Deedo IDDP-PUN-VZ1RCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 60% of its units are booked.
Kiwale, Pune 412101 · Property rates in Kiwale · by Saniket Buildcon
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- P52100050643Registered 21 Apr 2023, completion promised 31 Jul 2027, revised to 30 Nov 2027.
- P52100079133Registered 10 Feb 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
2 registrations · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
7 buildings
Open a building to see every flat, floor by floor.
- B1 Wing21 floors · 84 units70% booked
- B2 Wing22 floors · 88 units77% booked
- B3 Wing22 floors · 88 units66% booked
- B4 Wing22 floors · 88 units91% booked
- Building - A Wing - A322 floors · 24 units0% booked
- Building - A Wing - A422 floors · 36 units0% booked
- Building - A Wing - A522 floors · 36 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrations2
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100050643 | 21 Apr 2023 | 31 Jul 2027 | 30 Nov 2027 | Saniket Buildcon | Project page |
| P52100079133 | 10 Feb 2025 | 31 Dec 2028 | 30 Apr 2029 | Saniket Buildcon | Project page |
Documents273
2 documents held by Deedo, 271 filings listed on MahaRERA's project page
Registration certificate (2)
Finance
- PAN CardP52100050643 · 1 PAN Card.pdf · uploaded 18 Mar 2023Source
- Other – FinanceP52100050643 · Rera Mhada letter-1-199_compressed.pdf · uploaded 13 Apr 2023Source
- PAN CardP52100079133 · SANIKET BUILDCON - PAN.pdf · uploaded 16 Nov 2024Source
- Other – FinanceP52100079133 · Latest Declaration - Landowner Bank Account.pdf · uploaded 28 Nov 2024Source
- Other – FinanceP52100079133 · Latest Declaration of Land Value - Form 3.pdf · uploaded 4 Dec 2024Source
- Other – FinanceP52100079133 · POA - Gaikwad.pdf · uploaded 23 Dec 2024Source
Show all 273 documentsShow fewer documents
Finance
Legal
- Legal Title reportP52100050643 · 1 Copy of the legal title report (5).pdf · uploaded 18 Mar 2023Source
- Legal Title reportP52100050643 · Supplementory Title Report 2022_compressed.pdf · uploaded 18 Mar 2023Source
- Declaration Form BP52100050643 · 1 Declaration in FORM B.pdf · uploaded 18 Mar 2023Source
- Legal Title reportP52100079133 · Latest Title Report - 1st Part.pdf · uploaded 28 Nov 2024Source
- Declaration Form BP52100079133 · Form B - Developer.pdf · uploaded 28 Nov 2024Source
- Other – LegalP52100079133 · Deed of Disolution.pdf · uploaded 27 Jan 2025Source
- Other – LegalP52100079133 · 7-12 Extract.pdf · uploaded 31 Jan 2025Source
- Other – LegalP52100079133 · AFS_Saniket Buildcon_The Rising Phase 2_11122024.pdf · uploaded 31 Jan 2025Source
- Other – LegalP52100079133 · Deviation Report - AFS - Revised payment terms_11zon.pdf · uploaded 31 Jan 2025Source
- Legal Title reportP52100079133 · Latest Flow of the Title - 2nd part compr.pdf · uploaded 31 Jan 2025Source
Migrated
- 1 PAN CardP52100050643 · 1 PAN Card.pdf · uploaded 18 Mar 2023Source
- 1 Copy of the legal title reportP52100050643 · 1 Copy of the legal title report (5).pdf · uploaded 18 Mar 2023Source
- 2 Copy of the legal title reportP52100050643 · Supplementory Title Report 2022_compressed.pdf · uploaded 18 Mar 2023Source
- 1 a Details of encumbrances concerned to FinanceP52100050643 · 1 a Details of encumbrances concerned to Finance.pdf · uploaded 18 Mar 2023Source
- 2 a Details of encumbrances concerned to FinanceP52100050643 · Legal Encumbrance Certificate (1).pdf · uploaded 18 Mar 2023Source
- 1 b Details of encumbrances concerned to LegalP52100050643 · 1 a Details of encumbrances concerned to Finance.pdf · uploaded 18 Mar 2023Source
- 2 b Details of encumbrances concerned to LegalP52100050643 · Legal Encumbrance Certificate (1).pdf · uploaded 18 Mar 2023Source
- 1 Copy of Layout Approval (in case of layout)P52100050643 · 1 Copy of Layout Approval (in case of layout) (1).pdf · uploaded 18 Mar 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100050643 · 1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentP52100050643 · 2 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentP52100050643 · 3 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentP52100050643 · 4 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentP52100050643 · 5 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentP52100050643 · 6 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 7 Building Plan Approval / NA Order for plotted developmentP52100050643 · 7 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 8 Building Plan Approval / NA Order for plotted developmentP52100050643 · 8 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 9 Building Plan Approval / NA Order for plotted developmentP52100050643 · 9 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100050643 · 1 Commencement Certificates _ NA Order for plotted development (3).pdf · uploaded 18 Mar 2023Source
- 1 Declaration about Commencement CertificateP52100050643 · 1 Declaration about Commencement Certificate.pdf · uploaded 18 Mar 2023Source
- 1 Declaration in FORM BP52100050643 · 1 Declaration in FORM B.pdf · uploaded 18 Mar 2023Source
- 1 CERSAI detailsP52100050643 · 1 CERSAI details.pdf · uploaded 18 Mar 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · New Form-3 CA Certificate_compressed.pdf · uploaded 18 Mar 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsP52100050643 · 1 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 18 Mar 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsP52100050643 · 2 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 18 Mar 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsP52100050643 · 3 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 18 Mar 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsP52100050643 · 4 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 18 Mar 2023Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsP52100050643 · 5 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 18 Mar 2023Source
- 1 Proforma of Allotment letterP52100050643 · 1 Proforma of Allotment letter.pdf · uploaded 18 Mar 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100050643 · 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same.pdf · uploaded 18 Mar 2023Source
- 1 Deviation Report with respect to Allotment letterP52100050643 · 1 Deviation Report with respect to Allotment letter.pdf · uploaded 18 Mar 2023Source
- 2 Copy of Layout Approval (in case of layout)P52100050643 · 1 OF 13 (1)_compressed.pdf · uploaded 20 Mar 2023Source
- 1 Proforma of Agreement for saleP52100050643 · AFS Revised Draft 29-03-2023.pdf · uploaded 29 Mar 2023Source
- 1 Deviation Report with respect to model copy of AgreementP52100050643 · AFS-Revised Deviation Report.pdf · uploaded 29 Mar 2023Source
- 1 Other – FinanceP52100050643 · Rera Mhada letter-1-199_compressed.pdf · uploaded 13 Apr 2023Source
- 1 Other – TechnicalP52100050643 · Rera Mhada letter-1-199_compressed.pdf · uploaded 13 Apr 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · FORM 1- Sept 2023.pdf · uploaded 21 Dec 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · Form 1 - July 2023.pdf · uploaded 21 Dec 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · FORM 2 - SEPT 23.pdf · uploaded 21 Dec 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · FORM 2 - JULY 2023.pdf · uploaded 21 Dec 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · FORM 3 - SEPT 23.pdf · uploaded 21 Dec 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · Form 3 - July 23.pdf · uploaded 21 Dec 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · Form 1 - The Rising as on Dec 2023.pdf · uploaded 12 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · Form 1 - The Rising as on Dec 2023.pdf · uploaded 18 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · FORM 2 - The Rising as on DEC 2023.pdf · uploaded 18 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100050643 · FORM 2A - The Rising as on FY 2022-23.pdf · uploaded 18 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · FORM 3 - The Rising as on DEC 2023.pdf · uploaded 18 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · FORM 1 - The Rising as on March 2024.pdf · uploaded 15 Apr 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · FORM 2 - The Rising as on March 2024.pdf · uploaded 15 Apr 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · FORM 3 - The Rising as on March 2024.pdf · uploaded 15 Apr 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · 5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf · uploaded 20 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · 4 Engineer’s Certificate on Cost Incurred on Project (Form 2) (4).pdf · uploaded 20 Apr 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · R.pdf · uploaded 20 Apr 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · Form 1 - July 2024.pdf · uploaded 27 Jul 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · Form 2 - July 2024.pdf · uploaded 27 Jul 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · Form 3- July 2024_11zon (1).pdf · uploaded 27 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100050643 · Quality Certificate - FY 2023-24.pdf · uploaded 29 Jul 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100050643 · Form 2A- July 2024.pdf · uploaded 30 Jul 2024Source
- 1 Disclosure of sold/ booked inventoryP52100050643 · Circular 29 - Saniket Buildcon_11zon.pdf · uploaded 7 Aug 2024Source
- 1 Copy of Layout Approval (in case of layout)P52100050643 · 1 OF 17 _12_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100050643 · CC-99-2024 Dated 7-10-2024.pdf · uploaded 17 Oct 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentP52100050643 · CC-99-2024 Dated 7-10-2024.pdf · uploaded 17 Oct 2024Source
- 10 Building Plan Approval / NA Order for plotted developmentP52100050643 · 11 OF 17 _3_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 6 Building Plan Approval / NA Order for plotted developmentP52100050643 · 7 of 17 _rotated.pdf · uploaded 17 Oct 2024Source
- 11 Building Plan Approval / NA Order for plotted developmentP52100050643 · 12 of 17 _2_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 12 Building Plan Approval / NA Order for plotted developmentP52100050643 · 13 of 17 _1_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 13 Building Plan Approval / NA Order for plotted developmentP52100050643 · 14 of 17 _15_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 14 Building Plan Approval / NA Order for plotted developmentP52100050643 · 15 of 17 _14_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 15 Building Plan Approval / NA Order for plotted developmentP52100050643 · 16 of 17 _13_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 16 Building Plan Approval / NA Order for plotted developmentP52100050643 · 16 of 17 _13_11zon_rotated_rotated.pdf · uploaded 17 Oct 2024Source
- 17 Building Plan Approval / NA Order for plotted developmentP52100050643 · 17 of 17 (1)_rotated.pdf · uploaded 17 Oct 2024Source
- 9 Building Plan Approval / NA Order for plotted developmentP52100050643 · 10 OF 17 _4_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 8 Building Plan Approval / NA Order for plotted developmentP52100050643 · 9 of 17 _5_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 7 Building Plan Approval / NA Order for plotted developmentP52100050643 · 8 OF 17_6_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentP52100050643 · 6 OF 17 _7_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentP52100050643 · 5 OF 17 _8_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentP52100050643 · 4 OF 17 _9_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentP52100050643 · 3 OF 17_10_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100050643 · 2 OF 17_11_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · Form 1 - Sept 24.pdf · uploaded 7 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · Form 3 - Sept 24.pdf · uploaded 7 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · Form 2 - Sept 24.pdf · uploaded 7 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100050643 · Form 2A- Sept 24.pdf · uploaded 7 Nov 2024Source
- 1 PAN CardP52100079133 · SANIKET BUILDCON - PAN.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100050643 · Form 5 - THE RISING for FY 2023-24.pdf · uploaded 26 Nov 2024Source
- 2 Copy of the legal title reportP52100079133 · Latest Title Report - 1st Part.pdf · uploaded 28 Nov 2024Source
- 1 a Details of encumbrances concerned to FinanceP52100079133 · Encrumbance Letter- Finance.pdf · uploaded 28 Nov 2024Source
- 2 a Details of encumbrances concerned to FinanceP52100079133 · Encrumbance Letter - Legal.pdf · uploaded 28 Nov 2024Source
- 1 Copy of Layout Approval (in case of layout)P52100079133 · Layout pg 1.pdf · uploaded 28 Nov 2024Source
- 1 Proforma of Allotment letterP52100079133 · Allotment letter_Saniket Buildcon_The Rising Phase 2_03122024.pdf · uploaded 28 Nov 2024Source
- 1 Declaration in FORM BP52100079133 · Form B - Developer.pdf · uploaded 28 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100079133 · Form 3 - The Rising Phase-2_11zon.pdf · uploaded 28 Nov 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100079133 · CC-99-2024 Dated 7-10-2024.pdf · uploaded 28 Nov 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100079133 · Layout pg 1.pdf · uploaded 28 Nov 2024Source
- 8 Building Plan Approval / NA Order for plotted developmentP52100079133 · Layout pg 8.pdf · uploaded 28 Nov 2024Source
- 7 Building Plan Approval / NA Order for plotted developmentP52100079133 · Layout pg 7.pdf · uploaded 28 Nov 2024Source
- 6 Building Plan Approval / NA Order for plotted developmentP52100079133 · Layout pg 6.pdf · uploaded 28 Nov 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentP52100079133 · Layout pg 5.pdf · uploaded 28 Nov 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentP52100079133 · Layout pg 4.pdf · uploaded 28 Nov 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentP52100079133 · Layout pg 3.pdf · uploaded 28 Nov 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentP52100079133 · Layout pg 2.pdf · uploaded 28 Nov 2024Source
- 1 Declaration about Commencement CertificateP52100079133 · Format-D - Declaration of CC.pdf · uploaded 28 Nov 2024Source
- 1 CERSAI detailsP52100079133 · Cersai Declaration.pdf · uploaded 28 Nov 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)P52100079133 · Format A- All RERA Designated bank accounts.pdf · uploaded 28 Nov 2024Source
- 1 Deviation Report with respect to Allotment letterP52100079133 · Deviation Report - AL.pdf · uploaded 28 Nov 2024Source
- 1 b Details of encumbrances concerned to LegalP52100079133 · Encrumbance Letter- Finance.pdf · uploaded 28 Nov 2024Source
- 2 b Details of encumbrances concerned to LegalP52100079133 · Encrumbance Letter - Legal.pdf · uploaded 28 Nov 2024Source
- 1 Other – FinanceP52100079133 · Latest Declaration - Landowner Bank Account.pdf · uploaded 28 Nov 2024Source
- 1 Other – TechnicalP52100079133 · Annexure A - Order No 50.pdf · uploaded 28 Nov 2024Source
- 1 Deviation Report with respect to model copy of AgreementP52100079133 · Deviation Report - AFS.pdf · uploaded 28 Nov 2024Source
- 1 Proforma of Agreement for saleP52100079133 · AFS_Saniket Buildcon_The Rising Phase 2_03122024.pdf · uploaded 28 Nov 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsP52100079133 · Annexure-A - Saniket Buildcon_11zon.pdf · uploaded 28 Nov 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P52100079133 · Format B - Declaration from the bank.pdf · uploaded 28 Nov 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectP52100079133 · Disclosure of Secured and Unsecured loan.pdf · uploaded 28 Nov 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentP52100079133 · CC Verification Mail - The Rising Phase - 2.pdf · uploaded 4 Dec 2024Source
- 2 Other – FinanceP52100079133 · Latest Declaration of Land Value - Form 3.pdf · uploaded 4 Dec 2024Source
- 2 Other – TechnicalP52100079133 · Plot Area Confirmation.pdf · uploaded 4 Dec 2024Source
- 3 Other – TechnicalP52100079133 · CC Verification Mail - The Rising Phase - 2.pdf · uploaded 4 Dec 2024Source
- 3 Other – FinanceP52100079133 · POA - Gaikwad.pdf · uploaded 23 Dec 2024Source
- 5 Other – FinanceP52100079133 · POA_ Sakrikar.pdf · uploaded 23 Dec 2024Source
- 4 Other – FinanceP52100079133 · POA - Sahasrabudhhe.pdf · uploaded 23 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · Form 1 - Jan-25.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · Form 3 - Jan 25_11zon.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · Form 2 - Jan-25.pdf · uploaded 20 Jan 2025Source
- 1 Other – LegalP52100079133 · Deed of Disolution.pdf · uploaded 27 Jan 2025Source
- 1 Copy of the legal title reportP52100079133 · Latest Flow of the Title - 2nd part compr.pdf · uploaded 31 Jan 2025Source
- 4 Other – LegalP52100079133 · Deviation Report - AFS - Revised payment terms_11zon.pdf · uploaded 31 Jan 2025Source
- 3 Other – LegalP52100079133 · AFS_Saniket Buildcon_The Rising Phase 2_11122024.pdf · uploaded 31 Jan 2025Source
- 2 Other – LegalP52100079133 · 7-12 Extract.pdf · uploaded 31 Jan 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100079133 · CC.pdf · uploaded 11 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100050643 · Form 1 - PHASE 1.pdf · uploaded 16 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100050643 · Form 3 - PHASE 1.pdf · uploaded 16 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100050643 · Form 2 - PHASE 1.pdf · uploaded 16 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100079133 · Form 1 - Phase 2.pdf · uploaded 16 Apr 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100079133 · Form 1 - Phase 2.pdf · uploaded 16 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100079133 · Form 3 - Phase 2.pdf · uploaded 16 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100079133 · Form 3 - Phase 2.pdf · uploaded 16 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100079133 · Form 2 - Phase 2.pdf · uploaded 16 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100079133 · Form 2 - Phase 2.pdf · uploaded 16 Apr 2025Source
- Form 1P52100079133 · Form 1 - Phase 2.pdf · uploaded 20 Jul 2025Source
- Form 2P52100079133 · Form 2 - Phase 2.pdf · uploaded 20 Jul 2025Source
- Form 3P52100079133 · Form 3 - Phase 2.pdf · uploaded 20 Jul 2025Source
- Disclosure of Sold and Booked InventoryP52100079133 · Circular 29 - Phase 2.pdf · uploaded 20 Jul 2025Source
- Withdrawal Update Form 1P52100079133 · Form 1 - The Rising Phase - 2 as on Sept 2025.pdf · uploaded 15 Dec 2025Source
- Withdrawal Update Form 2P52100079133 · Form 2 - The Rising Phase - 2 as on Sept 2025.pdf · uploaded 15 Dec 2025Source
- Withdrawal Update Form 3P52100079133 · Form 3 - The Rising Phase - 2 as on Sept 2025.pdf · uploaded 15 Dec 2025Source
- Withdrawal Update Form 1P52100050643 · Form 1 - The Rising as on June 2025.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 1P52100050643 · Form 1 - The Rising as on June 2025.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 1P52100050643 · Form 1 - The Rising as on Sept 2025.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 2P52100050643 · Form 2 - The Rising as on June 2025.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 2P52100050643 · Form 2 - The Rising as on June 2025.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 2P52100050643 · Form 2 - The Rising as on Sept 2025.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 3P52100050643 · Form 1 - The Rising as on June 2025.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 3P52100050643 · Form 3 - The Rising as on June 2025.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 3P52100050643 · Form 3 - The Rising as on Sept 2025.pdf · uploaded 19 Dec 2025Source
- Form 2A (FY 2024-2025)P52100079133 · Form 2A- Phase2 (2024-25).pdf · uploaded 13 Jan 2026Source
- Form 5 (FY 2024-2025)P52100079133 · Form 5 - Phase-2 Sept-25.pdf · uploaded 14 Jan 2026Source
- Withdrawal Update Form 1P52100050643 · Form 1- The Rising Phase 1 as on Dec 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 1P52100050643 · Form 1- The Rising Phase 1 as on Dec 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 2P52100050643 · Form 2- The Rising Phase 1 as on Dec 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 2P52100050643 · Form 2- The Rising Phase 1 as on Dec 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 3P52100050643 · Form 3- The Rising Phase 1 as on Dec 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 3P52100050643 · Form 3- The Rising Phase 1 as on Dec 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 1P52100079133 · Form 1 - The Rising Phase 2 as on Dec 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 2P52100079133 · Form 2 - The Rising Phase 2 as on Dec 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 3P52100079133 · Form 3 - The Rising Phase 2 as on Dec 2025_compressed.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 1P52100050643 · Form 1 - The Rising as on March 2026.pdf · uploaded 27 Apr 2026Source
- Withdrawal Update Form 2P52100050643 · Form 2 - The Rising as on March 2026.pdf · uploaded 27 Apr 2026Source
- Withdrawal Update Form 3P52100050643 · Form 3 - The Rising as on March 2026.pdf · uploaded 27 Apr 2026Source
- Withdrawal Update Form 1P52100079133 · Form 1 - The Rising Phase 2 as on March 2026.pdf · uploaded 27 Apr 2026Source
- Withdrawal Update Form 2P52100079133 · Form 2 - The Rising Phase 2 as on March 2026.pdf · uploaded 27 Apr 2026Source
- Withdrawal Update Form 3P52100079133 · Form 3 - The Rising Phase 2 as on March 2026.pdf · uploaded 27 Apr 2026Source
- Withdrawal Update Form 1P52100050643 · Form 1 -The Rising As on June 2026.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2P52100050643 · Form 2 -The Rising As on June 2026.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3P52100050643 · Form 3 -The Rising As on June 2026_compressed.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 1P52100079133 · Form 1 - The Rising Phase 2.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 2P52100079133 · Form 2 - Phase 2 (2).pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 3P52100079133 · Form 3 - the Rising Phase 2 (1)_compressed (1).pdf · uploaded 18 Jul 2026Source
- Form 5 (FY 2025-2026)P52100050643 · Form 5 - The Rising Fy 25-26.pdf · uploaded 6 Oct 2026Source
- Form 5 (FY 2025-2026)P52100079133 · The_Rising_Phase_-_2_Form5_2025-26_06-10-2026_15-45.pdf · uploaded 6 Oct 2026Source
Technical
- DocumentP52100050643 · 1 Copy of Layout Approval (in case of layout) (1).pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 2 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 3 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 4 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 5 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 6 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 7 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 8 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 9 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 18 Mar 2023Source
- DocumentP52100050643 · 1 OF 13 (1)_compressed.pdf · uploaded 20 Mar 2023Source
- Other – TechnicalP52100050643 · Rera Mhada letter-1-199_compressed.pdf · uploaded 13 Apr 2023Source
- DocumentP52100050643 · 1 OF 17 _12_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 2 OF 17_11_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 3 OF 17_10_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 4 OF 17 _9_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 5 OF 17 _8_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 6 OF 17 _7_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 7 of 17 _rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 8 OF 17_6_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 9 of 17 _5_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 10 OF 17 _4_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 11 OF 17 _3_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 12 of 17 _2_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 13 of 17 _1_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 14 of 17 _15_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 15 of 17 _14_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 16 of 17 _13_11zon_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 16 of 17 _13_11zon_rotated_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100050643 · 17 of 17 (1)_rotated.pdf · uploaded 17 Oct 2024Source
- DocumentP52100079133 · Layout pg 1.pdf · uploaded 28 Nov 2024Source
- DocumentP52100079133 · Layout pg 1.pdf · uploaded 28 Nov 2024Source
- DocumentP52100079133 · Layout pg 2.pdf · uploaded 28 Nov 2024Source
- DocumentP52100079133 · Layout pg 3.pdf · uploaded 28 Nov 2024Source
- DocumentP52100079133 · Layout pg 4.pdf · uploaded 28 Nov 2024Source
- DocumentP52100079133 · Layout pg 5.pdf · uploaded 28 Nov 2024Source
- DocumentP52100079133 · Layout pg 6.pdf · uploaded 28 Nov 2024Source
- DocumentP52100079133 · Layout pg 7.pdf · uploaded 28 Nov 2024Source
- DocumentP52100079133 · Layout pg 8.pdf · uploaded 28 Nov 2024Source
- Other – TechnicalP52100079133 · Annexure A - Order No 50.pdf · uploaded 28 Nov 2024Source
- Other – TechnicalP52100079133 · Plot Area Confirmation.pdf · uploaded 4 Dec 2024Source
- Other – TechnicalP52100079133 · CC Verification Mail - The Rising Phase - 2.pdf · uploaded 4 Dec 2024Source
- DocumentP52100079133 · 1 OF 20_highlighted__.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 2 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 3 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 4 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 5 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 6 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 7 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 8 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 9 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 10 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 11 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 12 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 13 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 14 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 15 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 16 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 17 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 18 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 19 OF 20_.pdf · uploaded 29 May 2026Source
- DocumentP52100079133 · 20 OF 20_.pdf · uploaded 29 May 2026Source
Technical (Architect)
- DocumentP52100050643 · Form 1 - Sept 24.pdf · uploaded 7 Nov 2024Source
- DocumentP52100050643 · Form 1 - Jan-25.pdf · uploaded 20 Jan 2025Source
- DocumentP52100050643 · Form 1 - PHASE 1.pdf · uploaded 16 Apr 2025Source
- DocumentP52100079133 · Form 1 - Phase 2.pdf · uploaded 16 Apr 2025Source
- DocumentP52100050643 · Form 1 -The Rising As on June 2026.pdf · uploaded 17 Jul 2026Source
- DocumentP52100079133 · Form 1 - The Rising Phase 2.pdf · uploaded 18 Jul 2026Source
Technical (Engineer)
- DocumentP52100050643 · Form 2 - Sept 24.pdf · uploaded 7 Nov 2024Source
- DocumentP52100050643 · Form 2 - Jan-25.pdf · uploaded 20 Jan 2025Source
- DocumentP52100050643 · Form 2 - PHASE 1.pdf · uploaded 16 Apr 2025Source
- DocumentP52100079133 · Form 2 - Phase 2.pdf · uploaded 16 Apr 2025Source
- DocumentP52100050643 · Form 2 -The Rising As on June 2026.pdf · uploaded 17 Jul 2026Source
- DocumentP52100079133 · Form 2 - Phase 2 (2).pdf · uploaded 18 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 67/2B/1, 67/2B/1/1(P) Mouje - Kiwale
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Phases
- 2
- Unit types
- 2BHK, 3BHK, 2BHK (MHADA), MHADA 2 BHK, Sale 2 BHK, Sale 3 BHK444 units in all
- Address
- Gat No. 67/2a/1 To 67/2a/5, 67/2b/1 And 67/2b/1/1 Kiwale, Adarsh Nagar, KiwalePIN 412101
- Village
- Kiwale, Haveli taluka
- Location
- 18.59468, 73.70954
- Land area for this project
- 8,943 sq m (96,262 sq ft)
- Permissible built-up area
- 40,934 sq m (4,40,608 sq ft)
- Sanctioned built-up area
- 34,934 sq m (3,76,025 sq ft)
- Recreational open space
- 1,880 sq m (20,235 sq ft)
- Designated bank account
- 171
- Developed in phases
- Yes
- Also registered as
- The Rising Phase - 2
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GAT NO. 67/2A/1 TO 67/2A/5, 67/2B/1 AND 67/2B/1/1 KIWALE
Boundaries
- North
- By Survey No 67 P
- South
- By Survey No 67 P And Road
- East
- By Survey No 67 P
- West
- By Survey No 67 P
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking444 units
265 of 444 units booked (60%), as the promoter reported to MahaRERA
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52100050643 | B1 Wing | 2BHK | 65.22 sq m · 702 sq ft | 42 | 31 |
| P52100050643 | B1 Wing | 2BHK | 68.44 sq m · 737 sq ft | 3 | 2 |
| P52100050643 | B1 Wing | 2BHK | 71.9 sq m · 774 sq ft | 1 | 1 |
| P52100050643 | B1 Wing | 3BHK | 89.16 sq m · 960 sq ft | 38 | 25 |
| P52100050643 | B2 Wing | 2BHK | 61.81 sq m · 665 sq ft | 21 | 16 |
| P52100050643 | B2 Wing | 2BHK | 62.42 sq m · 672 sq ft | 3 | 2 |
| P52100050643 | B2 Wing | 2BHK | 64.77 sq m · 697 sq ft | 1 | 1 |
| P52100050643 | B2 Wing | 2BHK | 65.22 sq m · 702 sq ft | 44 | 34 |
Show all 32 unit rowsShow fewer unit rows
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52100050643 | B2 Wing | 2BHK | 68.44 sq m · 737 sq ft | 1 | 1 |
| P52100050643 | B2 Wing | 3BHK | 79.84 sq m · 859 sq ft | 18 | 14 |
| P52100050643 | B3 Wing | 2BHK | 61.81 sq m · 665 sq ft | 17 | 15 |
| P52100050643 | B3 Wing | 2BHK | 62.42 sq m · 672 sq ft | 3 | 3 |
| P52100050643 | B3 Wing | 2BHK | 65.22 sq m · 702 sq ft | 32 | 28 |
| P52100050643 | B3 Wing | 2BHK (MHADA) | 50 sq m · 538 sq ft | 22 | 0 |
| P52100050643 | B3 Wing | 3BHK | 79.84 sq m · 859 sq ft | 14 | 12 |
| P52100050643 | B4 Wing | 2BHK | 65.22 sq m · 702 sq ft | 45 | 41 |
| P52100050643 | B4 Wing | 2BHK | 68.44 sq m · 737 sq ft | 3 | 3 |
| P52100050643 | B4 Wing | 2BHK | 71.9 sq m · 774 sq ft | 1 | 1 |
| P52100050643 | B4 Wing | 3BHK | 89.16 sq m · 960 sq ft | 39 | 35 |
| P52100079133 | Building - A Wing - A3 | MHADA 2 BHK | 48.18 sq m · 519 sq ft | 6 | 0 |
| P52100079133 | Building - A Wing - A3 | MHADA 2 BHK | 50 sq m · 538 sq ft | 18 | 0 |
| P52100079133 | Building - A Wing - A4 | Sale 2 BHK | 59.84 sq m · 644 sq ft | 1 | 0 |
| P52100079133 | Building - A Wing - A4 | Sale 2 BHK | 62.95 sq m · 678 sq ft | 9 | 0 |
| P52100079133 | Building - A Wing - A4 | Sale 2 BHK | 66.18 sq m · 712 sq ft | 1 | 0 |
| P52100079133 | Building - A Wing - A4 | Sale 2 BHK | 66.5 sq m · 716 sq ft | 18 | 0 |
| P52100079133 | Building - A Wing - A4 | Sale 3 BHK | 81.17 sq m · 874 sq ft | 7 | 0 |
| P52100079133 | Building - A Wing - A5 | Sale 2 BHK | 65.22 sq m · 702 sq ft | 2 | 0 |
| P52100079133 | Building - A Wing - A5 | Sale 2 BHK | 66.5 sq m · 716 sq ft | 16 | 0 |
| P52100079133 | Building - A Wing - A5 | Sale 2 BHK | 68.44 sq m · 737 sq ft | 1 | 0 |
| P52100079133 | Building - A Wing - A5 | Sale 2 BHK | 72.66 sq m · 782 sq ft | 1 | 0 |
| P52100079133 | Building - A Wing - A5 | Sale 2 BHK | 89.16 sq m · 960 sq ft | 1 | 0 |
| P52100079133 | Building - A Wing - A5 | Sale 2 BHK | 90.26 sq m · 972 sq ft | 15 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Engineer | Sunil Rakhunde | — | P52100079133 |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kiwale
- Miracle - IIRERA PR1260002601874
- Sukhwani Palmera Reserves Phase IRERA PR1260002601641
- BlessingsRERA PM1260002601556
- The Rising Phase-3RERA PR1262022601361
- CitrineRERA PR1260002601192
- Rudraksh HomeRERA PR1260002601195
- 73 ParkRERA PR1260002601181
- Mangalam StarviewRERA PM1260002601151
All 123 projects in Kiwale · Compare The Rising with another project