Company or firm · first RERA registration 2020
Mayuresh Realty Private Limited
Deedo IDDD-J01NOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late.
Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Agami Infinity ParkDeregistered: MAYURESH REALTY PRIVATE LIMITED | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Agami Infinity ParkP99000024826 | Khairepada | Certificate Signed | 30 Mar 2024 | 30 Mar 2025 | +32 mo* |
| Agami Infinity ParkP99000027009 | Khairepada | Certificate Signed | 30 Apr 2028 | 30 Aug 2028 | +4 mo |
Mayuresh Realty Private Limited, in questions
Does Mayuresh Realty Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Mayuresh Realty Private Limited registered with MahaRERA?
1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Mayuresh Realty Private Limited have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology