RERA projects in Karve Nagar

49 projects under 49 MahaRERA registrations, registered 2017–2026. 47% have a completion date extended beyond the one promised.

Locality
49RERA projects
49Registrations
21Completion still due28 past their completion date
4 monthsMedian extension beyond promised date47% of registrations extended
3Regulatory caseson 3 projects
60Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20175
20183
20194
20202
20215
20227
20238
20244
20257
20264

Projects in Karve Nagar

49 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
KomalSrkd Landmark LLPP5210004723612 Oct 202230 Jun 202630 Jun 2026Promised date passed0
MukundKotibhaskar Infrastructures &Developers Pvt.Ltd.P5210004586015 Jun 202231 May 202431 May 2024Promised date passed0
PrajaktaVishva Gangotree BuildconP5210004604315 Jun 202230 Jun 202630 Jun 2026Promised date passed0
Anika Gokul NiwasAlok Arun ShethP5210004546519 May 202231 Dec 202631 Dec 2026Not yet due0
Vision HarmonyM/S Vista Vision Developers LLPP5210003341822 Feb 20225 Jun 20255 Jun 2025Promised date passed0
KBC Tower Karvenagar Business ComplexM/s Shri Sairaj AssociatesP521000307008 Sep 202128 Feb 202328 Feb 2025Extended 24 mo0
BlossomDigamber ParulekarP5210003003926 Jul 202131 Dec 202331 Dec 2023Promised date passed0
1 GoldleafGoldleaf RealtorsP5210002807231 Jan 202130 Sep 202630 Jan 2027Extended 4 mo0
Suyash Apartment CondominiumS S AssociatesP5210002799825 Jan 202130 Oct 202330 Oct 2023Promised date passed0
Le SkylarkKakade Green Estates Private LimitedP521000277973 Jan 202115 Dec 202615 Apr 2027Extended 4 mo0
Parth Enclave Building FParth DevelopersP5210002556628 Jun 202030 Sep 202324 Mar 2025Extended 18 mo0
Lolage Cornershrinivas tukaram badveP5210002422027 Jan 202030 Mar 202530 Mar 2025Promised date passed0
VaishnaviVaishnavi DevelopersP521000218768 Aug 201931 Jul 202331 Jul 2023Promised date passed0
ManomayGokhale Buildcon LLPP521000215235 Jul 201930 Dec 202230 Dec 2022Promised date passed0
Pentagon TowersRaichandani Constructions & DevelopersP5210002122314 Jun 201930 Mar 20231 Jul 2024Extended 16 mo0
AshirwadAshok Ramjibhai RathodP5210001996615 Mar 201930 Jun 202129 Dec 2022Extended 18 mo0
Shades Of TradeKakade Green Estates Private LimitedP5210001785424 Sep 201810 Nov 202210 Nov 2022Promised date passed1
Nirman RiversideGururaj Narsinha JoshiP5210001688720 Jun 201830 Dec 202230 Dec 2022Promised date passed0
Krishnai Plazanitin shamrao patilP521000147652 Jan 201831 May 201820 May 2019Extended 12 mo0
Shewale ParkShewale & SonsP521000126547 Sep 201731 Mar 201831 Mar 2018Promised date passed0
Suvela ApartmentsFengse BrothersP5210000837818 Aug 201730 Dec 202330 Dec 2023Promised date passed0
River Dale ResidencyMaha Anand Pinnac AssociatesP521000049529 Aug 201730 Jun 202231 Aug 2025Extended 38 mo0
GopalkrupaLagoo ApteP521000034795 Aug 201731 Dec 201831 Dec 2018Promised date passed0
Parth Enclave E BuildingParth DevelopersP5210000067819 Jul 201731 Aug 201831 Aug 2018Promised date passed0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Kotibhaskar Infrastructures &Developers Pvt.Ltd.3 projects
  2. Kakade Green Estates Private Limited2 projects
  3. Parth Developers2 projects
  4. Ranade Realtors LLP2 projects
  5. Urban Realty2 projects
  6. Alok Arun Sheth1 project
  7. AMS Homes1 project
  8. Ashok Ramjibhai Rathod1 project
  9. Badhekar Properties1 project
  10. Bhagyashree Niwas Hsg Soc Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology