Venkatesh Vanaya
Completion due Sep 2032Kharadi, Pune 411014 |Promoter: Svbpl Homes Pvt Ltd
Project summary
As registered with MahaRERA
- RERA registrations
- 6
- Phases
- 6
- Buildings
- 11
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2030
PR1261012601206- Registered
- 16 Jul 2026
- Promised
- 31 Dec 2030
Completion promised for 31 Dec 2031
PC1261012601213- Registered
- 16 Jul 2026
- Promised
- 31 Dec 2031
Completion promised for 30 Jun 2031
PR1261012601229- Registered
- 20 Jul 2026
- Promised
- 30 Jun 2031
Completion promised for 31 Aug 2030
PR1261012601264- Registered
- 20 Jul 2026
- Promised
- 31 Aug 2030
Show 2 more registrations
Completion promised for 30 Sep 2032
PR1261012601239- Registered
- 20 Jul 2026
- Promised
- 30 Sep 2032
Completion promised for 30 Sep 2030
PR1261012601304- Registered
- 24 Jul 2026
- Promised
- 30 Sep 2030
6 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1261012601206 | 16 Jul 2026 | 31 Dec 2030 | — | Svbpl Homes Pvt Ltd | Project page |
| PC1261012601213 | 16 Jul 2026 | 31 Dec 2031 | — | Svbpl Homes Pvt Ltd | Project page |
| PR1261012601229 | 20 Jul 2026 | 30 Jun 2031 | — | Svbpl Homes Pvt Ltd | Project page |
| PR1261012601264 | 20 Jul 2026 | 31 Aug 2030 | — | Svbpl Homes Pvt Ltd | Project page |
| PR1261012601239 | 20 Jul 2026 | 30 Sep 2032 | — | Svbpl Homes Pvt Ltd | Project page |
| PR1261012601304 | 24 Jul 2026 | 30 Sep 2030 | — | Svbpl Homes Pvt Ltd | Project page |
11 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Floors with CC | Units |
|---|---|---|---|
| Venkatesh Wing-A | 0 | 2 | 0 |
| Venkatesh Wing B | 0 | 3 | 0 |
| Venkatesh Wing-C | 0 | 3 | 0 |
| Wing-D Wing-D | 21 | 25 | 144 |
| Wing-G Wing-G | 1 | 5 | 6 |
| Wing-H Wing-H | 21 | 25 | 84 |
| Wing-I Wing-I | 21 | 25 | 84 |
| Wing-J Wing-J | 21 | 25 | 84 |
| Wing K Wing-K | 21 | 25 | 126 |
| Wing-L Wing-L | 21 | 24 | 123 |
| Wing-M- Wing-M- | 2 | 3 | 16 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
6 documents held by Deedo
Registration certificates
- Registration certificatePR1261012601229 · 18 Aug 2026ViewSource
- Registration certificatePR1261012601206 · 21 Aug 2026ViewSource
- Registration certificatePR1261012601239 · 27 Aug 2026ViewSource
- Registration certificatePC1261012601213 · 7 Sep 2026ViewSource
- Registration certificatePR1261012601264 · 11 Sep 2026ViewSource
- Registration certificatePR1261012601304 · 17 Sep 2026ViewSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Kharadi
Survey, CTS, gat or plot numbers