Haveli · RERA P52100030550
IDBLD_03036714 floorsPromised date passed
14Sanctioned habitable floorsregistration certificate
30 Jun 2025Revised completionpromised 30 Jun 2025
4 of 4Units bookedMahaRERA project page
Floors
14 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100030550 · registered 30 Aug 2021
- Promised completion
- 30 Jun 2025
- Revised completion
- 30 Jun 2025
- Sanctioned habitable floors
- 14
- ProjectId
- 30,138
- ProjectName
- EPIC PHASE 3
- TotalUnitCount
- 0
- ProjectBuildingId
- 60,242
- BuildingNameNumber
- B BUILDING-PART
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100030550
- ProjectBuildingWingsId
- 60,242
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- B BUILDING-PART
- NoOfBuildingWingFloorProposed
- 14
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 14
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK 11TH FLOOR | 60.1 m² (647 sq.ft) | 1 | 1 |
| 2BHK 11TH FLOOR | 67.3 m² (725 sq.ft) | 1 | 1 |
| 3BHK 11TH FLOOR | 104.8 m² (1,128 sq.ft) | 1 | 1 |
| 3BHK 11TH FLOOR | 105.6 m² (1,137 sq.ft) | 1 | 1 |
| Total | 4 | 4 |