RERA projects in Andgaon
1 project under 1 MahaRERA registration, registered 2026–2026. 100% have a completion date extended beyond the one promised.
Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2026 | 1 |
Projects in Andgaon
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aqua ViePavan Hooja, Veena Hooja, Varun Hooja, Sanat Hooja | PM1260002601298 | 24 Jul 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
Other localities in Mulshi
Most active promoters
By projects registered here, as named on MahaRERA.
- Pavan Hooja, Veena Hooja, Varun Hooja, Sanat Hooja1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology