Skip to content
Commercial · 1 building · 76 unitsRERA P52100028706

Parshwa Capital

Deedo IDDP-PUN-W6KJ

MahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 54% of its units are booked.

Charholi, Pune 412105 · by Parshwa Properties · 33% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales54% booked41 of 76 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year

  • This projectRegistered 25 Mar 2021, completion promised 30 Jun 2023, revised to 30 Jun 2024.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100028706
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002870625 Mar 202130 Jun 202330 Jun 2024Parshwa PropertiesProject page
Documents94

3 documents held by Deedo, 91 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPancard_ Parshwa Properties.PDF · uploaded 8 Mar 2021Source

Legal

  • Declaration Form BForm B.pdf · uploaded 8 Mar 2021Source
  • Legal Title reportSearch Title.pdf · uploaded 18 Mar 2021Source
  • Declaration Form BForm B New.pdf · uploaded 8 Jun 2023Source

Migrated

  • 1 PAN CardPancard_ Parshwa Properties.PDF · uploaded 8 Mar 2021Source
Show all 94 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncrumbance.pdf · uploaded 8 Mar 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 8 Mar 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout Approval.pdf · uploaded 8 Mar 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 8 Mar 2021Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 8 Mar 2021Source
  • 1 Proforma of Allotment letterallotment letter.pdf · uploaded 9 Mar 2021Source
  • 2 Proforma of Allotment letterCommercial Agreement to sale.pdf · uploaded 9 Mar 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 12 Mar 2021Source
  • 1 Copy of the legal title reportSearch Title.pdf · uploaded 18 Mar 2021Source
  • 1 Declaration about Commencement CertificateCircular 32.pdf · uploaded 14 Sep 2021Source
  • 1 Disclosure of sold/ booked inventorySold circular RERA -Q-1.pdf · uploaded 14 Sep 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 signed revised.pdf · uploaded 15 Sep 2021Source
  • 2 Copy of Layout Approval (in case of layout)Layout approval.pdf · uploaded 27 Oct 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 27 Oct 2021Source
  • 2 Declaration about Commencement CertificateCircular 32.pdf · uploaded 27 Oct 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 21 Jan 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2_compressed.pdf · uploaded 21 Jan 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 13 Jun 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 13 Jun 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Revised Form 3 compressed.pdf · uploaded 13 Jun 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 final.pdf · uploaded 20 Jul 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 final.pdf · uploaded 20 Jul 2022Source
  • 2 Disclosure of sold/ booked inventorySold Circular Q-1 Capital.pdf · uploaded 20 Jul 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final scanned UPLOAD.pdf · uploaded 20 Jul 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Declaration scanned.pdf · uploaded 26 Jul 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Declaration scanned.pdf · uploaded 26 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Declaration scanned.pdf · uploaded 26 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Declaration scanned.pdf · uploaded 26 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Declaration scanned.pdf · uploaded 26 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Declaration scanned.pdf · uploaded 26 Jul 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Parshwa Capital.pdf · uploaded 13 Oct 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q-2.pdf · uploaded 13 Oct 2022Source
  • 3 Disclosure of sold/ booked inventorySold Circular Q-2_ Capital.pdf · uploaded 13 Oct 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 5 scanned Capital.pdf · uploaded 24 Dec 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1 Architect Certificate _ Capital _ Q-3.pdf · uploaded 16 Jan 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q-3 Capital.pdf · uploaded 16 Jan 2023Source
  • 4 Disclosure of sold/ booked inventorySold Circular- 29 RERA Q-3 _Capital.pdf · uploaded 16 Jan 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 _ CA certificate _ Q-3 _ Capital final.pdf · uploaded 17 Jan 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Scanned by CA.pdf · uploaded 24 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 scanned Capital.pdf · uploaded 24 Jan 2023Source
  • 3 Copy of Layout Approval (in case of layout)HPSC0870 Layout.pdf · uploaded 25 Apr 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentHPSC0871.pdf · uploaded 25 Apr 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentHPSC0872.pdf · uploaded 25 Apr 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentHPSC0873.pdf · uploaded 25 Apr 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentHPSC0874.pdf · uploaded 25 Apr 2023Source
  • 6 Building Plan Approval / NA Order for plotted developmentHPSC0875.pdf · uploaded 25 Apr 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 25 Apr 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 22 May 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 May 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Final_compressed.pdf · uploaded 22 May 2023Source
  • 5 Disclosure of sold/ booked inventorySold circular.pdf · uploaded 23 May 2023Source
  • 2 Declaration in FORM BForm B New.pdf · uploaded 8 Jun 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Parshwa Capital Form 2.pdf · uploaded 29 Jul 2023Source
  • 6 Disclosure of sold/ booked inventorySold Circular.pdf · uploaded 29 Jul 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Parshwa Capital Form 3_compressed.pdf · uploaded 29 Jul 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 capital.pdf · uploaded 2 Aug 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Parshwa Capital_ Form 2_ Engineering Certificate.pdf · uploaded 16 Oct 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Parshwa Capital FINAL.pdf · uploaded 16 Oct 2023Source
  • 7 Disclosure of sold/ booked inventorySOLD CIRCULAR.pdf · uploaded 24 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Capital upload.pdf · uploaded 2 Dec 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 Jan 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Parshwa Capital Q2.pdf · uploaded 25 Jan 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Jan 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA and Promoter Signed.pdf · uploaded 25 Jan 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Apr 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q-4 Capital.pdf · uploaded 22 Apr 2024Source
  • 8 Disclosure of sold/ booked inventorySold inventory Q 4 capital.pdf · uploaded 22 Apr 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 (Q4 23-24).pdf · uploaded 10 May 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentParshwa Capital Completion.pdf · uploaded 10 May 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Architect certificate capital.pdf · uploaded 10 May 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 capital building Q1 upload.pdf · uploaded 20 Jul 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Capital Q 1.pdf · uploaded 20 Jul 2024Source
  • 9 Disclosure of sold/ booked inventorySold Circular- 29 RERA Q-1 (1).pdf · uploaded 20 Jul 2024View
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 upload_compressed.pdf · uploaded 20 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Final.pdf · uploaded 30 Dec 2024Source

Technical

  • DocumentLayout Approval.pdf · uploaded 8 Mar 2021Source
  • DocumentLayout Approval.pdf · uploaded 8 Mar 2021Source
  • DocumentLayout approval.pdf · uploaded 27 Oct 2021Source
  • DocumentHPSC0870 Layout.pdf · uploaded 25 Apr 2023Source
  • DocumentHPSC0871.pdf · uploaded 25 Apr 2023Source
  • DocumentHPSC0872.pdf · uploaded 25 Apr 2023Source
  • DocumentHPSC0873.pdf · uploaded 25 Apr 2023Source
  • DocumentHPSC0874.pdf · uploaded 25 Apr 2023Source
  • DocumentHPSC0875.pdf · uploaded 25 Apr 2023Source

Technical (Architect)

  • DocumentForm 1 capital building Q1 upload.pdf · uploaded 20 Jul 2024Source

Technical (Engineer)

  • DocumentForm 2 Capital Q 1.pdf · uploaded 20 Jul 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 463/2 PART

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Unit types
Multipurpose hall, Office space, Restaurant, Shop76 units in all
Address
Survey No 463/2 Part, Charholi Bk, Charholi BkPIN 412105
Village
Charholi, Haveli taluka
Land area for this project
1,898 sq m (20,434 sq ft)
Permissible built-up area
4,588 sq m (49,382 sq ft)
Sanctioned built-up area
4,588 sq m (49,382 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

SURVEY NO 463/2 PART

Land as published on MahaRERA's project page

SURVEY NO 463/2 PART

Boundaries

North
By Road
South
By Property Of Survey No 462 Hissa No 1
East
By Remaining Property Of Survey No 463 Hissa No 2
West
By Property Of Survey No 464 And Survey No 465

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking76 units

41 of 76 units booked (54%), as the promoter reported to MahaRERA

Multipurpose hall · 1 unitOffice space · 36 unitsRestaurant · 1 unitShop · 38 units
TypeCarpet areaUnitsBooked
Multipurpose hall146.56 sq m · 1,578 sq ft11
Office space16.28 sq m · 175 sq ft22
Office space16.89 sq m · 182 sq ft22
Office space17.21 sq m · 185 sq ft21
Office space22.55 sq m · 243 sq ft62
Office space23.43 sq m · 252 sq ft42
Office space23.91 sq m · 257 sq ft21
Office space24.76 sq m · 267 sq ft20
Show all 46 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Office space24.84 sq m · 267 sq ft41
Office space25.29 sq m · 272 sq ft10
Office space25.31 sq m · 272 sq ft10
Office space26.21 sq m · 282 sq ft10
Office space31.18 sq m · 336 sq ft11
Office space33.53 sq m · 361 sq ft10
Office space33.54 sq m · 361 sq ft44
Office space35.46 sq m · 382 sq ft10
Office space35.48 sq m · 382 sq ft11
Office space39.33 sq m · 423 sq ft10
Restaurant294.32 sq m · 3,168 sq ft10
Shop14.81 sq m · 159 sq ft22
Shop14.95 sq m · 161 sq ft11
Shop15.14 sq m · 163 sq ft11
Shop15.39 sq m · 166 sq ft11
Shop16.27 sq m · 175 sq ft10
Shop21.84 sq m · 235 sq ft10
Shop22.94 sq m · 247 sq ft11
Shop23.11 sq m · 249 sq ft10
Shop23.21 sq m · 250 sq ft10
Shop24.57 sq m · 264 sq ft22
Shop25.53 sq m · 275 sq ft22
Shop25.62 sq m · 276 sq ft10
Shop26.98 sq m · 290 sq ft11
Shop28.02 sq m · 302 sq ft11
Shop28.08 sq m · 302 sq ft11
Shop33.48 sq m · 360 sq ft11
Shop38.01 sq m · 409 sq ft42
Shop38.22 sq m · 411 sq ft11
Shop39.38 sq m · 424 sq ft22
Shop40.21 sq m · 433 sq ft21
Shop40.42 sq m · 435 sq ft10
Shop40.92 sq m · 440 sq ft21
Shop41.69 sq m · 449 sq ft10
Shop41.7 sq m · 449 sq ft11
Shop43.24 sq m · 465 sq ft11
Shop59.86 sq m · 644 sq ft30
Shop63.32 sq m · 682 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectLandmark Design Group—
Chartered accountantCa Vaibhav Modi—
EngineerRahul S Mutha—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology