Projects compared side by side
Khairepada · Palghar
Registration
RERA numbers
PromoterMayuresh Realty Private Limited
Status on MahaRERACertificate Signed
Registered on9 Mar 2020
Delivery
Promised completion30 Apr 2028
Revised completion30 Aug 2028
Delay vs RERA date+4 monthsrevised completion date
Extension certificates1
Size
Project land area—
Buildings on record10
Units464
Units booked5512% of units
Regulatory
MahaRERA cases0
Documents on file3
Last checked on MahaRERA21 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology