Kurar, Mumbai Suburban

Deedo IDDL-MSB-KURAR

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects14
Registrations16some projects hold several
Completion still due133 past their date
Median extension4 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

16 MahaRERA registrations in Kurar

2 not yet due11 extended, not yet due3 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Kurar

14 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Jaliyan Grand TownshipShree Jaliyan Realty Venture LLPDue Apr 2032, extended 4 mo——
Lk AuraL K Infracon LLPDue Jan 2030, extended 4 mo——
Ventara HeightsShree Jaliyan Realty Venture LLPDue Apr 2030, extended 4 mo——
Mauli Pride 1 BcdeMauli Sai Developers Pvt LtdDue Apr 2029, extended 4 mo——
Shree Ashish Apartment Co-Operative Housing Society LimitedOm Sai Developers & PromotersDue Oct 2030, extended 4 mo——
All 14 projects →
Kurar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. L K Infracon Llp3 projects
  2. D.G.S Township Private Limited2 projects
  3. Shree Jaliyan Realty Venture LLP2 projects
  4. Brijwasi Builders1 project
  5. Chinnapan Swamy Anthony1 project
  6. Mauli Sai Developers Pvt Ltd1 project
  7. M Construction Company1 project
  8. Om Sai Developers & Promoters1 project
  9. Pritesh Damji Savla1 project
  10. Sarjivan Bldg No 2 Coop Hsg Soc Limited1 project

Kurar, in questions

How many projects in Kurar run late?

9 in 10 MahaRERA registrations (14 of 16): their completion date was extended or has passed, data through 5 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kurar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology