Deedo IDDP-PUN-FP3CMahaRERA shows it completed, after its date was pushed back 5 years and 4 months; no MahaRERA orders on record; 56% of its units are booked.
Kharadi, Pune 411014 · Property rates in Kharadi · by Ajitkumar Suresh Londhe
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 5 years and 4 months
- This projectRegistered 1 Mar 2018, completion promised 10 Sep 2018, revised to 1 Jan 2024.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Nov 2026 | Main building · 1 | Rental | — | View Rental, Nov 2026 | |
| Jul 2025 | Main building · 1 | Rental | — | View Rental, Jul 2025 | |
| Dec 2022 | Not on record | Rental | — | View Rental, Dec 2022 | |
| Jun 2019 | Unit 3 | Mortgage | — | View Mortgage, Jun 2019 |
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100015486
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100015486 | 1 Mar 2018 | 10 Sep 2018 | 1 Jan 2024 | Ajitkumar Suresh Londhe | Project page |
Documents61
3 documents held by Deedo, 58 filings listed on MahaRERA's project page
Show all 61 documentsShow fewer documents
Legal
- Declaration Form BFORM-B FINAL.pdf · uploaded 27 Feb 2024Source
Migrated
- 1 Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 22 Feb 2018Source
- 1 Building Plan Approval (IOD)Plan.pdf · uploaded 22 Feb 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement certificates.pdf · uploaded 22 Feb 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architecture certificate.pdf · uploaded 22 Feb 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate.pdf · uploaded 22 Feb 2018Source
- 1 PAN Cardpan card.pdf · uploaded 27 Feb 2018Source
- 1 Copy of the legal title reportsearch report-ilovepdf-compressed.pdf · uploaded 27 Feb 2018Source
- 1 Details of encumbrancesnon cum.pdf · uploaded 27 Feb 2018Source
- 1 Declaration in FORM BForm b-ilovepdf-compressed.pdf · uploaded 27 Feb 2018Source
- 1 Certificates of CA (Form 3)ca cert-ilovepdf-compressed.pdf · uploaded 27 Feb 2018Source
- 1 Otherplan.pdf · uploaded 27 Feb 2018Source
- 1 Proforma of Allotment letteragreement-for-sale-annexure-a.pdf · uploaded 28 Feb 2018Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form5.pdf · uploaded 4 Dec 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form5.pdf · uploaded 4 Dec 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)ENGINEERS CERTIFICATE.pdf · uploaded 13 Dec 2019Source
- 1 Architect’s Certificate on Completion of Project (Form 4)ARCICTURE CERTIFICATE.pdf · uploaded 25 Dec 2019Source
- 2 Certificates of CA (Form 3)Form_3_maha_rera_ca_certificate.pdf · uploaded 9 Jan 2020Source
- 1 Declaration about Commencement Certificatecomersement certificate.pdf · uploaded 7 Mar 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A -20-21.pdf · uploaded 7 Mar 2022Source
- 1 Disclosure of sold/ booked inventoryCONSENT LETTER 7-3-22.pdf · uploaded 7 Mar 2022Source
- 1 CERSAI detailsSEARCH AND TITLE REPORT.pdf · uploaded 7 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 -2019-20.pdf · uploaded 7 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 -2020-21.pdf · uploaded 7 Mar 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM - 2A 1.pdf · uploaded 5 Apr 2022Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM - 2A.pdf · uploaded 5 Apr 2022Source
- 2 Disclosure of sold/ booked inventoryFORM-B.pdf · uploaded 5 Apr 2022Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 29 Apr 2022Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 29 Apr 2022Source
- 2 CERSAI detailsCERSAI REPORT.pdf · uploaded 29 Apr 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 -2019-20.pdf · uploaded 29 Apr 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 -2020-21.pdf · uploaded 29 Apr 2022Source
- 3 Disclosure of sold/ booked inventoryFORM 29 SOLD BOOK INVENTRY.pdf · uploaded 5 May 2022Source
- 4 Disclosure of sold/ booked inventoryFORM 29 SOLD BOOK INVENTRY.pdf · uploaded 6 May 2022Source
- 2 OtherFORM - B.pdf · uploaded 6 May 2022Source
- 5 Disclosure of sold/ booked inventoryFORM 29 SOLD BOOK INVENTRY.pdf · uploaded 10 May 2022Source
- 6 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD BOOKED INVENTORY.pdf · uploaded 12 May 2022Source
- 7 Disclosure of sold/ booked inventoryFORM 29 SOLD BOOK INVENTRY.pdf · uploaded 30 May 2022Source
- 8 Disclosure of sold/ booked inventoryFORM 29 SOLD BOOK INVENTRY.pdf · uploaded 2 Jun 2022Source
- 9 Disclosure of sold/ booked inventoryFORM 29 SOLD BOOK INVENTRY.pdf · uploaded 2 Jun 2022Source
- 10 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD UNSOLD.pdf · uploaded 2 Jun 2022Source
- 11 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD UNSOLD.pdf · uploaded 4 Jun 2022Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 8 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM-2 ENGINEER CERTIFICATE.pdf · uploaded 8 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM-2 ENGINEER CERTIFICATE.pdf · uploaded 8 Feb 2024Source
- 12 Disclosure of sold/ booked inventorySOLD BOOKED INVENTRY.pdf · uploaded 8 Feb 2024View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM-5.pdf · uploaded 8 Feb 2024Source
- 2 Declaration in FORM BFORM-B FINAL.pdf · uploaded 27 Feb 2024Source
- 3 CERSAI detailsCREDIA CERTIFICATE.pdf · uploaded 27 Feb 2024Source
Technical
Technical (Architect)
- DocumentFORM-1.pdf · uploaded 8 Feb 2024Source
Technical (Engineer)
- Documentengineer certificate.pdf · uploaded 22 Feb 2018Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 22/1/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Resindetial9 units in all
- Address
- 22/1/1, Pune, PunePIN 411014
- Village
- Kharadi
- Location
- 18.54633, 73.93640
- Land area for this project
- 554 sq m (5,963 sq ft)
- Permissible built-up area
- 8,03,334 sq m (86,47,007 sq ft)
- Sanctioned built-up area
- 8,03,334 sq m (86,47,007 sq ft)
- Recreational open space
- 275 sq m (2,960 sq ft)
- Designated bank account
- 35
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
22/1/1
Boundaries
- North
- 56575
- South
- 56575
- East
- 23560
- West
- 22010
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking9 units
5 of 9 units booked (56%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Resindetial | 47.64 sq m · 513 sq ft | 9 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Nisar Pathan | — |
| Chartered accountant | Ca Prutha Sunil Shah | — |
| Engineer | S R Consultant | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kharadi
- Ganga Altus Building GRERA PC1260002602605
- The MonarchRERA PM1260002601832
- Venkatesh Vanaya - Wing – N (MHADA)- Phase - 8RERA PR1261012601751
- Venkatesh Vanaya₹13,040 a sq ft
- 48 Willow By OxyRERA PM1260002601164
- Zen KodeRERA PC1260002600251
- HemantRERA PR1260002600119
- Edition MRERA PC1260002502564
All 3,136 projects in Kharadi · Compare Om Bhagyashree Construction with another project
Om Bhagyashree Construction in numbers
Registered deals, summarised
Deedo has 4 registered documents at Om Bhagyashree Construction, from Jun 2019 to Nov 2026: 3 leave and licence agreements, 1 mortgage.
- Are properties at Om Bhagyashree Construction rented out?
- Yes: 3 leave and licence agreements are registered at Om Bhagyashree Construction, at a median rent since Jun 2019 of about ₹7,000 a month with a deposit of about ₹10,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Om Bhagyashree Construction by Deedo, last updated with deals registered in Nov 2026.
Latest deal · Rental · Nov 2026