2026View
- Form 2A (FY 2025-2026)Form 2 A flora phase 4_0001.pdf · uploaded 26 May 2026Source
- Form 2A (FY 2026-2027)Form 2 A flora phase 4_0001.pdf · uploaded 26 May 2026Source
- Form 1architect YD ph 4.pdf · uploaded 20 Jul 2026Source
- Form 2engineer certificate form 2 Ph 4.pdf · uploaded 20 Jul 2026Source
- Form 3Form 3 flora phase 4_0001.pdf · uploaded 20 Jul 2026Source
- Disclosure of Sold and Booked InventoryOxy flora phase 4 Sold-Booked inventory_0001.pdf · uploaded 20 Jul 2026View
Technical
- Document2 (1).pdf · uploaded 22 Feb 2025Source
- Document1 (6).pdf · uploaded 15 Mar 2025Source
- Document2 (2).pdf · uploaded 15 Mar 2025Source
- Document3 (1).pdf · uploaded 15 Mar 2025Source
- Other – TechnicalANNEXURE A_0001.pdf · uploaded 19 Mar 2025Source
- Other – Technicalclarification.pdf · uploaded 19 Mar 2025Source
- Other – TechnicalFor CC verification.pdf · uploaded 22 Mar 2025Source
- Other – TechnicalCC Verifiecation EMAIL Acknowledgement.pdf · uploaded 28 Mar 2025Source
- Other – TechnicalCersai declration.pdf · uploaded 4 Jun 2025Source
Technical (Architect)
- Documentform 1_0001.pdf · uploaded 22 Apr 2025Source
Technical (Engineer)
- Documentform 2_0001.pdf · uploaded 22 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 272 (Part), 275
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- Flat 201, Flat 202, Flat 203 landowner, Flat 204, Flat 205, Flat 206, Flat 207, Flat 208, Flat 209, Flat 210, Flat 211, Flat 302, Flat 303 landowner, Flat 305, Flat 306, Flat no 301, Flat no 304, Shop 1, Shop 10, Shop 101, Shop 102, Shop 103 landowner, Shop 104, Shop 105, Shop 106, Shop 107, Shop 108, Shop 109, Shop 11, Shop 110, Shop 12, Shop 2, Shop 3 landowner, Shop 4, Shop 5, Shop 6, Shop 7, Shop 8, Shop 939 units in all
- Address
- Gat No -271, 272 (Part), 275, 277 & 278 Lonikand, Tal-Haveli, Dist-Pune 412216, Pune Nagar RoadPIN 412216
- Village
- Loni-kand, Haveli taluka
- Location
- 18.62007, 74.02536
- Land area for this project
- 7,852 sq m (84,518 sq ft)
- Permissible built-up area
- 3,589 sq m (38,630 sq ft)
- Sanctioned built-up area
- 1,794 sq m (19,315 sq ft)
- Recreational open space
- 693 sq m (7,458 sq ft)
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Gat No -271 ,272 (Part),275,277 & 278 Lonikand ,Tal-Haveli,Dist-Pune 412216
Boundaries
- North
- Pune Nagar Road
- South
- Adj Gat No -270 Part
- East
- Adj Gat No-270 Part
- West
- Adj Gat No -272
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking39 units
0 of 39 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Flat 201 | 38.94 sq m · 419 sq ft | 1 | 0 |
| Flat 202 | 36.34 sq m · 391 sq ft | 1 | 0 |
| Flat 203 landowner | 36.34 sq m · 391 sq ft | 1 | 0 |
| Flat 204 | 41.05 sq m · 442 sq ft | 1 | 0 |
| Flat 205 | 35.36 sq m · 381 sq ft | 1 | 0 |
| Flat 206 | 23.65 sq m · 255 sq ft | 1 | 0 |
| Flat 207 | 23.69 sq m · 255 sq ft | 1 | 0 |
| Flat 208 | 26.32 sq m · 283 sq ft | 1 | 0 |
Show all 39 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Flat 209 | 37.11 sq m · 399 sq ft | 1 | 0 |
| Flat 210 | 27.78 sq m · 299 sq ft | 1 | 0 |
| Flat 211 | 27.97 sq m · 301 sq ft | 1 | 0 |
| Flat 302 | 36.34 sq m · 391 sq ft | 1 | 0 |
| Flat 303 landowner | 36.34 sq m · 391 sq ft | 1 | 0 |
| Flat 305 | 35.36 sq m · 381 sq ft | 1 | 0 |
| Flat 306 | 187.9 sq m · 2,023 sq ft | 1 | 0 |
| Flat no 301 | 38.94 sq m · 419 sq ft | 1 | 0 |
| Flat no 304 | 41.05 sq m · 442 sq ft | 1 | 0 |
| Shop 1 | 45.45 sq m · 489 sq ft | 1 | 0 |
| Shop 10 | 29.07 sq m · 313 sq ft | 1 | 0 |
| Shop 101 | 38.39 sq m · 413 sq ft | 1 | 0 |
| Shop 102 | 19.59 sq m · 211 sq ft | 1 | 0 |
| Shop 103 landowner | 19.59 sq m · 211 sq ft | 1 | 0 |
| Shop 104 | 21.67 sq m · 233 sq ft | 1 | 0 |
| Shop 105 | 30.48 sq m · 328 sq ft | 1 | 0 |
| Shop 106 | 23.73 sq m · 255 sq ft | 1 | 0 |
| Shop 107 | 24.04 sq m · 259 sq ft | 1 | 0 |
| Shop 108 | 24.35 sq m · 262 sq ft | 1 | 0 |
| Shop 109 | 24.04 sq m · 259 sq ft | 1 | 0 |
| Shop 11 | 29.38 sq m · 316 sq ft | 1 | 0 |
| Shop 110 | 24.35 sq m · 262 sq ft | 1 | 0 |
| Shop 12 | 37.06 sq m · 399 sq ft | 1 | 0 |
| Shop 2 | 44.48 sq m · 479 sq ft | 1 | 0 |
| Shop 3 landowner | 69.87 sq m · 752 sq ft | 1 | 0 |
| Shop 4 | 52.97 sq m · 570 sq ft | 1 | 0 |
| Shop 5 | 24.62 sq m · 265 sq ft | 1 | 0 |
| Shop 6 | 24.62 sq m · 265 sq ft | 1 | 0 |
| Shop 7 | 26.82 sq m · 289 sq ft | 1 | 0 |
| Shop 8 | 37.61 sq m · 405 sq ft | 1 | 0 |
| Shop 9 | 28.77 sq m · 310 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atit Admulwar Planners | — |
| Chartered accountant | Ritesh Shah | — |
| Chartered accountant | Yogesh D Mali | — |
| Engineer | Atul pachore | — |
| Engineer | Nilesh Raskar | — |
| Other | Arihant Cosulting Engineers LLP | — |
| Other | Equicom Structural Consultancy | — |
Source: MahaRERA project page. Contact details are not shown.