Epic Phase 3
Deedo IDDP-PUN-A4NHIts promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 75% of its units are booked.
Haveli, Maharashtra 411027 · Property rates in Haveli · by Yashada World · 33% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 30 Aug 2021, completion promised 30 Jun 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- A Building-Part14 floors · 4 units100% booked
- B Building-Part14 floors · 4 units100% booked
- C Building-Part14 floors · 4 units50% booked
- D Building-Part14 floors · 4 units50% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100030550
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100030550 | 30 Aug 2021 | 30 Jun 2025 | 30 Jun 2025 | Yashada World | Project page |
Documents47
2 documents held by Deedo, 45 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardYashada World Pan Card.pdf · uploaded 13 Aug 2021Source
Legal
Show all 47 documentsShow fewer documents
Migrated
- 1 Declaration about Commencement CertificateDECLARATION FOR EPIC.pdf · uploaded 13 Aug 2021Source
- 1 Declaration in FORM BDecalaration Form B 30 Dec 2020.pdf · uploaded 13 Aug 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED-compressed.pdf · uploaded 18 Aug 2021Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN - 01-compressed.pdf · uploaded 20 Aug 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentPLAN NO - 10 11th floor.pdf · uploaded 20 Aug 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Letter Dated 2020 08 13 Phase III.pdf · uploaded 20 Aug 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Epic- Engineers Certificate _14082021103817.PDF · uploaded 20 Aug 2021Source
- 1 Proforma of Allotment letterLetter of Allotment.pdf · uploaded 20 Aug 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentPLAN NO - 5 11th floor.pdf · uploaded 21 Aug 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCC - EPIC -2021.pdf · uploaded 21 Aug 2021Source
- 2 Proforma of Allotment letterAgreement RERA - Phase III - EPIC -21-08-2021.pdf · uploaded 21 Aug 2021Source
- 1 CERSAI detailsCERSAI Search Report 200250830833 EPIC.PDF · uploaded 9 Nov 2022Source
- 1 Disclosure of sold/ booked inventorySold unsold epic sold unsold sept 2022.pdf · uploaded 28 Dec 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Cert-Epic-Ph-III-31-03-2022.PDF · uploaded 19 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A-Epic-Ph-III-31-03-2022.PDF · uploaded 19 Jan 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)EPIC-PH 3 FORM 3 31-03-2022.PDF · uploaded 19 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Yashada World EPIC Form 5 Phase III 21 22.pdf · uploaded 13 Feb 2023Source
- 2 Disclosure of sold/ booked inventoryEPIC (1).pdf · uploaded 30 May 2023View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Epic 3_31052023160346.pdf · uploaded 1 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form2A Epic Ph 3 22-23.PDF · uploaded 5 Jul 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Epic Ph-III March 2022.pdf · uploaded 1 Aug 2023Source
- 2 a Details of encumbrances concerned to FinanceEpic three legal encumbrance 23082023121431.PDF · uploaded 23 Aug 2023Source
- 1 b Details of encumbrances concerned to LegalEpic three legal encumbrance 23082023121431.PDF · uploaded 23 Aug 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Epic Ph-3 June 2023 (1).pdf · uploaded 23 Aug 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameEpic three ac decalaration 23082023121321.PDF · uploaded 23 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)ph-3 2022-2023.pdf · uploaded 10 Nov 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 epic ph 3 dec 2023.pdf · uploaded 8 Feb 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Y world phase iii DEC 2023.pdf · uploaded 8 Feb 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Epic phase 3 UP TO 31 3 2024.pdf · uploaded 22 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2a ph3_17072024130115.PDF · uploaded 17 Jul 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Epic phase 3 form 1_31072024162813.PDF · uploaded 31 Jul 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Epic phase 3 form 2_31072024163120.PDF · uploaded 31 Jul 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)EPIC PHASE 3- FORM 2-MARCH 2024.PDF · uploaded 18 Oct 2024Source
Technical
Technical (Architect)
- DocumentEpic phase 3 form 1_31072024162813.PDF · uploaded 31 Jul 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK 11TH FLOOR, 3BHK 11TH FLOOR16 units in all
- Address
- S.no.18/1/1 P Pimple Nilakh, Dp Road, VishalnagarPIN 411027
- Village
- Pimpri Chinchawad (M Corp.), Haveli taluka
- Land area for this project
- 501 sq m (5,393 sq ft)
- Permissible built-up area
- 12,000 sq m (1,29,167 sq ft)
- Sanctioned built-up area
- 10,000 sq m (1,07,639 sq ft)
- Designated bank account
- 109
- Developed in phases
- Yes
Land as published on MahaRERA's project page
S.NO.18/1/1 P PIMPLE NILAKH
Boundaries
- North
- S No 19
- South
- S No 18 Remaining
- East
- 12 Mtr Dp Road
- West
- S No 18 Remaining
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking16 units
12 of 16 units booked (75%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Building-Part | 2BHK 11TH FLOOR | 60.32 sq m · 649 sq ft | 1 | 1 |
| A Building-Part | 2BHK 11TH FLOOR | 68.03 sq m · 732 sq ft | 1 | 1 |
| A Building-Part | 3BHK 11TH FLOOR | 110.09 sq m · 1,185 sq ft | 1 | 1 |
| A Building-Part | 3BHK 11TH FLOOR | 110.16 sq m · 1,186 sq ft | 1 | 1 |
| B Building-Part | 2BHK 11TH FLOOR | 60.13 sq m · 647 sq ft | 1 | 1 |
| B Building-Part | 2BHK 11TH FLOOR | 67.31 sq m · 725 sq ft | 1 | 1 |
| B Building-Part | 3BHK 11TH FLOOR | 104.76 sq m · 1,128 sq ft | 1 | 1 |
| B Building-Part | 3BHK 11TH FLOOR | 105.59 sq m · 1,137 sq ft | 1 | 1 |
Show all 16 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| C Building-Part | 2BHK 11TH FLOOR | 70.91 sq m · 763 sq ft | 1 | 0 |
| C Building-Part | 2BHK 11TH FLOOR | 73.49 sq m · 791 sq ft | 1 | 0 |
| C Building-Part | 3BHK 11TH FLOOR | 93.11 sq m · 1,002 sq ft | 1 | 1 |
| C Building-Part | 3BHK 11TH FLOOR | 99.5 sq m · 1,071 sq ft | 1 | 1 |
| D Building-Part | 2BHK 11TH FLOOR | 66.47 sq m · 715 sq ft | 1 | 0 |
| D Building-Part | 2BHK 11TH FLOOR | 66.6 sq m · 717 sq ft | 1 | 1 |
| D Building-Part | 2BHK 11TH FLOOR | 74.28 sq m · 800 sq ft | 1 | 0 |
| D Building-Part | 2BHK 11TH FLOOR | 75.79 sq m · 816 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sankalp Designers Vinod Chitnis | — |
| Architect | Vaibhav Jain | — |
| Chartered accountant | Mahesh Ghare | — |
| Engineer | Hiralal Bhaskar Sonawnae | — |
| Engineer | Prasad Kulkarni | — |
| Other | G A Bhilare Consultants | — |
| Other | Strudcom Consultants | — |