Parshwa Properties
Deedo IDDD-Q5MWOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 15 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Parshwa Gold County Wing AP52100000180 | Haveli | Certificate Signed | 30 Oct 2021 | 30 Oct 2021 | On date |
| Parshwa Gold County Wing BP52100020952 | Charholi | Certificate Signed | 31 Dec 2021 | 30 Jun 2023 | +18 mo |
| Parshwa CapitalP52100028706 | Charholi | Certificate Signed | 30 Jun 2023 | 30 Jun 2024 | +12 mo |
Parshwa Properties, in questions
Does Parshwa Properties finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 15 mo late. Across Maharashtra, 73% kept their date.
How many projects has Parshwa Properties registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Parshwa Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.