8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects465
Registrations472some projects hold several
Completion still due175252 past their date
Median extension4 months38% of registrations extended
Regulatory cases7on 7 projects

8 in 10 registrations run late here

472 MahaRERA registrations in Baramati and the places within it

41 not yet due134 extended, not yet due252 past even the latest date45 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Baramati

465 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
S R Tower Phase 8S R Group Promoter And BuildersDue Jul 2030, extended 4 mo——
Tanai M Building BSurekha Vishnu KumbharDue Jul 2028, extended 4 mo——
Ramraj Residency B BuildingRamchandra Dinkar DevkateDue Apr 2031, extended 4 mo——
Skygreen NestSkygreen Nest LLPDue Dec 2030——
Vrindavan ViharPrafull Dashrath Pawar And AssociatesDue Jan 2028, extended 4 mo——
Samarth HeightsSamarth DevelopersDue Oct 2029, extended 4 mo——
Sujit PrideTanishq Builders And DevelopersDue Jun 2029, extended 4 mo——
Nirvana HomesOakspace RealtyDue Apr 2029, extended 4 mo——
Swapnapurti ParkDS ConstructionDue Apr 2030, extended 4 mo——
Shivnandan CityShivnandan DevelopersDue Apr 2030, extended 4 mo——
Chaitanya ShrushtiChaitanya BuildersDue Jan 2032, extended 4 mo——
Aishwarya TownshipRaj ConstructionDue Feb 2027——
Isha ResidencyK K DevelopersDue Nov 2028, extended 4 mo——
Shriram EliteShriram Builders and DevelopersDue Apr 2031, extended 4 mo——
Adi AnviAdi DevelopersDue Apr 2032, extended 4 mo——
Vrindavan ParkSunrise InfraDue Oct 2028, extended 4 mo——
Devale Paradise Wing C1M.b DevelopersDue Apr 2031, extended 4 mo——
Ikra TowerRk InfraDue Apr 2028, extended 4 mo——
Abhang ParadiseD S ConstructionDue Apr 2031, extended 4 mo——
Krupasindhu ClassicAngaraj Mahadev GaikwadDue Oct 2027, extended 4 mo——
Malgunde IconMalgunde Balgude DevelopersDue Aug 2030, extended 4 mo——
Advik ResidencyDue Mar 2027——
Devgiri ParkUnique DevelopersDue Apr 2028, extended 4 mo——
Deokate Patil’s Park Town Row House C & DDeokate Patil AssociatesDue Apr 2028, extended 4 mo——
Infinity TowerSamarth DevelopersDue Oct 2029, extended 4 mo——
Baramati market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Mehta Builders9 projects
  2. Pratap Laxman Chavan5 projects
  3. Adi Developers4 projects
  4. Jay Nanaso Patil4 projects
  5. Mukti Township Development & Construction Co. Pvt. Ltd4 projects
  6. Sagar Mahadev Kate4 projects
  7. Sanjay Walchand Sanghavi4 projects
  8. S R Group Promoter And Builders4 projects
  9. Rajmata Construction3 projects
  10. R. H. Associates3 projects

Baramati, in questions

How many projects in Baramati run late?

8 in 10 MahaRERA registrations (386 of 472): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Baramati by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology