Completion was pushed back 4 years, to Dec 2028; no MahaRERA orders on record; 0% of its units are booked.

Dhansar, Palghar 401404 · by Nice Realty

DeliveryExtended 4 yrsPromised Dec 2024 · now due Dec 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 45 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 years, to Dec 2028

  • This projectRegistered 24 May 2022, completion promised 31 Dec 2024, revised to 31 Dec 2028.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000045519
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900004551924 May 202231 Dec 202431 Dec 2028Nice RealtyProject page
Documents57

2 documents held by Deedo, 55 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN-NICE REALTY.pdf · uploaded 12 May 2022Source

Legal

  • Legal Title reportCopy of the legal title report.pdf · uploaded 12 May 2022Source
  • Declaration Form BAFFIDAVIT CUM DECLARATION.pdf · uploaded 12 May 2022Source
  • Declaration Form BAFFIDAVIT.pdf · uploaded 8 Feb 2025Source
  • Declaration Form BfORM-b.pdf · uploaded 3 Apr 2025Source

Migrated

  • 1 PAN CardPAN-NICE REALTY.pdf · uploaded 12 May 2022Source
Show all 57 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportCopy of the legal title report.pdf · uploaded 12 May 2022Source
  • 1 Details of encumbrancesENCUMBRANCES.pdf · uploaded 12 May 2022Source
  • 1 Copy of Layout Approval (in case of layout)Copy of Layout Approval.pdf · uploaded 12 May 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval.pdf · uploaded 12 May 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentNA ORDER.pdf · uploaded 12 May 2022Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 12 May 2022Source
  • 1 Declaration in FORM BAFFIDAVIT CUM DECLARATION.pdf · uploaded 12 May 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 (1).pdf · uploaded 12 May 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE.pdf · uploaded 12 May 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200237125318_For_Asset_Based_Search_11_05_2022_15_33_55_985 (1).pdf · uploaded 12 May 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE (1).pdf · uploaded 12 May 2022Source
  • 1 Proforma of Allotment letterAGREEMENT FOR SALE -AADARSH SAROVAR.pdf · uploaded 12 May 2022Source
  • 2 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 18 May 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE .pdf · uploaded 6 Jul 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE .pdf · uploaded 6 Jul 2024Source
  • 1 Disclosure of sold/ booked inventoryDocScanner 29 Jun 2024 5-12 pm.pdf · uploaded 6 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form-2A 2022-23.pdf · uploaded 16 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf · uploaded 16 Jul 2024Source
  • 1 Declaration in FORM BAFFIDAVIT.pdf · uploaded 8 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 8 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 8 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD BOOKED INVENTORY.pdf · uploaded 8 Feb 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)BANK ACCOUNT DECLARATION.pdf · uploaded 8 Feb 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST DECLARATION.pdf · uploaded 8 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A.pdf · uploaded 8 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 (4)_compressed.pdf · uploaded 16 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form-5 Fy 2022-23.pdf · uploaded 16 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 fy 2023-24.pdf · uploaded 16 Feb 2025Source
  • 1 Declaration in FORM BfORM-b.pdf · uploaded 3 Apr 2025Source
  • 1 Other – TechnicalPERT AADARSH.pdf · uploaded 3 Apr 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 2 Dec 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 2 Dec 2025Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 2 Dec 2025Source
  • Withdrawal Update Form 1FORM - 1.pdf · uploaded 27 Mar 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 27 Mar 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 27 Mar 2026Source
  • Withdrawal Update Form 1FORM-1 MARCH 2026 (4).pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2FORM-2 MARCH 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3FORM-3 MARCH 2026 (3)_compressed.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1Form-1 June 2026 (2).pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 2Form-2 June 2026 (3).pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 3Form-3 June 2026 (4)_compressed.pdf · uploaded 12 Aug 2026Source

Technical

  • DocumentCopy of Layout Approval.pdf · uploaded 12 May 2022Source
  • DocumentBuilding Plan Approval.pdf · uploaded 12 May 2022Source
  • Other – TechnicalPERT AADARSH.pdf · uploaded 3 Apr 2025Source

Technical (Architect)

  • DocumentFORM 1.pdf · uploaded 8 Feb 2025Source
  • DocumentForm-1 June 2026 (2).pdf · uploaded 12 Aug 2026Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 8 Feb 2025Source
  • DocumentForm-2 June 2026 (3).pdf · uploaded 12 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 300/1 at Palghar

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—45 units in all
Address
300/1, New Satpati Road, DhansaarPIN 401404
Village
Dhansar, Palghar taluka
Land area for this project
769 sq m (8,273 sq ft)
Permissible built-up area
1,710 sq m (18,407 sq ft)
Sanctioned built-up area
1,710 sq m (18,407 sq ft)
Recreational open space
77 sq m (832 sq ft)
Designated bank account
190
Developed in phases
No

Survey, CTS, gat or plot numbers

300/1 at Palghar

Land as published on MahaRERA's project page

300/1

Boundaries

North
Gut No 300
South
Gut No 299
East
Gut No 304
West
Village Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking45 units

45 units registered

— · 45 units
TypeCarpet areaUnits
——45

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPranav Deshmukh—
Chartered accountantV G Kothari And Co—
Chartered accountantVvk & Co.—
EngineerVishvas S Shah—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Dhansar

All 30 projects in Dhansar · Compare Aadarsh Sarovar Wing-A with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology