6 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects7
Registrations7
Completion still due61 past their date
Median extension4 months57% of registrations extended
Regulatory cases0none on MahaRERA's lists
Kalamana market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

7 in 10 registrations run late here

7 MahaRERA registrations in Kalamana

2 not yet due4 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Kalamana

7 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sai Nagri 21Saidham Builders and InfratechDue Oct 2031——
Pp1190002502511Vyankatesha Builders And DevelopersDue Mar 2031——
Sai Nagri 13Saidham Builders and InfratechDue May 2031, extended 4 mo——
Techops Park 2Techops Infrastructure Pvt. Ltd.Due Apr 2030, extended 4 mo——
Anant EnclaveAjay Anantrao BhureDue Jul 2028, extended 4 mo——
Techops ParkSunrise Dreamland Pvt LtdDue Apr 2028, extended 4 mo——
Vyankatesh City 4Vyankatesha Builders And Developers3 yrs 3 mo late—55%

Most active promoters

  1. Saidham Builders and Infratech2 projects
  2. Vyankatesha Builders And Developers2 projects
  3. Ajay Anantrao Bhure1 project
  4. Sunrise Dreamland Pvt Ltd1 project
  5. Techops Infrastructure Pvt. Ltd.1 project
Data through28 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology