Khandve Patil Constructions

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Estique Phase IP52100002751Baner2017Not reported31 Dec 201831 Dec 2019+12 months
Estique Phase IIP52100017913Baner2018Not reported31 Dec 2019—On date
Estique B WingP52100032999Baner2022Not reported31 Dec 202330 Jun 2024+6 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Estique Phase I+12 mo
  • Estique Phase IIOn date
  • Estique B Wing+6 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Estique Phase I (P52100002751).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology