Skip to content

D Building-Part · Epic Phase 3

Haveli · RERA P52100030550

IDBLD_03036914 floorsPromised date passed
14Sanctioned habitable floorsregistration certificate
30 Jun 2025Revised completionpromised 30 Jun 2025
2 of 4Units bookedMahaRERA project page

Floors

14 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100030550 · registered 30 Aug 2021
Promised completion
30 Jun 2025
Revised completion
30 Jun 2025
Sanctioned habitable floors
14
ProjectId
30,138
ProjectName
EPIC PHASE 3
TotalUnitCount
0
ProjectBuildingId
60,244
BuildingNameNumber
D BUILDING-PART
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100030550
ProjectBuildingWingsId
60,244
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
D BUILDING-PART
NoOfBuildingWingFloorProposed
14
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
14

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK 11TH FLOOR66.5 m² (715 sq.ft)10
2BHK 11TH FLOOR66.6 m² (717 sq.ft)11
2BHK 11TH FLOOR74.3 m² (800 sq.ft)10
2BHK 11TH FLOOR75.8 m² (816 sq.ft)11
Total42
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology