Vyahad, Nagpur
10 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects2
Registrations2
Completion still due20 past their date
Median extension4 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Vyahad
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shiv NagarJiyalal Sharnagat, Dilip Kawale, Daliram Sharnagat, Sampatiprasad Patle | P50500056435 | 31 May 2024 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Suyog NagarShri. Jiyalal U. Sharnagat, Shri. Dilip P. Kawale, Shri. Daliram U. Sharnagat | P50500056376 | 31 May 2024 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
Nearby: other localities in Nagpur (Rural)
Most active promoters
- Jiyalal Sharnagat, Dilip Kawale, Daliram Sharnagat, Sampatiprasad Patle1 project
- Shri. Jiyalal U. Sharnagat, Shri. Dilip P. Kawale, Shri. Daliram U. Sharnagat1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology