Skip to content

Chakan (Ct), Pune

Deedo IDDL-PUN-CHAKAN

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects62
Registrations64some projects hold several
Completion still due2737 past their date
Median extension4 months55% of registrations extended
Regulatory cases1on 2 projects

9 in 10 registrations run late here

64 MahaRERA registrations in Chakan (Ct)

7 not yet due20 extended, not yet due37 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Chakan (Ct)

62 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
The Grand CentralGrow More Buildcon1 yr 11 mo late—70%
Nakoda HeightAmbika DevelopersDue Dec 2028——
Shreeram TradeconShreeram Tradecon2 yrs 8 mo late——
Crown Field Wing BManjare And Mutke AssociatesCompleted—100%
Anand ResidencyMedankar Shevkari AssociatesCompleted—60%
Raj ApoorvamCrystal LandmarkDue Apr 2028, extended 4 mo——
Gulmohar ParkG G Builders And DevelopersCompleted—100%
Kalp HomesDwarkamai EnterprisesCompleted—100%
Creative Ventures ChakanCreative Ventures ChakanDue Dec 2027, extended 6 yrs—21%
Vastu Forest NestVastushilpbuilders & DevelopersCompleted—86%
SpringfieldSwami Samarth Associates7 yrs 11 mo late—63%
Tiara Meadow Phase ITiara HousingCompleted—97%
Phase II - C1, D1 and E1 BuildingsShree Sai Associates6 yrs 11 mo late—86%
Phase IV - K1 and L1 BuildingsShree Sai Associates6 yrs 11 mo late—91%
Prasanna I SquarePrasanna DevelopersCompleted, extended 3 yrs 9 mo—63%
Sejal HomesSaubhari DevelopersCompleted—100%
ShivshaktiAtul Harishchandra YelbharCompleted, extended 4 yrs—39%
shree hari ResidencyArchie Nova Associates7 yrs 11 mo late—85%
sudarshan heightssudarshan propertiesCompleted, extended 1 yr—100%
The UrbanaIntercontinental Infrastructure Limited8 mo late—45%
Unicon BlissShree Vijayalaxmi DevelopersCompleted——
Phase I - Buildings A, A1, P and S, T, U Combined wingShree Sai AssociatesDue Apr 2031, extended 4 mo—80%
Dnyanada City And Dnyanada Commercial CenterBhagwan Narayan PokharkarDue Dec 2027, extended 4 yrs—64%
Siddhi HomesShree Ganesh DevelopersCompleted—84%
Pradnyesh ResidencyM\s Pradnyesh Builders And DevelopersCompleted—100%
Chakan (Ct) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Shree Sai Associates4 projects
  2. Intercontinental Infrastructure Limited3 projects
  3. Ravindra Yamnaji Bhor2 projects
  4. Shree Vijayalaxmi Developers2 projects
  5. Shriram Reality2 projects
  6. Sudarshan Properties2 projects
  7. Xrbia Chakan Developers Private Limited2 projects
  8. Xrbia Chakan Developers Private Limited2 projects
  9. Ambika Developers1 project
  10. Archie Nova Associates1 project

Chakan (Ct), in questions

How many projects in Chakan (Ct) run late?

9 in 10 MahaRERA registrations (57 of 64): their completion date was extended or has passed, data through 29 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Chakan (Ct) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology