8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,568
Registrations1,648some projects hold several
Completion still due826669 past their date
Median extension4 months61% of registrations extended
Regulatory cases24on 22 projects

8 in 10 registrations run late here

1,648 MahaRERA registrations in Vasai and the places within it

189 not yet due637 extended, not yet due669 past even the latest date153 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Vasai

1,568 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Abdul Hakeem Heights A WingYash LifespacesDue Jul 2029, extended 4 mo——
Classic Nanda DeepSethi DevelopersDue Apr 2031, extended 4 mo——
New NalandaComfort Infrastructure & Developers Private LimitedDue Apr 2031, extended 4 mo——
Atharva GokulAtharva DevelopersDue Oct 2030, extended 4 mo——
Manas OmkarManas Omkar Developers LLPDue Apr 2031, extended 4 mo——
Harmony GrandShree Siddhivinayak Builders And DevelopersDue Apr 2030, extended 4 mo——
Makwana ResidencyJitendra Prabhudas MakwanaDue Apr 2031, extended 4 mo——
Phoenix SereniaPhoenix RealtyDue Apr 2030, extended 4 mo——
Mohak Garden City (Elysian)VMS EnterprisesDue Sep 2031, extended 4 mo——
Rudra ResidencyAadiraj IndustriesDue Apr 2030, extended 4 mo——
Vartak TowerG.r.s. Group Builders & DevelopersDue Apr 2029, extended 4 mo——
Krishna NiwasRajlaxmi RedevelopersDue Aug 2029, extended 4 mo——
Gokul Nakshatra IIJsb Homemakers Private LimitedDue Apr 2030, extended 4 mo——
Viva AnantDeepak Harishchandra ThakurDue Apr 2033, extended 4 mo——
Sunteck Beach Residences - Tower A4Sunteck Real Estates Private LimitedDue Apr 2035, extended 4 mo——
AstoriaAlmighty HomesDue Nov 2028, extended 4 mo——
Taqwa HeightsHaleema DevelopersDue Nov 2028, extended 4 mo——
Lotus HarmonyShree Ekveera ConstructionDue Jul 2031, extended 4 mo——
AvanindraOjas VenturesDue Aug 2029, extended 4 mo——
Macchimar SocietyMacchimar Seva Sahakari Housing Society Limited VirarDue Jul 2029, extended 4 mo——
Sunteck Beach Residences - Tower A8Sunteck Real Estates Private LimitedDue Apr 2035, extended 4 mo——
Galaxy Garden - IIAsian Builders and DevelopersDue Jul 2031, extended 4 mo——
The CurveAbhinav Realty Spaces LLPDue Oct 2031, extended 4 mo——
Seabreeze Phase 1Dvnm Ventures LLPDue Apr 2030, extended 4 mo——
Ruturaj GardenRuturaj SquaresDue Apr 2033, extended 4 mo——
Vasai market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Jsb Homemakers Private Limited9 projects
  2. Shantee Housing8 projects
  3. Shantee Homes Realty Llp6 projects
  4. Shantee Realty And Life Space6 projects
  5. Sunteck Realty Limited6 projects
  6. Viva Winner Venture Relators Llp6 projects
  7. Ameya Builders & Property Developers5 projects
  8. Kawali Builders5 projects
  9. Sanskruti Builder & Developer5 projects
  10. Shree Mahavir Builders And Developers5 projects

Vasai, in questions

How many projects in Vasai run late?

8 in 10 MahaRERA registrations (1,306 of 1,648): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Vasai by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology