Bhor, Pune
5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects58
Registrations59some projects hold several
Completion still due1825 past their date
Median extension4 months47% of registrations extended
Regulatory cases2on 2 projects
Projects in Bhor
58 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Pooja Heavan ParkPooja Developers | P52100013053 | 14 Sep 2017 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| ShreepadSachn Ashok Harnaskar | P52100012094 | 1 Sep 2017 | 27 Jan 2021 | 27 Jan 2021 | Promised date passed | 0 |
| Bougain Villa - Cluster 1Synergy Properties | P52100011902 | 31 Aug 2017 | 31 Dec 2031 | 30 Apr 2032 | Extended 4 mo | 0 |
| Greystone ParkSiddheshwar Construction | P52100010640 | 31 Aug 2017 | 12 Feb 2018 | 12 Feb 2018 | Promised date passed | 0 |
| Madhusudan ApartmentsVastupurti Constructions | P52100010907 | 31 Aug 2017 | 31 Jul 2019 | 31 Jul 2019 | Promised date passed | 0 |
| SnehsparshPushkar Realty | P52100011416 | 31 Aug 2017 | 31 May 2018 | 31 May 2018 | Promised date passed | 0 |
| Casuarina - Cluster C And DSynergy Properties | P52100010452 | 27 Aug 2017 | 1 Dec 2021 | 31 Dec 2028 | Extended 84 mo | 0 |
| Raj Tej Commercial ComplexSangram Anantrao Thopte | P52100010209 | 24 Aug 2017 | 31 Mar 2019 | 30 Sep 2020 | Extended 18 mo | 0 |
| Aapla Ghar Ambegaon Annex Phase IMaple Buildcon | P52100008761 | 19 Aug 2017 | 30 Dec 2023 | 31 Dec 2029 | Extended 72 mo | 0 |
| Bougain Villa - Cluster 3Synergy Properties | P52100009058 | 19 Aug 2017 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Baneswar ParadiseTupe Helude Associates | P52100004273 | 9 Aug 2017 | 30 Dec 2020 | 30 Dec 2020 | Promised date passed | 0 |
| Shreyas Happy HomesShreyas Shelters | P52100004564 | 9 Aug 2017 | 1 Oct 2023 | 1 Oct 2023 | Promised date passed | 0 |
| Swapnalok Township Amenity BuildingSwapnalok Developers | P52100004288 | 9 Aug 2017 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| N 1 PrimaNevara Developers | P52100004062 | 7 Aug 2017 | 8 Nov 2028 | 8 Mar 2029 | Extended 4 mo | 0 |
| Sai Sparsh-A1, A2Jalan Associates | P52100003561 | 5 Aug 2017 | 31 Dec 2018 | 30 Jun 2024 | Extended 66 mo | 0 |
| Swapnalok NagariSwapnalok Developers | P52100001827, P52100017102 | 29 Jul 2017 | 30 Jun 2024 | 30 Jun 2024 | Promised date passed | 0 |
| Happiness Hub - VarveParanjape Schemes (Construction) Ltd | P52100000303 | 15 Jul 2017 | 31 Mar 2020 | 28 Mar 2025 | Extended 60 mo | 0 |
| Bougain Villa - Cluster 2 | P52100011459 | — | — | — | — | 0 |
| Daffodills | P52100004308 | — | — | — | — | 0 |
| Laxmi Damodar Park | P52100014462 | — | — | — | — | 0 |
| P52100080964 | P52100080964 | — | — | — | — | 0 |
| Sacramento Valley | P52100018774 | — | — | — | — | 0 |
| Sahyadri City | P52100013642 | — | — | — | — | 0 |
| Sai SparshA3,A4 | P52100003340 | — | — | — | — | 0 |
| Samarath Farm | P52100003072 | — | — | — | — | 0 |
Nearby: other talukas in Pune
Most active promoters
- Swapnalok Developers6 projects
- Synergy Properties3 projects
- Castle Dream Space2 projects
- Gangotree Homes And Holidays2 projects
- Paranjape Schemes (Construction) Ltd2 projects
- Ananda Senior Living Pvt. Ltd.1 project
- Arvind Sopanrao Mohite1 project
- Dhankawade Square Realtors LLP1 project
- Ds Builders And Developers1 project
- Ishaan Buildcon1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology