Saniket Buildcon

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
The RisingP52100050643Haveli2023Certificate Signed31 Jul 202730 Nov 2027+4 months
The RisingP52100079133Haveli2025Certificate Signed31 Dec 202830 Apr 2029+4 months
The Rising Phase-3PR1262022601361Kiwale2026Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • The Rising+4 mo
  • The Rising+4 mo
  • The Rising Phase-3On date

Track record notes

  • Longest extension on record: 4 months, for The Rising (P52100050643).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology