Kothrud, Pune 411038 |Promoter: Aahan Builders Through Aniruddha Mukund Kulkarni

Residential / Group HousingRERAP52100053061
12 Oct 2023Registered with MahaRERA
31 Dec 2026Promised completion
30 Apr 2027Revised completionPushed back 4 months
1Building
21Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2.5BHK, 2BHK, 3.5BHK, 3BHK21 units in all
Address
Sr. No. 91, CTS No. 1077/9, Hissa No. 2, Plot No. 32, Kothrud North, Sr. No. 91, CTS No. 1077/9, Hissa No. 2, Plot No.32, Kothrud North, PunePIN 411038
Designated bank account
86
Developed in phases
No

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
12 Oct 2023
Promised
31 Dec 2026
Revised
30 Apr 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005306112 Oct 202331 Dec 202630 Apr 2027Aahan Builders Through Aniruddha Mukund KulkarniProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Anupam Apartment721

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 21 units booked (0%), as the promoter reported to MahaRERA

2.5BHK · 2 units2BHK · 12 units3.5BHK · 2 units3BHK · 5 units
TypeCarpet areaUnitsBooked
2.5BHK72.87 sq m · 784 sq ft10
2.5BHK79.99 sq m · 861 sq ft10
2BHK62.28 sq m · 670 sq ft30
2BHK72.13 sq m · 776 sq ft30
2BHK73.63 sq m · 793 sq ft10
2BHK81.2 sq m · 874 sq ft10
2BHK81.53 sq m · 878 sq ft10
2BHK81.61 sq m · 878 sq ft10
Show all 16 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK86.16 sq m · 927 sq ft10
2BHK88.78 sq m · 956 sq ft10
3.5BHK73.63 sq m · 793 sq ft10
3.5BHK75.66 sq m · 814 sq ft10
3BHK71.49 sq m · 770 sq ft10
3BHK76.8 sq m · 827 sq ft10
3BHK120.14 sq m · 1,293 sq ft20
3BHK120.17 sq m · 1,293 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 128 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardAniruddha's PAN card.pdf · uploaded 14 Jul 2023Source
  • Other – FinanceCERSAI 22Sept2023.pdf · uploaded 26 Sep 2023Source

Legal

  • Declaration Form BForm B- Promoter_compressed.pdf · uploaded 14 Jul 2023Source
  • Legal Title reportFoarmat A New_11zon.pdf · uploaded 29 Jul 2023Source
  • Legal Title reportLegal Report New_11zon.pdf · uploaded 16 Aug 2023Source
  • Other – LegalIOD (4).pdf · uploaded 31 Aug 2023Source

Migrated

  • 1 PAN CardAniruddha's PAN card.pdf · uploaded 14 Jul 2023Source
Show all 129 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceEncumbarance.pdf · uploaded 14 Jul 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbarance.pdf · uploaded 14 Jul 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 14 Jul 2023Source
  • 1 Declaration about Commencement CertificateDecleration of Commencement Cert.pdf · uploaded 14 Jul 2023Source
  • 1 Declaration in FORM BForm B- Promoter_compressed.pdf · uploaded 14 Jul 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnuxure.pdf · uploaded 14 Jul 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation For Allotment Letter.pdf · uploaded 14 Jul 2023Source
  • 1 Copy of Layout Approval (in case of layout)Maiin Layout_compressed.pdf · uploaded 15 Jul 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Sanction Plan_compressed.pdf · uploaded 15 Jul 2023Source
  • 1 Proforma of Allotment letterModel Allotment letter anupam_compressed.pdf · uploaded 15 Jul 2023Source
  • 1 Proforma of Agreement for saleAgreement to sale 29 July 23.pdf · uploaded 15 Jul 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same (22) (1).pdf · uploaded 15 Jul 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report for Agreetment to Sale_11zon.pdf · uploaded 15 Jul 2023Source
  • 1 Copy of the legal title reportFoarmat A New_11zon.pdf · uploaded 29 Jul 2023Source
  • 1 CERSAI detailsCERSAISearchReport.pdf · uploaded 29 Jul 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 04Oct23.pdf · uploaded 29 Jul 2023Source
  • 2 Copy of the legal title reportLegal Report New_11zon.pdf · uploaded 16 Aug 2023Source
  • 1 Other – LegalIOD (4).pdf · uploaded 31 Aug 2023Source
  • 1 Other – FinanceCERSAI 22Sept2023.pdf · uploaded 26 Sep 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 27 Feb 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2 anupam apartment.pdf · uploaded 29 Feb 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3 Aahan Builder 1.pdf · uploaded 29 Feb 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentHPSC0209_11zon.pdf · uploaded 22 Apr 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentHPSC0209_11zon.pdf · uploaded 22 Apr 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentHPSC0210_11zon.pdf · uploaded 22 Apr 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentHPSC0211_11zon.pdf · uploaded 22 Apr 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentHPSC0212_11zon.pdf · uploaded 22 Apr 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentHPSC0213_11zon.pdf · uploaded 22 Apr 2024Source
  • 8 Building Plan Approval / NA Order for plotted developmentHPSC0214_11zon.pdf · uploaded 22 Apr 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 3 Jun 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (9).pdf · uploaded 3 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)1.pdf · uploaded 3 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3A_organized.pdf · uploaded 3 Jun 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (8) (1).pdf · uploaded 10 Jun 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Engineer’s Certificate on Cost Incurred on Project (Form 2) (4).pdf · uploaded 10 Jun 2024Source
  • 1 Copy of Layout Approval (in case of layout)main layout_compressed (5).pdf · uploaded 15 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 15 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted development2-3.pdf · uploaded 15 Jan 2025Source
  • 2 Building Plan Approval / NA Order for plotted development3-3.pdf · uploaded 15 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)11zon_organized-PDF.pdf · uploaded 17 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Aahan BuildersForm 3 on 07032025 (2).pdf · uploaded 17 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)signed F2 (1).pdf · uploaded 17 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of2 jan 2024.pdf · uploaded 13 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 june 2024.pdf · uploaded 13 May 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3.pdf · uploaded 13 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ANUPAM APARTMENT Dec 2024 (1).pdf · uploaded 13 May 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ANUPAM APARTMENT Dec 2024 (1).pdf · uploaded 13 May 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Anupam form 2(2) (1).pdf · uploaded 13 May 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)anupam old form 2.pdf · uploaded 13 May 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Engineer’s Certificate on 26 feb 2025.pdf · uploaded 13 May 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 Engineer’s Certificate on 31 des 2024 1.pdf · uploaded 13 May 2025Source
  • 1 Disclosure of sold/ booked inventorydec mrch su.pdf · uploaded 13 May 2025Source
  • 2 Disclosure of sold/ booked inventorysigned sold unsold march 2024.pdf · uploaded 13 May 2025Source
  • Form 1Dec 2023 Form 1.pdf · uploaded 20 Aug 2025Source
  • Form 2Dec 2023 Form 2.pdf · uploaded 20 Aug 2025Source
  • Form 3Dec 2023 Form 3.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventoryDec 2023 A.pdf · uploaded 20 Aug 2025Source
  • Form 1March 2024 Form 1.pdf · uploaded 20 Aug 2025Source
  • Form 2March 2024 Form 2.pdf · uploaded 20 Aug 2025Source
  • Form 3March 2024 Form 3.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventoryMarch 2024 Sold Unsold.pdf · uploaded 20 Aug 2025Source
  • Form 1Jun 2024 Form 1.pdf · uploaded 20 Aug 2025Source
  • Form 2Jun 2024 Form 2.pdf · uploaded 20 Aug 2025Source
  • Form 3Jun 2024 Form 3 s.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventoryJun 24 Sold Unsold.pdf · uploaded 20 Aug 2025Source
  • Form 1Sep 2024 Form 1_compressed.pdf · uploaded 20 Aug 2025Source
  • Form 2Form 2 sep 24.pdf · uploaded 20 Aug 2025Source
  • Form 3Anupam Sept 2024 Form 3.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventorySep 24 Sold Unsold.pdf · uploaded 20 Aug 2025Source
  • Form 1March 2025 Form 1 s_compressed.pdf · uploaded 20 Aug 2025Source
  • Form 2Form 2 March 25.pdf · uploaded 20 Aug 2025Source
  • Form 3Anupam March 2025 Form 3.pdf · uploaded 20 Aug 2025Source
  • Disclosure of Sold and Booked InventoryMarch 2025 A Sold Unsold.pdf · uploaded 20 Aug 2025Source
  • Form 1Jun 2025 Anupm Apartment_compressed.pdf · uploaded 10 Oct 2025Source
  • Form 2ANUPAMA APARTMENT june 25 Form 2.pdf · uploaded 10 Oct 2025Source
  • Form 3Anupam CA Certificate Form 3..pdf · uploaded 10 Oct 2025Source
  • Disclosure of Sold and Booked InventoryJun 2024 Soil Unsold.pdf · uploaded 10 Oct 2025Source
  • Form 1Dec 2024 Anupam Apartment Form 1_compressed.pdf · uploaded 11 Oct 2025Source
  • Form 2ANUPAMA March 25 Form 2.pdf · uploaded 11 Oct 2025Source
  • Form 3Aahan BuildersForm 3 Dec 2024.pdf · uploaded 11 Oct 2025Source
  • Disclosure of Sold and Booked InventoryDec 24 Sold Unsold.pdf · uploaded 11 Oct 2025Source
  • Form 1Form 1 s_compressed (1).pdf · uploaded 14 Nov 2025Source
  • Form 2Anupam 2nd Quarter Engineer Certificate.pdf · uploaded 14 Nov 2025Source
  • Form 3Anupam Form 3 Sept 25.pdf · uploaded 14 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold unsold (1).pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2023-2024)Anupam 23 - 24.pdf · uploaded 12 Dec 2025Source
  • Form 2A (FY 2024-2025)Anupam 24 - 25.pdf · uploaded 12 Dec 2025Source
  • Form 5 (FY 2023-2024)FY 23-24 (1).pdf · uploaded 12 Dec 2025Source
  • Form 5 (FY 2024-2025)FY 24-25 (2) (1).pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 1Form 1 Anupam s.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 2Anupam Form 2 31st Mar 26 s.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 3Ms Aahan Builders Form -3 (1) (1) (1).pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 1Anupam Architect Certificate June 26..pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2Form 2 Anupam June 26.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3CA Certificate Jun 2026_compressed.pdf · uploaded 18 Sep 2026Source

Technical

  • DocumentMaiin Layout_compressed.pdf · uploaded 15 Jul 2023Source
  • DocumentBuilding Sanction Plan_compressed.pdf · uploaded 15 Jul 2023Source
  • DocumentHPSC0209_11zon.pdf · uploaded 22 Apr 2024Source
  • DocumentHPSC0209_11zon.pdf · uploaded 22 Apr 2024Source
  • DocumentHPSC0210_11zon.pdf · uploaded 22 Apr 2024Source
  • DocumentHPSC0211_11zon.pdf · uploaded 22 Apr 2024Source
  • DocumentHPSC0212_11zon.pdf · uploaded 22 Apr 2024Source
  • DocumentHPSC0213_11zon.pdf · uploaded 22 Apr 2024Source
  • DocumentHPSC0214_11zon.pdf · uploaded 22 Apr 2024Source
  • Documentmain layout_compressed (5).pdf · uploaded 15 Jan 2025Source
  • Document2-3.pdf · uploaded 15 Jan 2025Source
  • Document3-3.pdf · uploaded 15 Jan 2025Source

Technical (Architect)

  • Document11zon_organized-PDF.pdf · uploaded 17 Mar 2025Source
  • Document1 Architect’s Certificate of2 jan 2024.pdf · uploaded 13 May 2025Source
  • DocumentAnupam Architect Certificate June 26..pdf · uploaded 18 Sep 2026Source

Technical (Engineer)

  • Documentsigned F2 (1).pdf · uploaded 17 Mar 2025Source
  • DocumentANUPAM APARTMENT Dec 2024 (1).pdf · uploaded 13 May 2025Source
  • DocumentANUPAM APARTMENT Dec 2024 (1).pdf · uploaded 13 May 2025Source
  • DocumentAnupam form 2(2) (1).pdf · uploaded 13 May 2025Source
  • Documentanupam old form 2.pdf · uploaded 13 May 2025Source
  • Document7 Engineer’s Certificate on 26 feb 2025.pdf · uploaded 13 May 2025Source
  • Document8 Engineer’s Certificate on 31 des 2024 1.pdf · uploaded 13 May 2025Source
  • DocumentForm 2 Anupam June 26.pdf · uploaded 18 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Kothrud, Haveli taluka

Survey, CTS, gat or plot numbers

CTS No. 1077/9Hissa No. 2Plot No. 32Sr. No. 91

Boundaries

North
By Road
South
By Road
East
By CTS No 1077
West
By CTS No 1077

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectIndiocorp Designs Private Limited—
Chartered accountantS G Mundada & Co—
EngineerRohinee Engineers—