RERA projects in Wadi

11 projects under 12 MahaRERA registrations, registered 2017–2026. 17% have a completion date extended beyond the one promised.

11RERA projects
12Registrationssome projects hold several
6Completion still due6 past their completion date, 4 marked completed
60 monthsMedian extension beyond promised date17% of registrations extended
1Regulatory caseson 1 project
7Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20183
20190
20201
20210
20220
20231
20242
20250
20263

Projects in Wadi

11 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Ayodhya ResidencySanjay Namdeorao RagitPM119000260084618 Jun 202631 Jan 2031—Not yet due0
Shiv NagariFortune RealtorsPP1190002600554, PP119000260064027 May 202631 Mar 2028—Not yet due0
SamruddhiTapasya Devcon LLPP505000772732 Aug 202431 Mar 2028—Not yet due0
Omnira HeightsOmnira AssociatesP5050005576716 Apr 202431 Dec 2027—Not yet due0
Lotus EnclaveM/S. Empower InfrastructureP5050004870913 Jan 202331 Dec 2024—Promised date passed1
Royal ParkSamrat BuildconP505000247622 Mar 202028 Nov 2023—Promised date passed0
Sanskruti ApartmentSuryabhan Natthuji SambareP5050001862922 Nov 201827 Dec 2022—Completed0
Poorva HeightsAnand Ravindra Palandurkar & Amol Ravindra PalandurkarP5050001722223 Jul 201831 Dec 201930 Nov 2026Extended 83 mo0
Namdeowadi-1Laxmi Bhagwan KshirsagarP505000155508 Mar 201830 Mar 2022—Completed0
Sankalp EnclaveM/S. N.k. AssociatesP505000126587 Sep 201731 Mar 2019—Completed0
Vasant MaltiDnyaneshwar Shankarrao GawandeP5050001072631 Aug 201726 Feb 201830 Mar 2021Completed0

Other localities in Nagpur (Rural)

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Anand Ravindra Palandurkar & Amol Ravindra Palandurkar1 project
  2. Dnyaneshwar Shankarrao Gawande1 project
  3. Fortune Realtors1 project
  4. Laxmi Bhagwan Kshirsagar1 project
  5. M/S. Empower Infrastructure1 project
  6. M/S. N.k. Associates1 project
  7. Omnira Associates1 project
  8. Samrat Buildcon1 project
  9. Sanjay Namdeorao Ragit1 project
  10. Suryabhan Natthuji Sambare1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology