Mohagaon Kh., Nagpur
5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects4
Registrations4
Completion still due40 past their date
Median extension4 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Mohagaon Kh.
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Ayodhya Nagri-IIShraddha Infra | PP1190002502939 | 18 Mar 2026 | 10 Feb 2030 | 10 Jun 2030 | Extended 4 mo | 0 |
| Mauli Town-23Kirtisagar Realty | P50500076899 | 9 Jul 2024 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Mauli Town-24Mauli Infra | P50500066531 | 11 Jun 2024 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Gulsons EstateSantosh Kumar Narayan Bopche | P50500051793 | 3 Jul 2023 | 31 Aug 2027 | 31 Dec 2027 | Extended 4 mo | 0 |
Nearby: other localities in Nagpur (Rural)
Most active promoters
- Kirtisagar Realty1 project
- Mauli Infra1 project
- Santosh Kumar Narayan Bopche1 project
- Shraddha Infra1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology