Agami Infinity Park
Completion due Apr 2028Khairepada, Palghar 401501 |Promoter: Mayuresh Realty Private Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 1
Location
Coordinates as published by MahaRERA
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
P99000024826The latest completion date on record passed 1 year and 7 months ago.
- Registered
- 9 Mar 2020
- Promised
- 30 Mar 2024
- Revised
- 30 Mar 2025
Completion promised for 30 Apr 2028
P99000027009- Registered
- 10 Nov 2020
- Promised
- 30 Apr 2028
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000024826 | 9 Mar 2020 | 30 Mar 2024 | 30 Mar 2025 | Mayuresh Realty Private Limited | Project page |
| P99000027009 | 10 Nov 2020 | 30 Apr 2028 | — | Mayuresh Realty Private Limited | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.