Skip to content
Residential / Group Housing · 7 buildings · 120 unitsRERA P52100000458

Nithyam

Deedo IDDP-PUN-QHN5

Completion was pushed back 1 year to Mar 2023, and that date has passed too; no MahaRERA orders on record; 92% of its units are booked.

Charholi Kh, Pune 412105 · by G And S Associates · 33% of its projects kept the RERA date

Delivery4 yrs 8 mo latePromised Mar 2022 · revised Mar 2023 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales92% booked110 of 120 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year to Mar 2023, and that date has passed too

  • This projectRegistered 18 Jul 2017, completion promised 30 Mar 2022, revised to 30 Mar 2023, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

7 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100000458
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000045818 Jul 201730 Mar 202230 Mar 2023G And S AssociatesProject page
Documents88

3 documents held by Deedo, 85 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPan Card G AND S.pdf · uploaded 14 Jul 2017Source

Legal

  • Declaration Form BFORM B NITHYAM.pdf · uploaded 14 Jul 2017Source
  • Legal Title reportCharholi Search Report updated.pdf · uploaded 14 Jul 2017Source

Migrated

  • 1 PAN CardPan Card G AND S.pdf · uploaded 14 Jul 2017Source
  • 1 Copy of the legal title reportCharholi Search Report updated.pdf · uploaded 14 Jul 2017Source
Show all 88 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesCertificate - Charoli khurd.pdf · uploaded 14 Jul 2017Source
  • 1 Declaration in FORM BFORM B NITHYAM.pdf · uploaded 14 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE (ARCON FORMAT).pdf · uploaded 14 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Master Plan 1-11.pdf · uploaded 15 Jul 2017Source
  • 1 Building Plan Approval (IOD)A1 A2 1.pdf · uploaded 15 Jul 2017Source
  • 2 Building Plan Approval (IOD)A1 A2 2.pdf · uploaded 15 Jul 2017Source
  • 3 Building Plan Approval (IOD)A3 3.pdf · uploaded 15 Jul 2017Source
  • 4 Building Plan Approval (IOD)A3 4.pdf · uploaded 15 Jul 2017Source
  • 5 Building Plan Approval (IOD)B1 B2 5.pdf · uploaded 15 Jul 2017Source
  • 6 Building Plan Approval (IOD)Club House.pdf · uploaded 15 Jul 2017Source
  • 7 Building Plan Approval (IOD)Front Elevation A1 A2.pdf · uploaded 15 Jul 2017Source
  • 8 Building Plan Approval (IOD)Front Elevation A3.pdf · uploaded 15 Jul 2017Source
  • 9 Building Plan Approval (IOD)Front Elevation B1 And B2.pdf · uploaded 15 Jul 2017Source
  • 10 Building Plan Approval (IOD)Parking Layout.pdf · uploaded 15 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentChallan CC No 117.pdf · uploaded 15 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Nithyam Engg Certificate.pdf · uploaded 15 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA Certificate Nithyam.pdf · uploaded 15 Jul 2017Source
  • 1 Proforma of Allotment letterUnit Agreement Charholi.pdf · uploaded 15 Jul 2017Source
  • 1 Certificates of CA (Form 5)Audit Report.pdf · uploaded 30 Sep 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect compressed.pdf · uploaded 31 Jan 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 ENGINEERS CERTIFICATE Nithyam 31 12 2018.pdf · uploaded 31 Jan 2019Source
  • 2 Certificates of CA (Form 3)CA nithyam.pdf · uploaded 31 Jan 2019Source
  • 2 Proforma of Allotment letterUNIT AGREEMENT DRAFT Nithyam.pdf · uploaded 29 May 2019Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nithyam Phase1 Arc Cer.pdf · uploaded 23 Jul 2019Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nithyam Phase1 Arc Cer.pdf · uploaded 23 Jul 2019Source
  • 3 Proforma of Allotment letterUNIT AGREEMENT DRAFT Nithyam.pdf · uploaded 5 Sep 2019Source
  • 2 Certificates of CA (Form 5)Audit Report_Nithyam.pdf · uploaded 30 Sep 2019Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)040216151203_0001.pdf · uploaded 11 Oct 2019Source
  • 2 Copy of Layout Approval (in case of layout)Layout_compressed.pdf · uploaded 30 Nov 2019Source
  • 11 Building Plan Approval (IOD)A1-Floor Plan (5-6-7) (2).pdf · uploaded 30 Nov 2019Source
  • 12 Building Plan Approval (IOD)B2- Floor Plan (5-7) (2).pdf · uploaded 30 Nov 2019Source
  • 13 Building Plan Approval (IOD)B2-Floor Plan (6)_compressed.pdf · uploaded 30 Nov 2019Source
  • 4 Proforma of Allotment letterUNIT AGREEMENT DRAFT Nithyam _2_.pdf · uploaded 2 Dec 2019Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nithyam_Phase_1.pdf · uploaded 13 Jan 2020Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nithyam RERA PHASE 1.pdf · uploaded 12 Jun 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)UNIT AGREEMENT DRAFT NITHYAM.pdf · uploaded 27 Aug 2020Source
  • 5 Proforma of Allotment letterUNIT AGREEMENT DRAFT NITHYAM.pdf · uploaded 27 Aug 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentMX-M265NV_20200928_180833.pdf · uploaded 28 Sep 2020Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE - PHASE 1.pdf · uploaded 12 Oct 2020Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nithyam_Phase-1.pdf · uploaded 11 Jan 2021Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nithyam Architect Certificate - Phase 1.pdf · uploaded 7 Apr 2021Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)MX-M265NV_20210701_145846.pdf · uploaded 1 Jul 2021Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate - Phase 1 Nithyam.pdf · uploaded 30 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Nithyam Form 5.pdf · uploaded 31 Dec 2021Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nithyam_Phase-1.pdf · uploaded 12 Jan 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Nithyam Form 5 FY 20-21 Complete Set.pdf · uploaded 10 Mar 2022Source
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Phase 1.pdf · uploaded 12 Apr 2022Source
  • 1 Declaration about Commencement CertificateForm D.pdf · uploaded 14 Apr 2022Source
  • 1 Disclosure of sold/ booked inventoryDisclousre.pdf · uploaded 14 Apr 2022View
  • 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 14 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)18-19.pdf · uploaded 16 Apr 2022Source
  • 3 Certificates of CA (Form 5)ca certificate (1).pdf · uploaded 29 Jul 2022Source
  • 4 Certificates of CA (Form 5)Nithyam Phase I- CA cert- Sept'2022.pdf · uploaded 10 Nov 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY FORMATION CERTIFICATE.pdf · uploaded 24 Nov 2022Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engg certificate.pdf · uploaded 17 May 2023Source
  • 1 Other – TechnicalA1 completion certificet.pdf · uploaded 21 Oct 2023Source
  • 2 Other – TechnicalB2 completion certificet.pdf · uploaded 21 Oct 2023Source
  • 3 Other – TechnicalFORM 4 A1, B2.pdf · uploaded 26 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)NITHYAM PHASE I 2022.pdf · uploaded 4 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)NITHYAM PHASE I 2023.pdf · uploaded 4 Mar 2024Source

Technical

  • DocumentA1 A2 1.pdf · uploaded 15 Jul 2017Source
  • DocumentA1 A2 2.pdf · uploaded 15 Jul 2017Source
  • DocumentA3 3.pdf · uploaded 15 Jul 2017Source
  • DocumentA3 4.pdf · uploaded 15 Jul 2017Source
  • DocumentB1 B2 5.pdf · uploaded 15 Jul 2017Source
  • DocumentClub House.pdf · uploaded 15 Jul 2017Source
  • DocumentFront Elevation A1 A2.pdf · uploaded 15 Jul 2017Source
  • DocumentFront Elevation A3.pdf · uploaded 15 Jul 2017Source
  • DocumentMaster Plan 1-11.pdf · uploaded 15 Jul 2017Source
  • DocumentFront Elevation B1 And B2.pdf · uploaded 15 Jul 2017Source
  • DocumentParking Layout.pdf · uploaded 15 Jul 2017Source
  • DocumentLayout_compressed.pdf · uploaded 30 Nov 2019Source
  • DocumentA1-Floor Plan (5-6-7) (2).pdf · uploaded 30 Nov 2019Source
  • DocumentB2- Floor Plan (5-7) (2).pdf · uploaded 30 Nov 2019Source
  • DocumentB2-Floor Plan (6)_compressed.pdf · uploaded 30 Nov 2019Source
  • Other – TechnicalA1 completion certificet.pdf · uploaded 21 Oct 2023Source
  • Other – TechnicalB2 completion certificet.pdf · uploaded 21 Oct 2023Source
  • Other – TechnicalFORM 4 A1, B2.pdf · uploaded 26 Dec 2023Source

Technical (Architect)

  • DocumentArchitect Certificate Phase 1.pdf · uploaded 12 Apr 2022Source

Technical (Engineer)

  • Documentengg certificate.pdf · uploaded 17 May 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 1 2 3 4 5

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop120 units in all
Address
1 2 3 4 5, Gat No. 1 To 5, Charholi KhurdPIN 412105
Village
charholi kh, Khed taluka
Land area for this project
11,100 sq m (1,19,479 sq ft)
Permissible built-up area
11,745 sq m (1,26,418 sq ft)
Sanctioned built-up area
4,586 sq m (49,360 sq ft)
Recreational open space
994 sq m (10,699 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

1 2 3 4 5

Land as published on MahaRERA's project page

1 2 3 4 5

Boundaries

North
Gat No 6
South
Road
East
Gat No 34 To 61
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking120 units

110 of 120 units booked (92%), as the promoter reported to MahaRERA

1BHK · 56 units2BHK · 56 unitsShop · 8 units
BuildingTypeCarpet areaUnitsBooked
A11BHK33.12 sq m · 357 sq ft1312
A11BHK33.19 sq m · 357 sq ft1414
A11BHK33.2 sq m · 357 sq ft11
A12BHK55.19 sq m · 594 sq ft44
A12BHK55.2 sq m · 594 sq ft87
A12BHK55.37 sq m · 596 sq ft88
A12BHK55.38 sq m · 596 sq ft88
A1Shop23.91 sq m · 257 sq ft22
Show all 14 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A1Shop30.12 sq m · 324 sq ft20
A1Shop30.81 sq m · 332 sq ft21
A1Shop33.92 sq m · 365 sq ft22
B21BHK25.15 sq m · 271 sq ft2826
B22BHK43.31 sq m · 466 sq ft2017
B22BHK43.46 sq m · 468 sq ft88

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArcon—
EngineerHansal Parikh & Associates—
OtherSquire 9 Corporation Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Charholi Kh

All 21 projects in Charholi Kh · Compare Nithyam with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology