Deedo IDDP-PUN-GT2FCompletion was pushed back 4 months, to May 2027; no MahaRERA orders on record.
Kothrud, Pune 411038 · Property rates in Kothrud · by Re Nirmitee Projects
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to May 2027
- This projectRegistered 25 Aug 2023, completion promised 1 Jan 2027, revised to 1 May 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
- Primary sale · May 2026
- Primary sale · Dec 2025
- Primary sale · Nov 2025
- Primary sale · Oct 2025
- Primary sale · Aug 2025
- Primary sale · May 2025
- Primary sale · Mar 2025
- Primary sale · Mar 2025
- Primary sale · Feb 2025
- Primary sale · Mar 2024
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| May 2026 | Ved Anandghan · 702 | Primary sale | 628 sq ft | View Primary sale, May 2026 | |
| Dec 2025 | Main building · 703 | Primary sale | 947 sq ft | View Primary sale, Dec 2025 | |
| Nov 2025 | Main building · 401 | Primary sale | 646 sq ft | View Primary sale, Nov 2025 | |
| Oct 2025 | Main building · 303 | Primary sale | 925 sq ft | View Primary sale, Oct 2025 | |
| Aug 2025 | Main building · 202 | Primary sale | 623 sq ft | View Primary sale, Aug 2025 | |
| May 2025 | Main building · 502 | Primary sale | 623 sq ft | View Primary sale, May 2025 | |
| Mar 2025 | Main building · 402 | Primary sale | 623 sq ft | View Primary sale, Mar 2025 | |
| Mar 2025 | Main building · 201 | Primary sale | 646 sq ft | View Primary sale, Mar 2025 | |
| Feb 2025 | Main building · 501 | Primary sale | 646 sq ft | View Primary sale, Feb 2025 | |
| Mar 2024 | Main building · 603 | Primary sale | 902 sq ft | View Primary sale, Mar 2024 |
3 buildings
Open a building to see every flat, floor by floor.
- Building (P52100052437)Size not on record50% booked
- Main buildingSize not on record
- Main building91% built7 floors
Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100052437
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100052437 | 25 Aug 2023 | 1 Jan 2027 | 1 May 2027 | Re Nirmitee Projects | Project page |
Documents137
51 documents held by Deedo, 86 filings listed on MahaRERA's project page
Commencement certificate (3)
Show all 137 documentsShow fewer documents
Form 1 (6)
Form 2 (5)
Other (23)
- Other17 May 2025ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedView
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Document library
- Commencement Certificates / NA Order for plotted developmentCommencement Certificate.PDF · uploaded 1 Jul 2023View
- Declaration about Commencement CertificateDECLARATION ABOUT COM M ENCEM NT CERTI FICATE.PDF · uploaded 1 Jul 2023View
- Deviation Report with respect to Allotment letterDeviation Report with respect to Allotment letter.PDF · uploaded 1 Jul 2023View
- Deviation Report with respect to model copy of AgreementDeviation Report with respect to Agreement for Sale.PDF · uploaded 1 Jul 2023View
- Proforma of Agreement for saleAgreement For Sale.pdf · uploaded 1 Jul 2023View
- Proforma of Allotment letterAllotment Letter.pdf · uploaded 1 Jul 2023View
- Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 1 Jul 2023View
- Building Plan Approval / NA Order for plotted developmentBlue Print.pdf · uploaded 1 Jul 2023View
- Declaration in FORM BForm B.PDF · uploaded 1 Jul 2023View
- CERSAI detailsCERSAI Search Report.pdf · uploaded 1 Jul 2023View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.PDF · uploaded 4 Jul 2023View
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank Account for real estate projects.PDF · uploaded 10 Jul 2023View
- a Details of encumbrances concerned to FinanceDetails of encumbrances - Finance.PDF · uploaded 14 Jul 2023View
- b Details of encumbrances concerned to LegalDetails of encumbrances - Finance.PDF · uploaded 14 Jul 2023View
- CERSAI detailsDeclaration of CERSAI report.PDF · uploaded 14 Jul 2023View
- Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate organization.PDF · uploaded 19 Jul 2023View
- Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate organization.PDF · uploaded 19 Jul 2023View
- Copy of the legal title reportLegal Title Report.PDF · uploaded 21 Jul 2023View
- Other – LegalForm B.PDF · uploaded 28 Jul 2023View
- Commencement Certificates / NA Order for plotted developmentCommencement Certificate.PDF · uploaded 6 Nov 2023View
- Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 6 Nov 2023View
- Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 6 Nov 2023View
- Declaration about Commencement CertificateDECLARATION ABOUT COMM ENCEM NT CE RTI FICATE.PDF · uploaded 6 Nov 2023View
- Form 5 (FY 2023-2024)Re-Nirmitee Project - From-5-FY 23-24.pdf · uploaded 3 Oct 2024View
- Form 1Form 1_June 24.PDF · uploaded 3 Oct 2024View
- Form 2Form 2 June 24.pdf · uploaded 3 Oct 2024View
- Form 1Form 1_March 24.PDF · uploaded 3 Oct 2024View
- Form 2Form 2 31.03.2024.pdf · uploaded 3 Oct 2024View
- Form 1Form 1_Dec 23.PDF · uploaded 3 Oct 2024View
- Form 2Form 2 31.12.2023.pdf · uploaded 3 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sept 23.pdf · uploaded 10 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 23.PDF · uploaded 10 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 24.PDF · uploaded 10 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_June 24.PDF · uploaded 10 Oct 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 Sept 23.PDF · uploaded 10 Oct 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec 23.pdf · uploaded 10 Oct 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 24.pdf · uploaded 10 Oct 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 24.pdf · uploaded 10 Oct 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)From-5-FY 23-24.pdf · uploaded 10 Oct 2024View
- Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 15 Oct 2024View
- Disclosure of sold/ booked inventoryDis_Sept 23.PDF · uploaded 15 Oct 2024View
- Disclosure of sold/ booked inventoryDis_Dec 23.PDF · uploaded 15 Oct 2024View
- Disclosure of sold/ booked inventoryDis_March 24.PDF · uploaded 15 Oct 2024View
- Disclosure of sold/ booked inventoryDis_June 24.PDF · uploaded 15 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sept 23.pdf · uploaded 16 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 23.pdf · uploaded 16 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 24.pdf · uploaded 16 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_June 24.pdf · uploaded 16 Oct 2024View
- Form 1RE Nirmitee Prrojects form1.PDF · uploaded 15 May 2025View
- Form 2Re nirmitee Projects Form 2.pdf · uploaded 15 May 2025View
- Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold inventory.PDF · uploaded 15 May 2025View
- Form 1RE Nirmitee Prrojects form1.PDF · uploaded 15 May 2025View
- Form 2Re nirmitee Projects Form 2.pdf · uploaded 15 May 2025View
- Disclosure of Sold and Booked InventoryRenirmitee Form 3 March 25.PDF · uploaded 15 May 2025View
- Form 1Form 1.pdf · uploaded 17 May 2025View
- Form 2Form 2.pdf · uploaded 17 May 2025View
- Disclosure of Sold and Booked InventoryDisclosure of inventory.pdf · uploaded 17 May 2025View
- Withdrawal Update Form 1RE Nirmitee Prrojects form1.PDF · uploaded 17 May 2025View
- Withdrawal Update Form 1RE Nirmitee Prrojects form1.PDF · uploaded 17 May 2025View
- Withdrawal Update Form 2Re nirmitee Projects Form 2.pdf · uploaded 17 May 2025View
- Withdrawal Update Form 2Re nirmitee Projects Form 2.pdf · uploaded 17 May 2025View
- Withdrawal Update Form 1Renirmitee Form 1.PDF · uploaded 8 Oct 2025View
- Withdrawal Update Form 2Renirmitee Form 2.PDF · uploaded 8 Oct 2025View
- Withdrawal Update Form 1Form 1 RE Nirmitee.pdf · uploaded 12 Feb 2026View
- Withdrawal Update Form 2Renirmitee Form 2.pdf · uploaded 12 Feb 2026View
- Withdrawal Update Form 1Renirmitee form 1.PDF · uploaded 22 Apr 2026View
- Withdrawal Update Form 2Renirmitee form 2.PDF · uploaded 22 Apr 2026View
- Form 5 (FY 2024-2025)Form 5 2024-25.PDF · uploaded 3 Jun 2026View
- Form 5 (FY 2025-2026)Form 5 2025-26.PDF · uploaded 3 Jun 2026View
- Form 2A (FY 2023-2024)Form 2 A 2023-24.PDF · uploaded 8 Jun 2026View
- Form 2A (FY 2024-2025)Form 2 A 2024-25.PDF · uploaded 8 Jun 2026View
- Form 2A (FY 2025-2026)Form 2 A 2025-26.PDF · uploaded 8 Jun 2026View
- Withdrawal Update Form 1RP Form 1.PDF · uploaded 21 Jul 2026View
- Withdrawal Update Form 2RP Form 2.PDF · uploaded 21 Jul 2026View
- Withdrawal Update Form 1RP FORM 1.PDF · uploaded 29 Oct 2026View
- Withdrawal Update Form 2RP FORM 2.PDF · uploaded 29 Oct 2026View
Promoter documents
Technical documents
Other legal documents
- Other – LegalForm B.PDFView
Commencement certificates and NA orders
Proforma allotment letter
- Proforma allotment letterAllotment Letter.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 611, CTS No.611 · MCGM
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Active
- Address
- Plot No. 150, Survey No. 26 Hissa No. 1/2/3/4, CTS No.611, Kothrud, PunePIN 411038
- Village
- Kothrud, Haveli taluka
- Location
- 18.49161, 73.80134
- Land area for this project
- 602 sq m (6,477 sq ft)
- Permissible built-up area
- 1,921 sq m (20,679 sq ft)
- Sanctioned built-up area
- 1,921 sq m (20,679 sq ft)
- Planning authority
- MCGM
- Designated bank account
- Au Small Finance Bank Limited
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
- Also registered as
- Ved Anandaghan, वेद आनंदघन
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
611
Boundaries
- North
- By Plot No 151
- South
- By Colony Road
- East
- By 30 wide colony Road
- West
- By Plot No 142
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking0 parking spaces
0 units registered
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress2 buildings and areas
Work completed, as the promoter reported it to MahaRERA (Form 1)
Ved Anandghan
Show all 11 activitiesShow fewer activities
Common areas and amenities
Show all 15 activitiesShow fewer activities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shinde Joshi & Associates | — |
| Chartered accountant | Aghav Wavhal & Associates | — |
| Chartered accountant | Kailash R Mundada & Co | — |
| Engineer | Mahesh Baste | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kothrud
- SuramyaRERA PR1260002602717
- 1st Avenue - VinaykunjRERA PR1261012602185
- Yash Aura₹8,350 a sq ft
- Aqura IndraprasthaRERA PM1260002601531
- GurusevaRERA PR1260002601254
- Shree Ganesh Park Chsl₹12,610 a sq ft
- Shri Dattakrupa₹13,760 a sq ft
- Lotus SevaRERA PM1260002600759
All 4,695 projects in Kothrud · Compare Ved Anandghan with another project
Ved Anandghan in numbers
Registered deals, summarised
Deedo has 13 registered documents at Ved Anandghan, from Mar 2024 to Sep 2026: 10 sales, 2 leave and licence agreements, 1 mortgage. The median registered sale since Mar 2024 works out to about ₹17,000 per sq ft, at a median of ₹1.13 Cr a deal; 0% of sales were resales.
- What is the price per sq ft at Ved Anandghan?
- The median registered sale since Mar 2024 works out to about ₹17,000 per sq ft, at a median of ₹1.13 Cr a deal; 0% of sales were resales.
- How many properties have been sold at Ved Anandghan?
- 10 sales are registered at Ved Anandghan.
- Are properties at Ved Anandghan rented out?
- Yes: 2 leave and licence agreements are registered at Ved Anandghan.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Ved Anandghan by Deedo, last updated with deals registered in Sep 2026.
Latest deal · Primary sale · May 2026