Teerth Technospace
Completion date passedBaner, Pune 411045 |Promoter: Teerth Developers And Teerth Realties Jv
Project summary
As registered with MahaRERA
- RERA registrations
- 11
- Phases
- 11
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
P52100004739The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 9 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100004940The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 9 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100004297The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 9 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100005717The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 11 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Show 7 more registrations
Completion pushed back 1 year
P52100005429The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 11 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100005488The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 11 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100006190The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 14 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100006740The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 16 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100007204The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 17 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100007620The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 17 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
Completion pushed back 1 year
P52100011100The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 31 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
11 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100004739 | 9 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100004940 | 9 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100004297 | 9 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100005717 | 11 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100005429 | 11 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100005488 | 11 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100006190 | 14 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100006740 | 16 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100007204 | 17 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100007620 | 17 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
| P52100011100 | 31 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Teerth Developers And Teerth Realties Jv | Project page |
Documents
22 documents held by Deedo
Registration certificates
- Registration certificateP52100004739 · 9 Aug 2017ViewSource
- Registration certificateP52100004940 · 9 Aug 2017ViewSource
- Registration certificateP52100004297 · 9 Aug 2017ViewSource
- Registration certificateP52100005429 · 11 Aug 2017ViewSource
- Registration certificateP52100005717 · 11 Aug 2017ViewSource
- Registration certificateP52100005488 · 11 Aug 2017ViewSource
- Registration certificateP52100006190 · 14 Aug 2017ViewSource
- Registration certificateP52100006740 · 16 Aug 2017ViewSource
- Registration certificateP52100007204 · 17 Aug 2017ViewSource
- Registration certificateP52100007620 · 17 Aug 2017ViewSource
- Registration certificateP52100011100 · 31 Aug 2017ViewSource
Extension certificates
- Extension certificateP52100006190 · 4 Jan 2019ViewSource
- Extension certificateP52100005488 · 4 Jan 2019ViewSource
- Extension certificateP52100011100 · 23 Jan 2019ViewSource
- Extension certificateP52100004739 · 23 Jan 2019ViewSource
- Extension certificateP52100004940 · 23 Jan 2019ViewSource
- Extension certificateP52100004297 · 23 Jan 2019ViewSource
- Extension certificateP52100006740 · 23 Jan 2019ViewSource
- Extension certificateP52100007204 · 23 Jan 2019ViewSource
- Extension certificateP52100005429 · 25 Jan 2019ViewSource
- Extension certificateP52100005717 · 25 Jan 2019ViewSource
- Extension certificateP52100007620 · 25 Jan 2019ViewSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Baner
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.