Commercial · 1 building · 67 unitsRERA P52100012963

Mst Aspire

Deedo IDDP-PUN-YQNY

Completion was pushed back 6 years to May 2025, and that date has passed too; no MahaRERA orders on record; 33% of its units are booked.

Dhanori, Pune 411047 · Property rates in Dhanori · by Mst Group

Delivery7 yrs 6 mo latePromised May 2019 · revised May 2025 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales33% booked22 of 67 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 6 years to May 2025, and that date has passed too

  • This projectRegistered 7 Sep 2017, completion promised 18 May 2019, revised to 6 May 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Sep 2025Mst Aspire A-Wing · 2Rental—View Rental, Sep 2025

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100012963
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000129637 Sep 201718 May 20196 May 2025Mst GroupProject page
Documents31

2 documents held by Deedo, 29 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN.pdf · uploaded 29 Aug 2017Source

Legal

  • OtherNon Agri Certificate.pdf · uploaded 29 Aug 2017Source
  • Declaration Form BANN-B.pdf · uploaded 29 Aug 2017Source
  • Legal Title reportTITLE.pdf · uploaded 29 Aug 2017Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 29 Aug 2017Source
  • 1 Copy of the legal title reportTITLE.pdf · uploaded 29 Aug 2017Source
Show all 31 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesPARTNERSHIP.pdf · uploaded 29 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)2.pdf · uploaded 29 Aug 2017Source
  • 1 Building Plan Approval (IOD)1 (1).pdf · uploaded 29 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate(1).pdf · uploaded 29 Aug 2017Source
  • 1 Declaration in FORM BANN-B.pdf · uploaded 29 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECH.pdf · uploaded 29 Aug 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER.pdf · uploaded 29 Aug 2017Source
  • 1 Certificates of CA (Form 3)CA-MST.pdf · uploaded 29 Aug 2017Source
  • 1 Certificates of CA (Form 5)CA-MST.pdf · uploaded 29 Aug 2017Source
  • 1 Proforma of Allotment letterNon Agri Certificate.pdf · uploaded 29 Aug 2017Source
  • 1 OtherNon Agri Certificate.pdf · uploaded 29 Aug 2017Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)MST COMPLET.pdf · uploaded 8 Dec 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)MST-BS.pdf · uploaded 8 Dec 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)MST-PL.pdf · uploaded 8 Dec 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Engineers Certificate on Quality Assurance 2020.pdf · uploaded 29 Jul 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineers Certificate on Quality Assurance 2021.pdf · uploaded 29 Jul 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineers Certificate on Quality Assurance 2022.pdf · uploaded 29 Jul 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineers Certificate on Quality Assurance 2023.pdf · uploaded 29 Jul 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Engineers Certificate on Quality Assurance 2024.pdf · uploaded 29 Jul 2025Source

Technical

  • Document1 (1).pdf · uploaded 29 Aug 2017Source
  • Document2.pdf · uploaded 29 Aug 2017Source

Technical (Architect)

  • DocumentARCHITECH.pdf · uploaded 29 Aug 2017Source

Technical (Engineer)

  • DocumentENGINEER.pdf · uploaded 29 Aug 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S NO.283 5 PART

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK, 4BHK, Shop67 units in all
Address
S No.283 5 Part, Airport Road, Kasturba Hsg.societyPIN 411047
Village
Dhanori
Land area for this project
3,847 sq m (41,411 sq ft)
Permissible built-up area
3,847 sq m (41,411 sq ft)
Sanctioned built-up area
3,245 sq m (34,928 sq ft)
Recreational open space
313 sq m (3,367 sq ft)
Designated bank account
203
Developed in phases
No

Survey, CTS, gat or plot numbers

S NO.283 5 PART

Land as published on MahaRERA's project page

S NO.283 5 PART

Boundaries

North
S No 283 Part
South
Road 24 M Wide
East
S No 283 Part
West
Road 24 M Wide

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking67 units

22 of 67 units booked (33%), as the promoter reported to MahaRERA

1BHK · 25 units2BHK · 27 units3BHK · 8 units4BHK · 1 unitShop · 6 units
TypeCarpet areaUnitsBooked
1BHK45.25 sq m · 487 sq ft20
1BHK45.56 sq m · 490 sq ft70
1BHK45.63 sq m · 491 sq ft33
1BHK46.38 sq m · 499 sq ft64
1BHK47.68 sq m · 513 sq ft63
1BHK70.26 sq m · 756 sq ft10
2BHK68.87 sq m · 741 sq ft71
2BHK69.89 sq m · 752 sq ft22
Show all 26 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK69.9 sq m · 752 sq ft41
2BHK71 sq m · 764 sq ft22
2BHK73.09 sq m · 787 sq ft40
2BHK76.34 sq m · 822 sq ft50
2BHK77.32 sq m · 832 sq ft11
2BHK79.46 sq m · 855 sq ft11
2BHK86.89 sq m · 935 sq ft10
3BHK86.61 sq m · 932 sq ft10
3BHK89.82 sq m · 967 sq ft20
3BHK90.52 sq m · 974 sq ft44
3BHK95.44 sq m · 1,027 sq ft10
4BHK120.26 sq m · 1,294 sq ft10
Shop15.57 sq m · 168 sq ft10
Shop28.16 sq m · 303 sq ft10
Shop30.97 sq m · 333 sq ft10
Shop39.67 sq m · 427 sq ft10
Shop43.68 sq m · 470 sq ft10
Shop50.36 sq m · 542 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSomnath Kerur And Associates—
EngineerStructus Consultants Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Dhanori

All 2,604 projects in Dhanori · Compare Mst Aspire with another project

Mst Aspire in numbers

Registered deals, summarised

Deedo has 1 registered document at Mst Aspire, from Sep 2025 to Sep 2025: 1 leave and licence agreement.

Are properties at Mst Aspire rented out?
Yes: 1 leave and licence agreement is registered at Mst Aspire.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Mst Aspire by Deedo, last updated with deals registered in Sep 2025.

Latest deal · Rental · Sep 2025

₹20–50k / month

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology