Teerth Developers And Teerth Realties Jv
Deedo IDDD-HFVJOf 15 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
15 of 15 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 15 registrations
15 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Teerth TechnospaceP52100004297 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth Technospac 10P52100004312 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100004739 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100004940 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100005429 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100005488 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100005717 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100006190 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100006740 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100007204 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100007620 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth TechnospaceP52100011100 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth Technospace 5P52100011316 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth Technospace 4P52100011403 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Teerth Technospace 2P52100012046 | Baner | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
Show all 15 registrationsShow fewer
Teerth Developers And Teerth Realties Jv, in questions
Does Teerth Developers And Teerth Realties Jv finish projects on time?
Of 15 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Teerth Developers And Teerth Realties Jv registered with MahaRERA?
5 projects under 15 MahaRERA registrations; 15 completed on MahaRERA.
Does Teerth Developers And Teerth Realties Jv have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.