Adyali, Nagpur
3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects3
Registrations3
Completion still due12 past their date
Median extension4 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Adyali
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Yash Colony 2Yashom Builders & Developers Pvt. Ltd. | P50500046540 | 10 Aug 2022 | 31 May 2027 | 30 Sep 2027 | Extended 4 mo | 0 |
| Yash Colony-1Kishor Shivajirao Chopde | P50500030401 | 20 Aug 2021 | 10 Jun 2024 | 10 Jun 2024 | Promised date passed | 0 |
| Yash ColonyKishor Shivajirao Chopde | P50500024479 | 18 Feb 2020 | 30 Dec 2023 | 30 Dec 2023 | Promised date passed | 0 |
Nearby: other localities in Nagpur (Rural)
Most active promoters
- Kishor Shivajirao Chopde2 projects
- Yashom Builders & Developers Pvt. Ltd.1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology