Fetari, Nagpur
4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects5
Registrations5
Completion still due23 past their date
Median extension4 months40% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Fetari
5 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Anuj Nagri 2Kishor Nimbaji Akhand | PP1190002600467 | 19 May 2026 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Anuj NagriKishor Nimbaji Akhand | P50500080572 | 16 Jun 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Bharat Heritage Fetri 96/BBharat Heritage | P50500033331 | 16 Feb 2022 | 13 Jan 2026 | 13 Jan 2026 | Promised date passed | 0 |
| Premier NagarMayur Hemchand Shah | P50500020935 | 23 May 2019 | 30 Oct 2023 | 30 Oct 2023 | Promised date passed | 0 |
| Millennium ResidencyRakesh Babulal Patni | P50500009893 | 22 Aug 2017 | 5 Mar 2023 | 5 Mar 2023 | Promised date passed | 0 |
Nearby: other localities in Nagpur (Rural)
Most active promoters
- Kishor Nimbaji Akhand2 projects
- Bharat Heritage1 project
- Mayur Hemchand Shah1 project
- Rakesh Babulal Patni1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology