Charoli, Pune

Deedo IDDL-PUN-CHAROLI

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects29
Registrations29
Completion still due263 past their date
Median extension4 months83% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

29 MahaRERA registrations in Charoli

2 not yet due24 extended, not yet due3 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Charoli

29 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Shriram NyraShriram Samruddhi DevelopersDue Dec 2029——
Aarika Towers A And B BuildingsRkl Projects LLPDue Dec 2031——
Montreal F-GCharholi Infrastructure LLPDue Sep 2031, extended 4 mo——
Amrutyog ResidencyDeepchandra Developers Private LimitedDue Apr 2030, extended 4 mo——
Miami-A1-A2-A3-B2Pride Builders LLPDue Apr 2030, extended 4 mo——
All 29 projects →
Charoli market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. D R Gavhane Landmarks Llp2 projects
  2. Pride Builders Llp2 projects
  3. Swastik Buildtech2 projects
  4. Amg Landmark1 project
  5. Balaji Promoters1 project
  6. Bhosale Housing LLP1 project
  7. Charholi Infrastructure Llp1 project
  8. Deepchandra Developers Private Limited1 project
  9. Defense Warrior Properties1 project
  10. Ganesh Satish Patil1 project

Charoli, in questions

How many projects in Charoli run late?

9 in 10 MahaRERA registrations (27 of 29): their completion date was extended or has passed, data through 8 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Charoli by Deedo. Medians on fewer than 3 deeds are not shown.

Data through8 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology