Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 15 mo late — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay15 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Parshwa Gold County Wing AP52100000180HaveliCertificate Signed30 Oct 202130 Oct 2021On date
Parshwa Gold County Wing BP52100020952CharholiCertificate Signed31 Dec 202130 Jun 2023+18 mo
Parshwa CapitalP52100028706CharholiCertificate Signed30 Jun 202330 Jun 2024+12 mo

Parshwa Properties, in questions

Does Parshwa Properties finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 15 mo late. Across Maharashtra, 73% kept their date.

How many projects has Parshwa Properties registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.

Does Parshwa Properties have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology