Deedo IDDL-PUN-BARAMATI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects465
Registrations472some projects hold several
Completion still due175252 past their date
Median extension4 months38% of registrations extended
Regulatory cases7on 7 projects
8 in 10 registrations run late here
472 MahaRERA registrations in Baramati and the places within it
41 not yet due134 extended, not yet due252 past even the latest date45 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Baramati
465 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| S R Tower Phase 8S R Group Promoter And Builders | Due Jul 2030, extended 4 mo | — | — |
| Tanai M Building BSurekha Vishnu Kumbhar | Due Jul 2028, extended 4 mo | — | — |
| Ramraj Residency B BuildingRamchandra Dinkar Devkate | Due Apr 2031, extended 4 mo | — | — |
| Skygreen NestSkygreen Nest LLP | Due Dec 2030 | — | — |
| Vrindavan ViharPrafull Dashrath Pawar And Associates | Due Jan 2028, extended 4 mo | — | — |
| Samarth HeightsSamarth Developers | Due Oct 2029, extended 4 mo | — | — |
| Sujit PrideTanishq Builders And Developers | Due Jun 2029, extended 4 mo | — | — |
| Nirvana HomesOakspace Realty | Due Apr 2029, extended 4 mo | — | — |
| Swapnapurti ParkDS Construction | Due Apr 2030, extended 4 mo | — | — |
| Shivnandan CityShivnandan Developers | Due Apr 2030, extended 4 mo | — | — |
| Chaitanya ShrushtiChaitanya Builders | Due Jan 2032, extended 4 mo | — | — |
| Aishwarya TownshipRaj Construction | Due Feb 2027 | — | — |
| Isha ResidencyK K Developers | Due Nov 2028, extended 4 mo | — | — |
| Shriram EliteShriram Builders and Developers | Due Apr 2031, extended 4 mo | — | — |
| Adi AnviAdi Developers | Due Apr 2032, extended 4 mo | — | — |
| Vrindavan ParkSunrise Infra | Due Oct 2028, extended 4 mo | — | — |
| Devale Paradise Wing C1M.b Developers | Due Apr 2031, extended 4 mo | — | — |
| Ikra TowerRk Infra | Due Apr 2028, extended 4 mo | — | — |
| Abhang ParadiseD S Construction | Due Apr 2031, extended 4 mo | — | — |
| Krupasindhu ClassicAngaraj Mahadev Gaikwad | Due Oct 2027, extended 4 mo | — | — |
| Malgunde IconMalgunde Balgude Developers | Due Aug 2030, extended 4 mo | — | — |
| Advik Residency | Due Mar 2027 | — | — |
| Devgiri ParkUnique Developers | Due Apr 2028, extended 4 mo | — | — |
| Deokate Patil’s Park Town Row House C & DDeokate Patil Associates | Due Apr 2028, extended 4 mo | — | — |
| Infinity TowerSamarth Developers | Due Oct 2029, extended 4 mo | — | — |
Nearby: other talukas in Pune
Most active promoters
- Mehta Builders9 projects
- Pratap Laxman Chavan5 projects
- Adi Developers4 projects
- Jay Nanaso Patil4 projects
- Mukti Township Development & Construction Co. Pvt. Ltd4 projects
- Sagar Mahadev Kate4 projects
- Sanjay Walchand Sanghavi4 projects
- S R Group Promoter And Builders4 projects
- Rajmata Construction3 projects
- R. H. Associates3 projects
Baramati, in questions
How many projects in Baramati run late?
8 in 10 MahaRERA registrations (386 of 472): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Baramati by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology