Estique Phase I
Deedo IDDP-PUN-AQQRMahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 100% of its units are booked.
Baner, Pune 411045 · Property rates in Baner · by Khandve Patil Constructions · 0% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 1 year
- This projectRegistered 4 Aug 2017, completion promised 31 Dec 2018, revised to 31 Dec 2019.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100002751
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100002751 | 4 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Khandve Patil Constructions | Project page |
Documents26
2 documents held by Deedo, 24 filings listed on MahaRERA's project page
Finance
- PAN CardKHANDVE PATIL CONSTRUCTIONS_PAN.pdf · uploaded 26 Jul 2017Source
Legal
Show all 26 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)PLAN 02.pdf · uploaded 26 Jul 2017Source
- 1 Building Plan Approval (IOD)PLAN 01.pdf · uploaded 26 Jul 2017Source
- 1 Certificates of CA (Form 5)KPC FORM 3 RERA.pdf · uploaded 26 Jul 2017Source
- 1 Copy of the legal title reportTITLE SEARCH_KHANDVE PATIL_ESTIQUE_BANER.pdf · uploaded 27 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates_ESTIQUE.pdf · uploaded 27 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE 01_KHANDVE PATIL_ESTIQUE_BANER.pdf · uploaded 27 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CERTIFICATE 02_KHANDVE PATIL_ESTIQUE-BANER.pdf · uploaded 27 Jul 2017Source
- 1 Certificates of CA (Form 3)CA FORM 3 RERA.pdf · uploaded 27 Jul 2017Source
- 1 Proforma of Allotment letterESTIQUE_DRAFT D.pdf · uploaded 27 Jul 2017Source
- 2 Certificates of CA (Form 5)01_FORM 05_13-OCT-2018.pdf · uploaded 13 Oct 2018Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC - PART 1.pdf · uploaded 25 Oct 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)QUALITY ENGG 19-20.pdf · uploaded 18 Nov 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)QUALITY ENGG 20-21.pdf · uploaded 18 Nov 2021Source
- 1 Architect’s Certificate on Completion of Project (Form 4)ARCH FORM 04 - PHASE I.pdf · uploaded 18 Nov 2021Source
Technical
Technical (Architect)
- DocumentARCHITECT CERTIFICATE 01_KHANDVE PATIL_ESTIQUE_BANER.pdf · uploaded 27 Jul 2017Source
Technical (Engineer)
- DocumentENGINEERS CERTIFICATE 02_KHANDVE PATIL_ESTIQUE-BANER.pdf · uploaded 27 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 127 H.NO. 4, 2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2 BHK12 units in all
- Address
- 127 H.no. 4 And 5, 2PIN 411045
- Village
- Baner, Haveli taluka
- Location
- 18.56588, 73.77978
- Land area for this project
- 900 sq m (9,688 sq ft)
- Permissible built-up area
- 791 sq m (8,519 sq ft)
- Sanctioned built-up area
- 593 sq m (6,388 sq ft)
- Designated bank account
- 35
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
127 H.NO. 4 AND 5 , 2
Boundaries
- North
- Adj S No 127 Part
- South
- Adj S No 127 Part
- East
- S No 131 Part
- West
- S No 131 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking12 units
12 of 12 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 50.72 sq m · 546 sq ft | 4 | 4 |
| 2 BHK | 50.72 sq m · 546 sq ft | 8 | 8 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Walhekar & Associates | — |
| Other | Ca Sanket Vaidya | — |
| Other | Pushpa Constructions | — |
Source: MahaRERA project page. Contact details are not shown.