Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 45 mo late.

Projects34 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay45 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
NithyamP52100000458Charholi KhCertificate Signed30 Mar 202230 Mar 2023+55 mo*
KshithiP52100000607BanerCertificate Signed30 Mar 202230 Mar 2022On date
NithyamP52100020783Charholi KhCertificate Signed30 Dec 202330 Dec 2023+34 mo*
NithyamP52100052791Charholi KhCertificate Signed31 Dec 202731 Dec 2027On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology