Deedo IDDL-PUN-KHED7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects331
Registrations349some projects hold several
Completion still due125169 past their date
Median extension4 months51% of registrations extended
Regulatory cases8on 9 projects
7 in 10 registrations run late here
349 MahaRERA registrations in Khed and the places within it
34 not yet due91 extended, not yet due169 past even the latest date55 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Khed
331 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Avasa ParklandNaiknavare Housing Development Pvt.ltd | Completed, extended 1 yr | — | — |
| Kohinoor HeightsAbbas Ayub Ansari | Due Feb 2027, extended 4 mo | — | — |
| Dwarkadhish Park Building DSai Datta Enterprises | Due Apr 2029, extended 4 mo | — | — |
| Sarangi ParadiseSai Propking Reality | Due Jun 2027 | — | 30% |
| Vrudhi HeightsRam Properties | Due Apr 2028, extended 4 mo | — | — |
| Avasa WoodlandNaiknavare Housing Development Pvt.ltd | 11 mo late | — | — |
| Classic AmrutClassic Infra | Due Feb 2027, extended 4 mo | — | 27% |
| The Urbana-N1 and N2Intercontinental Infrastructure Limited | Due Apr 2029, extended 4 mo | — | 11% |
| Br 24Anil Ramchandra Rakshe | Due Dec 2027, extended 4 mo | — | 25% |
| Vallabh HeightsG R Developers | Due Jan 2027, extended 4 mo | — | — |
| Gulmohar ApartmentSai Builders And Developers | 5 mo late | — | 68% |
| Avasa GrovelandNaiknavare Housing Developments Pvt Ltd | 1 yr 11 mo late | — | — |
| The Urbana-N5A and N5BIntercontinental Infrastructure Limited | Due Apr 2029, extended 4 mo | — | — |
| Pearl UniconShree Vijayalaxmi Developers | 11 mo late | — | — |
| Siddhivinayak ResidencyKate Builders | Due Jul 2027, extended 4 mo | — | 11% |
| AvasagrasslandNaiknavare Housing Developments Pvt. Ltd. | 1 yr 11 mo late | — | — |
| DnyangangaIndrayani Ventures | Due Jul 2033, extended 4 mo | — | — |
| Shiv Shakti HeightsSahyadri Buildcon | Due Apr 2028, extended 4 mo | — | — |
| Shree Jay Ganesh AishwaryamMahendra Sayaji Pacharane | Due Apr 2028, extended 4 mo | — | 33% |
| Sky View Residencymangesh vasant gundal | Due Feb 2028 | — | 14% |
| Shree Samarth ShrushtiJagdamba Developers | Due Jan 2027, extended 4 mo | — | — |
| PrimusSuraj Group Pramoters And Builders | Completed | — | — |
| Aarambha VastuSai Shagun Builders And Developers | Due Jun 2027, extended 4 mo | — | 37% |
| Chakan High StreetChakan Business Hub LLP | Due Apr 2027, extended 4 mo | — | — |
| 7 Sagar PlazaSagar Kaluram Patole | Due Dec 2026, extended 4 mo | — | 5% |
Nearby: other talukas in Pune
Most active promoters
- Jagrutsara Structures Llp21 projects
- Sara Builders & Developers7 projects
- Anand Deoram Tambe4 projects
- Naiknavare Housing Developments Pvt. Ltd4 projects
- Shivam Developers Pvt. Ltd4 projects
- Shree Sai Associates4 projects
- Intercontinental Infrastructure Limited3 projects
- Mahendra Sayaji Pacharane3 projects
- Mangesh Vasant Gundal3 projects
- Maple Estates3 projects
Khed, in questions
How many projects in Khed run late?
7 in 10 MahaRERA registrations (260 of 349): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khed by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology