Kalamana, Nagpur
Deedo IDDL-NGP-KALAMANA6 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects7
Registrations7
Completion still due61 past their date
Median extension4 months57% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
7 MahaRERA registrations in Kalamana
2 not yet due4 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Kalamana
7 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sai Nagri 21Saidham Builders and Infratech | Due Oct 2031 | — | — |
| Pp1190002502511Vyankatesha Builders And Developers | Due Mar 2031 | — | — |
| Sai Nagri 13Saidham Builders and Infratech | Due May 2031, extended 4 mo | — | — |
| Techops Park 2Techops Infrastructure Pvt. Ltd. | Due Apr 2030, extended 4 mo | — | — |
| Anant EnclaveAjay Anantrao Bhure | Due Jul 2028, extended 4 mo | — | — |
| Techops ParkSunrise Dreamland Pvt Ltd | Due Apr 2028, extended 4 mo | — | — |
| Vyankatesh City 4Vyankatesha Builders And Developers | 3 yrs 3 mo late | — | 55% |
Nearby: other localities in Nagpur (Rural)
Most active promoters
- Saidham Builders and Infratech2 projects
- Vyankatesha Builders And Developers2 projects
- Ajay Anantrao Bhure1 project
- Sunrise Dreamland Pvt Ltd1 project
- Techops Infrastructure Pvt. Ltd.1 project
Data through28 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology